Calculate New Depreciation Rate For Existing Asset
Apr 4, 2014
I am looking to reassess the useful life of existing fixed assets by one/two years.
For example:-
Original cost $1,727.00
Start Date 30/12/2008
Current End of life 29/12/2013
New End of Life date 29/12/2014
5 year - 20%
NBV as at 30/06/2013 $174.12
How can I calculate the new rate, as I can not change the prior financial years depreciation. I am looking for a calculation, to test the assumptions, and see the overall change. This is just one example.
View 1 Replies
ADVERTISEMENT
Jan 25, 2010
I am working on a depreciation schedule in which I want the monthly depreciation of an asset to automatically calculate and, if the asset is fully depreciation, caclulate a zero or the balance to be depreciation (if less than the monthly depreciation). Please see below example. As you can see my asset is fully depreciated at the end of February but because there remains a $0.01, the formula is calculating another month in March and then reversing it in April (less the $0.01). Here's the formula I'm using. What am I doing wrong?
Column H is March, Column C is my monthly depreciation, and column E is my beginning book value:
=-IF(ABS(SUM($F2:H2))>=$E2,(SUM($F2:H2)+$E2),IF($E2=$C2,$C2,$E2)))
Purchase
PriceMonthly DepreciationAccumulated Depreciation 12/31/20091/1/2010 Beginning Book ValueJan-10Feb-10Mar-10Apr-10May-10
LCD PROJECTOR 797.12 13.29 (770.54) 26.58 (13.29) (13.29) (13.29) 13.28 -
View 9 Replies
View Related
Mar 20, 2009
I'm trying to calculate the Depreciation of the fixed asset for some items. I've tried the formulas that came with Excel but i don't know its not working or not give the correct value
so I attached a file as an example what I'm trying to have is
1- straight line method along the asset life
2- salvage must be ( 1 )
3- if the purchase date is equal to or before the middle of the month (14-15/02/2004) so the start of depreciation have to start from the beginning of the current month ( Feb) but if the date excess the day 15 ( 16/02/2004) the middle of the month , the the depreciation must start from the next month.
View 8 Replies
View Related
May 15, 2014
I am trying to figure out a formula to calculate remaining useful life. I have the following information:
In Service Date (Cell W2)
Estimated Life (Cell X2)
Aquired Value (Cell Z2)
Is there a formula that will just calculate how much life is left based on the information i have?
View 4 Replies
View Related
Feb 13, 2014
From a chart in Excel I need to automatically calculate what the annual percentage growth rate is of a trend line. How to automate this in Excel? I've attached a sample so you can see what I'm trying to accomplish.
View 6 Replies
View Related
Jan 29, 2007
I want to calculate the subscription rate as follows:- Subscription is fixed at the minimum rate of Rs.200 and is incremented at the rate of Rs.10/- for every Rs.200/- thereafter?
View 2 Replies
View Related
Nov 8, 2008
Some years ago I came across a formulae to calculate Daily Interest on a Building Society Savings account in the UK. I have used this since but find my calculations never work out the same as my BS, although to my advantage! It is =B3*B4/360*DAYS360(B5,B6,TRUE) Where:
B3=Capital
B4=Interest Rate
B5=Starting Date
B6=Finishing Date
For some reason the formulae uses 360/year and not 365/year. Using both still gives wrong answer.
View 2 Replies
View Related
Dec 27, 2012
I am trying to calculate a new base pay rate, but I need it make sure it is at least brought up the new minimum and capped at the new max of the range where applicable. The increase is based on 10%
So here are the columns used:
L = Current Base Pay
Q = New Min of the range
S = New Max of the range
U = where I want to calculate a 10% increase of L, but ensuring it is brought up to at least the min (Q) or not over Max (S). In other words if my min is $12 and Max $18 and my new base pay is $16 -- then I am good. However it if is $11.50 I need the formula to return at least $12. And visa versa -- if the new rate would be $18.50, I need it to return no more than $18.
View 3 Replies
View Related
Feb 13, 2010
I am trying to calculate APR (Annual Percentage Rate) for a mortgage loan that has a balloon feature. I have tried to the the RATE function but it only gives me the APR for a loan that is ammortized over 30 yrs and paid in 30 years. I need the APR for a loan that is ammortized for 30 years with a baloon in 5 years.
View 9 Replies
View Related
Nov 29, 2013
I have a workbook with rental properties containing 2 sheets. 1 sheet with the general details and the rate sets and 1 sheet where I'm trying to calculate the total price for a period of time between 2 dates. I would like the people who use this workbook to simply enter the dates and get a price based on the amount of days within a rate set.
eg: 1 to 7 days is weekly, 8 to 31 is monthly etc. To display this, I'm using: =LOOKUP(H3,{0,7,30,180,365;"daily","weekly","monthly","6 months","yearly"})
These rates are different for each property, and this formula isn't exactly dynamic; it just displays which rate should be used.
Now my idea is to use IF/THEN kind of a formula, but I'm lost on how to do this. The actual rates are on the other sheet in separate rows and columns belonging to the appropriate property. Also, the rates as they are will probably need to be recalculated to a daily number before it can be used for the price calculation, because a month has either 29, 30 or 31 days.
At the moment the daily rate is diplayed as a daily rate
The weekly as a weekly rate
The Monthly as a monthly rate
The 6-Monthly as a Monthly rate (with a minimum of 6 months of course)
And the yearly also as a Monthly rate (with a minimum of 12 Months)
I've attached the sheet as a reference : Property details import.xlsm‎
View 14 Replies
View Related
Jan 31, 2014
I currently use goal seek to calculate an interest rate for a loan product. My problem is i would like to have the same function but not through a goal seek. In goal seek i have to set the value i want to achieve but ideally i want it to calculate automatically
I have attached a workbook with details. I use a loan amortization schedule to calculate the interest from parameters set on sheet 1
View 2 Replies
View Related
Jun 6, 2014
What I need is a worksheet which will generate fields from a set of variables (similar to a loan amortization schedule).
I don't know how to write the field code to include the annual percentage rate increase based on that additional input variable.
Input variables would be:
starting rate: (ex: 8¢/kilowatt hour)
starting date: (ex: July 2013)
average kw hours/month: (ex: 1062.5 kw hours)
annual rate increase: (ex: 3% *default 0%)
years to display: (ex: 25 years, *shown in months in fields below)
service months per year: (ex: 12 *default 12)
[code].....
So, data fields below the variables would be blank until these are entered.
Assume I would protect the sheet to avoid messing it up.
this would generate a chart showing rates over time from the fields below.
Also it would generate fields in a summary area to show the rate per year for future years.
Secondary, if there were a way to input actual usage and rates from specific months in the past, that would be useful but not part of this forecast model.
The goal of this model is to forecast electrical costs for residential power users compared to independent solar power generation to 25 years forward.
I want to make this because I am skeptical of the advertised savings that solar installers use to convince clients that their return on investment is so high. I believe their data to be greatly inflated projections.
Using this in comparison with other data such as inflation and wages will allow me to get a very good economic picture of the future of independent solar energy generation and its impact on the average home owner.
View 2 Replies
View Related
Feb 4, 2014
I have a base rate in A1, the the units in B1 and need a total in C1.
In A3 i have discount rate (%) for units between 0 and 9
In B3 the have the discount rate (%) for units from 9 to 15
In C3 the have the discount rate (%) for units from 9 to 15
In D3 the have the discount rate (%) for units above 16.
How would the formula looklike?
View 3 Replies
View Related
Apr 18, 2006
I am trying to calculate earnings based upon hours worked based on 24 hours format (time out - time in = time worked) multiplied by hourly rate. I cannot get the proper calculation. How can I attach a copy of the Excel worksheet?
View 9 Replies
View Related
Dec 20, 2007
I have downloaded .csv files with my phone call costs. I want to compare phone companies, so I need to calculate the h:mm:ss amounts to $ based on flagfall and rate per 30 seconds. I can open the .csv files in Excel but I do not know anything about Excel.
View 4 Replies
View Related
Feb 5, 2008
I have a situation where I have to determine the required size of a deposit from which constant withdrawals are to be made until the deposit runs out to ZERO. The deposit earns interest at a fized rate, capitalized monthly after each withdrawal had been made.
In my example case, the target month (The actual cell that needs to have a value of ZERO (when the deposit runs out), or the "Range") is found in cell G16. In another situation, it may be found in cell G19 etc, depending on the situation.
It is this changing of the target cell (the one that needs to be ZERO) that has me stumped. I've been thinking of using VLOOKUP (not trying to lead you ;-)) to determine the actual position of the cell that need to have a value of zero but do not know how to build this into the VBA code of Goalseek. This target cell in the Goalseek code should be the cell in column G opposite the figure 1 in column A.
In my example I simply typed in a figure 1 in column A - in the actual spreadsheet the position of this figure is calculated with a formula and its position moves from situation to situation. If the 1 is in cell A19, the target cell, whose value should be ZERO, will then be cell G19..............
View 2 Replies
View Related
May 25, 2009
The way I have this sheet setup is to calculate a 20% fee off the interest earned column "D". Say you earned 6.5% on a beginning balance so the interest earned is in col "D". This works fine for a 20% fee but I need the fee to calculate a 10% fee if the interest in column "C" hit 4% or below and it also needs to be able to calculate a 20% fee if the interested earned is above 4%.
View 5 Replies
View Related
Nov 23, 2009
I have 3 sets of data for two different groups:
Group 1 - Inbound
- Total volume
- Gross adds
- Win rate (gross adds/total volume)
Group 2 - Outbound
- Total volume
- Gross adds
- Win rate (gross adds/total volume)
I need to calculate the weighted average of the win rate based on volume of calls. Is there any way to do that?
View 6 Replies
View Related
Mar 23, 2007
I am trying to put together a spreadhseet that will calculate the future cost of education fee assuming a given inflation rate. I would like the reuslt to be highlihted in a list or a table. The user would only need input current fee, inflation rate and years where fees are payable. The spreadsheet would do the rest. I have laid this our best I can attached.
View 5 Replies
View Related
Nov 15, 2013
I am looking to setup a formula to calculate a Fee that is based on the number of users of a service in a month, with the rate varying by the number of users. The first million users in a month will bring in $0.40 per user, for users 1-4M it will bring in $0.30 per user, for users 4M-7M it will bring in .20 per user, and for users beyond 7 million it will be .10 per user. So for example, if a user count was 9 million in a month, the calculation would be ($0.40 x 1 million) + ($0.30 x 3 million) + ($0.20 x 3 million) + ($0.10 x 2 million). I know the answer to the problem is obviously $2,100,000 but I can't build the formula that solves that and can handle instances where the user count is capped in one of the individual brackets. (IE if there are 3.5M users)
I've attached an example spreadsheet : Variable Fee Schedule.xlsx‎
View 7 Replies
View Related
Jun 18, 2009
Our office has a vacation days accrual policy based on number of years worked. We have a vacation days number, based on year of employment, the employee earns monthly. I need help with a worksheet, formulas, to document each employee, the year of employment they're in, # of days they have available based on the current month (which would need to add up automatically as the year progresses), then any days they request off, and finally a remaining balance of days left.
View 6 Replies
View Related
Jul 10, 2014
I have a model that makes projections based on annual growth rates. However, I need to evaluate the data based on monthly intervals. With an 8% return on an investment of $1,000,000 my ending balance at the end of the year should be $1,080,000 and in year 2 it would be $1,166,400 and so on. In order to evaluate the monthly data I need each month in year 1 to be based off $1,000,000, so it would be 8%/12=.006666% or $6,666.66 per month. The next year would be based off $1,000,000 + (6,666.66*12) = $1,080,000 and each month would be $7,200.
writing a formula to evaluate over 360 periods.
View 5 Replies
View Related
Jun 4, 2007
The formula I am looking for would tell me what annual growth rate % I would need to achieve to make any investment reach a set target, for instance, what % of fixed annual growth would I need to make 200K grow to 750k in say 10 yrs or any time scale. I was given the formula below but Excel tells me it's wrong, I have tried putting 10 before ^ and the 10 after but to no avail, could some kind soul please put me straight.
r = 100((Y/X)^(1/n))-1)
So for X = 200, Y = 750, n = 10, we have
r = 100((750/200)^(0.1))-1) = 14.1309%
View 3 Replies
View Related
May 21, 2008
Have 5 columns (A1-E1) with different bond data: (respectively)
Coupon, Maturity, Settlement, Price, Yield (asset swap is F1)
Depending on the type of swap I am performing i want the ASWAP (user-created) function to reference different values within the row.
For example: Swap 1 = settlement, maturity, coupon, price, curve
(curve is a user input single number 1-3)
Swap 2 = settlement, maturity, yield, price, curve (yield in place of coup)
Swap 3 = settlement, maturity, yield, 100, curve (100 for par redemption)
etc. I won't type out all the iterations, not necessary.
The way that I want the ASWAP to recognize which Swap# to use is by inputting a number into a cell beside the Aswap column that I can input 1, 2, 3, etc., and then recalculate to get the desired outcome. Want to keep this a static reference as well as the price at par (each owning their own single cell, not a fill down the columns because there are too many).
So assuming G1 is the Swap# input, and H1 is 100...
How do i write a formula that is capable of reading the input in G1 and outputting the proper swap calc.
My gut feeling was along the lines of nested IF's with the corresponding formula... but i won't mess around in futility on here.
Let me know if this is too confusing without me putting up an example.
View 9 Replies
View Related
Sep 15, 2007
My problem is the following:
I'm trying to model straight line depreciation over 5 years for certain investments. This could for example be done like this: ....
View 9 Replies
View Related
Feb 15, 2006
I have a list of items on which I need to calculate the SLD, normally I would just divide the Acq Cost by the Salvage period (5yrs) to calculate the yearly depreciation. However I have been asked to calculate it from the Cap Date, therfore the first year would only be a portion of the year and the final year would also be a potion of the year.
So I'm trying to calculate the depreciation period for an asset with an Acq Cost of £12500 and a Cap Date of 27th July 04 over a 5yr period from that date.
View 9 Replies
View Related
Dec 20, 2012
i am trying to get back to the original purchase date of an asset.
It has being depreciating using the reducing balance method.
I have the Net book value of the asset currently, the original cost and the depreciation rate.
However i do not know the quickest way in excel to work back to the original purchase date.
See attached file for examples and my long workaround to estimate purchase date.
View 1 Replies
View Related
Jun 11, 2014
I am in need of a formula to calculate monthly straight-line depreciation assets based on the current month’s days.
So, if an asset costs $10,000 and has 15 years of useful life, in June this would calculate 15 divided by 12 divided by 31 times 10,000. I want to put cost in one cell and date in another, for the formula.
BTW, someone is using this formula, =(16736*(1/15)*(6/12))*31/184
View 9 Replies
View Related
Feb 2, 2008
Using the declining balance depreciation formula how can I have the individual time frame results put into to cells?
View 9 Replies
View Related
Mar 18, 2013
how to calculate debt repayments using this approach.
As shown on the attached file repay issue.xlsx I have an example where a loan is taken out regularly (in the example every 6 years) but repaid over a shorter period (in this example every 3 years).
Using "IF(MOD(ROW" the formula identifies correctly when the loan has to be renewed, and calculates correctly how much needs to be borrowed.
C14 =IF(MOD((ROW(A14)-ROW($A$8)),B$3)=0,B9*C$5
Because Row 14 is six rows below the start (Row 8) which is the interval set by B3, it enters the loan percentage
(C5) of the asset value (B9) into C14.
Problem comes in the following rows. I need the formula to establish how many rows the "active" row is below the last "renewal", then deduct one fraction of the payback period for each row. By sheer coincidence the formula below works on the second row of the datsabase and deducts one third of the loan value because C8 WAS the previous "renewal", and row 9 is one below it:
=IF(MOD((ROW(A9)-ROW($A$8)),B$3)=0,B9*C$5,IF(MOD((ROW(A9)-ROW($A$8)),B$3)=1,C8-(C8*(COUNT(A9-A$8)/C6))))
I cannot "hard wire" the cell references into the formula because the renewal intervals and number of paybacks range from 25 year mortgages paid every year without being renewed to a one year loan on an item renewed every two years
View 2 Replies
View Related