Add Days To A Specific Date
Jul 11, 2007
A1=10 July 2007
A2=12 (number of days)
A3=21 July 2007
I need a formula in A3 that will basically add the number of days in A2 to the given date in A1.
Note: Don't know how would this work with 30 and/or 31 days months??
View 9 Replies
ADVERTISEMENT
Nov 22, 2013
I want to calculate the end date of my German courses. This is how it works:
A course consists of 60 LU*. The course can occur i. e. three times a week: Monday, Wednesday and Friday. In each day the course lasts 2 LU, which means 6 LU each week. There is no course on Tuesday, Thursday, Saturday, Sunday and on holidays. Therefore this type of course that begins on 18-Nov-2013 will end on 03-Feb-2014.
Another course which occurs Tuesday, Thursday and Saturday, and respectively has 2 LU on Tuesday, 2 LU on Thursday and 3 LU on Saturday and starts on 03-Dec-2013 will end on 06-Feb-2014.
Therefore I want to create a worksheet where I set the start date, choose the days and respectively the LU amount on those days. The end date shall be calculated according to these criteria.
The workday function on excel cannot do this and I do not have any programming skills to work with VBA.
Legend:
*LU = lesson units; 1 LU is 45 minutes
Holidays:
28-Nov-13
29-Nov-13
08-Dec-13
09-Dec-13
25-Dec-13
31-Dec-13
01-Jan-14
[Code] ...........
View 7 Replies
View Related
Jun 19, 2014
I'm using the code below to extract information from a 'Source' (Remaining Allocation Data) to a 'Destination' (All CTO Expired Assignments) sheet.
[Code] ......
The code works except for this part of the script
[Code] ....
What I'm trying to do is as follows:
Extract records where the FinDate is less than the CurrentDate, (i.e. 19/06/2014) and,
Is equal to and no greater than 28 days prior to the Current Date (i.e 22/05/14)
I've tried all sorts of formulas to try and get this to work including the 'DateAdd' function, but I've so far been unsuccessful.
View 2 Replies
View Related
May 18, 2008
the formula below prints monday to friday when i drag it down. Probably a very easy question but how would i change it so when i drag it down it includes saturdays so the only date missed out is Sunday.
It picks the date from cell a4. the code is from here: http://www.cpearson.com/excel/DateTimeWS.htm
=IF(WEEKDAY(A4)=7,A4+2,IF(WEEKDAY(A4)=6,A4+3,A4+1))
View 4 Replies
View Related
Sep 15, 2009
I am creating a tracking spreadsheet and I will need to f/u on a process 30/60/90 days out from a particular date. Example: CPAP Therapy began 1/22/09 and I need to follow-up by 2/22/09. How do I create formula to add 30/60 or 90 days out from the setup date?
View 6 Replies
View Related
Jan 20, 2013
I have a form with grouped check boxes for each day of the week, and start date and end date from the Microsoft Date and Time picker control. I want to know the total days within the date range based on check boxes. For example, Tuesday and Thursday are checked off. The start date is December 1, 2012 and end date is January 31, 2013. What is the total number of Tuesdays and Thursays in that two month date range.
View 2 Replies
View Related
Oct 8, 2013
I have a spreadsheet that contains dates in format mm/dd/yyyy. Lets call this Column C(Paydate). In Column A I have a date that needs to be a 2 business days before the paydate. If this date in column A winds up being a Saturday or Sunday, the function needs to return the previous Friday. If the date is any weekday then it should return that weekday
For example:
C1 = 10/18/2013(a Friday) then A1=10/16/2013
C2 = 10/14/2013(a Monday) then A2= 10/11/2013(the previous Friday since 2 days before 10/14/2013 is a Saturday)
C3 = 10/15/2013(a Tuesday) then A3= 10/11/2013(the previous Friday since 2 days before 10/15/2013 is a Sunday)
View 4 Replies
View Related
Feb 11, 2010
I'm documenting the steps of a process with each step accounting for a specific amount of business days. How do I determine the specific business day based on the number of days it takes to complete a process? For example: Start date then 45 business days from that date the next step begins...then 3 business days from that date the following step begins and so on.
View 5 Replies
View Related
Mar 17, 2014
excel.jpg
how to make my network days stop counting when I insert a value in the completed column (in this case H3). I have a Date Received column (A3), a due day column (G3) and the last column with the date (N3). My remaining days column keeps counting after I filled the completed cell (H3) and won't stop counting after. I need a formula to stop after the completed cell is fill up.
View 5 Replies
View Related
Jul 31, 2009
I'm needing a formula that will determine the number of days that fall in a specific month based on a date range. For example, if I have a date range of 10/15/2009 to 01/13/2009, I need the formula to determine the number of days in each month within the range (October has 15 days in the date range; November has 30, December has 31, and January has 13.) I have a large spreadsheet that would be so much easier to manage with such a formula. Currently, my spreadsheet is setup as follows. I need the forumla automatically fill in the number of days under each month.
Stard Date End Date Oct-09 Nov-09 Jan-10 Feb-10
10/15/2009 01/13/2009
I'm using Excel 2007.
View 9 Replies
View Related
May 27, 2012
There are dates in column C and I need to count how many days are coming due within 90 days of each date based on the today() function but do not exceed the 90 days.
Countif Today()+90
View 5 Replies
View Related
Mar 14, 2014
I am making process TAT(Turn Around Time) which required following information. In Excel 2007.
1-Count number of days between two dates where working days are (Sun to Thursday). So required to exclude (Friday,Sat + Holidays)
A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 22
D1-Days between two dates 21
E1 To E10-Holidays
2-Count number of days between two dates where working days are (Sat to Thursday). So required to exclude (Friday + Holidays)
A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 27
D1-Days between two dates 26
E1 To E10-Holidays
Note : Any weekend (off days) dates listed in holidays should not effect the query.
View 9 Replies
View Related
May 25, 2014
I am now trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.
View 1 Replies
View Related
Apr 8, 2009
I am trying to get the results of the number of days between today and a future date. I am using ="cell containing futuredate"-today() and it gets me the correct number of days. The problem comes in when I have yet to populate the future dates. I am getting -39991 (numeric value between today and jan 01 01) and because I am also using conditional formatting this is even more of a problem. Is there a way get excel to display nothing if it is a negative number? or to give a specified resut if the number becomes negative such as Expired or something of that nature?
View 3 Replies
View Related
May 19, 2009
I need a formula that will calculate the number of days from a date entered into cell A1 to today's date. Whether it's before or after todays date. Example:
5/10/2009 to today is -9
5/22/2009 to today is 3
View 2 Replies
View Related
Mar 19, 2012
how can i count the positive days to a inserted date value or the past days (negative value) to the system date (today).
View 5 Replies
View Related
Sep 18, 2008
I have a worksheet that has a sent date and expected delivery date I need create a macro that will alert me if today's date is within 5 days of expected delivery date.
View 14 Replies
View Related
Apr 2, 2009
I have two columns of dates, leave start and end dates (when people start leave i.e. annual leave). Would need to introduce column(s) to calculate how many days fell within the month including the end date and excludes weekends.
For example, if the staff on leave from 31st March to 6 April, i need to show that the number of leave taken as 1 day in March and 4 days in April.
View 9 Replies
View Related
May 26, 2014
i am trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.
View 4 Replies
View Related
Nov 19, 2008
If the 21st of September 2008 was on a Sunday, I need to work out the date for Sunday three months on....
View 9 Replies
View Related
Jan 17, 2010
I have two questions regarding date format and hope you can provide input.
1) say 01/01/2010 displays as Jan-10 and i need a new column to state it as JAN. What function should i use to achieve it?
2) i need to state the difference between first day and last day of the month. What function should i use to achieve it?
View 2 Replies
View Related
May 13, 2008
I have column B with a heading "Days Remaining" and column L with a heading "Deadline". starting with row 5, I need to be able to enter a date in L5 and see the days I have left, from that day untill today, on B5. I need to then be able to enter a date into L6 and see a result in B6 and on and on. Then I need to be able to insert or delete a column and have the formulas still work in the columns with the heading "Days Remaining" and "Deadline"
View 7 Replies
View Related
Jun 25, 2009
I am wondering if there is a way in XL2003 to determine how many times specific days of the month occur within a specified date range. For example, I need to find out how many times both the 1st of the month, and how many times the 15th of the month occur in the time period starting 05/02/2009, and ending 07/12/2009.
View 3 Replies
View Related
Jan 30, 2010
Can Anybody help me with a function that will arange all days from January acorrdingly with the year 2010. I am attacing a sample file to make it clear. I need the function to Check which month is in Cell H1 and arrange the days accordingly to the month and the year.
In my example the code must change the Cell values Like this: ...
View 9 Replies
View Related
Jan 22, 2008
I want to be able to count the number of days in a specific year between two dates.
Suggested formula input: DaysInYear(Date1,Date2,Year)
Examples:
DaysInYear(3/3/2005,3/3/2006,2006) should return 62 (31 in Jan, 28 in Feb and 3 in Mar.)
DaysInYear(3/3/2005,3/3/2007,2006) should return 365
View 4 Replies
View Related
Nov 15, 2008
I was wondering if anyone knows how I could enter a date in one cell, then another date in a second cell and in a third cell have it have it so it minuses the first date from the second and calculates the difference outputted in number of days.
Example: 04/31/08 - 04/01/08 = 30 (days)
View 2 Replies
View Related
Apr 23, 2008
I need to create a formula that states a delivery date when the order date is entered in an adjacent column. Items ordered on Monday, Tuesday and Wednesday will be delivered the Friday of the following week, eg. ordered 23rd April 2008, delivered on the 2nd of May 2008. Items ordered on Thursday or Friday will be delivered on a Friday 2 weeks later, eg. ordered on the 24th April, delivered on the 9th of May 2008
View 4 Replies
View Related
Aug 29, 2013
At the end of each month, my agency collects data about clients served in our programs. One of the many pieces of information they want is the number of "bed days" a client was residing within our programs for the given month.
For example:
Jon Doe entered the program on 7/16/13 and discharged on 8/15/13. I would like to know how to calculate the number of days in July that Mr. Doe was residing in the program. (The date of discharge is not included.)
I recently took over the responsibility of completing reports such as this one at my office. The previous person who completed the monthly reports would count the days by hand for each client, but I know there must be a better way.
View 6 Replies
View Related
Jul 27, 2012
ive created an excel spreadsheet with expiration dates in one row and im trying to write a code which will pull out all information in the column if the expiration date in a certain row is within 90 days of the date the excel file is accessed
View 2 Replies
View Related
Oct 29, 2009
I have todays date in cell A2. I have a range of dates in a row 4 and numbers below each date in row 6. What i want is to Sum the numbers below the dates in row 6 if the date in row 4 is with in 90 days before or after the date in cell A2.
Example......
The answer i should get is 4 since only 3 dates fall 90 days before or after todays date.
View 3 Replies