Calculate Specific Days Within Specified Date Range?
Jan 20, 2013
I have a form with grouped check boxes for each day of the week, and start date and end date from the Microsoft Date and Time picker control. I want to know the total days within the date range based on check boxes. For example, Tuesday and Thursday are checked off. The start date is December 1, 2012 and end date is January 31, 2013. What is the total number of Tuesdays and Thursays in that two month date range.
View 2 Replies
ADVERTISEMENT
Nov 22, 2013
I want to calculate the end date of my German courses. This is how it works:
A course consists of 60 LU*. The course can occur i. e. three times a week: Monday, Wednesday and Friday. In each day the course lasts 2 LU, which means 6 LU each week. There is no course on Tuesday, Thursday, Saturday, Sunday and on holidays. Therefore this type of course that begins on 18-Nov-2013 will end on 03-Feb-2014.
Another course which occurs Tuesday, Thursday and Saturday, and respectively has 2 LU on Tuesday, 2 LU on Thursday and 3 LU on Saturday and starts on 03-Dec-2013 will end on 06-Feb-2014.
Therefore I want to create a worksheet where I set the start date, choose the days and respectively the LU amount on those days. The end date shall be calculated according to these criteria.
The workday function on excel cannot do this and I do not have any programming skills to work with VBA.
Legend:
*LU = lesson units; 1 LU is 45 minutes
Holidays:
28-Nov-13
29-Nov-13
08-Dec-13
09-Dec-13
25-Dec-13
31-Dec-13
01-Jan-14
[Code] ...........
View 7 Replies
View Related
May 11, 2014
Is there a way to calculate how many days and hours there are in a date range IE 5/11/2014 to 10/31/2014 = days and hours
View 2 Replies
View Related
Jul 31, 2009
I'm needing a formula that will determine the number of days that fall in a specific month based on a date range. For example, if I have a date range of 10/15/2009 to 01/13/2009, I need the formula to determine the number of days in each month within the range (October has 15 days in the date range; November has 30, December has 31, and January has 13.) I have a large spreadsheet that would be so much easier to manage with such a formula. Currently, my spreadsheet is setup as follows. I need the forumla automatically fill in the number of days under each month.
Stard Date End Date Oct-09 Nov-09 Jan-10 Feb-10
10/15/2009 01/13/2009
I'm using Excel 2007.
View 9 Replies
View Related
Mar 26, 2014
I am trying to calculate the total amount of kilos for a specific date with a given time range.
As well as the average time they have been handled with in the same specifications.
Attached is a sample sheet of the info I am working with but I cant seem to get the formulas to work.
Book1.xlsx
View 9 Replies
View Related
May 19, 2009
I need a formula that will calculate the number of days from a date entered into cell A1 to today's date. Whether it's before or after todays date. Example:
5/10/2009 to today is -9
5/22/2009 to today is 3
View 2 Replies
View Related
Apr 2, 2009
I have two columns of dates, leave start and end dates (when people start leave i.e. annual leave). Would need to introduce column(s) to calculate how many days fell within the month including the end date and excludes weekends.
For example, if the staff on leave from 31st March to 6 April, i need to show that the number of leave taken as 1 day in March and 4 days in April.
View 9 Replies
View Related
May 13, 2008
I have column B with a heading "Days Remaining" and column L with a heading "Deadline". starting with row 5, I need to be able to enter a date in L5 and see the days I have left, from that day untill today, on B5. I need to then be able to enter a date into L6 and see a result in B6 and on and on. Then I need to be able to insert or delete a column and have the formulas still work in the columns with the heading "Days Remaining" and "Deadline"
View 7 Replies
View Related
Jul 7, 2013
How can i get the actual Payment due date from no. of days using macro. i. e.
Posting Date Dues Payment Date
------------ ------ ---------------
22.06.2013 21 days ???
View 9 Replies
View Related
May 18, 2006
I need to calculate on a spreadsheet the number of days between a specific date and the date the spread sheet is opened. I need to know the number of days a merchandise has been stored.
View 5 Replies
View Related
Apr 1, 2014
Need to calculate the number of days in December between two dates 11/20/2013 and 1/20/2014, how many days are in december? a formula that can calculate this?
View 9 Replies
View Related
Feb 6, 2009
I need to have a cell with a date in it then the next cell needs a formula to caluclate how many days it has been since that date???? I'm a real novice with excel.
View 9 Replies
View Related
Jul 11, 2007
A1=10 July 2007
A2=12 (number of days)
A3=21 July 2007
I need a formula in A3 that will basically add the number of days in A2 to the given date in A1.
Note: Don't know how would this work with 30 and/or 31 days months??
View 9 Replies
View Related
Feb 21, 2014
I'm trying to create a new column which calculates the number of days from the today's date to the due date of an invoice. Also a Column that an invoice is/was overdue.
Column A - Clerk inputs date that invoice was received
Column B - Clerk inputs the date that the bill was paid
Column C - Auto populates the due date of the invoice (20 days after the invoice is received)
Column D - I want a number of days to auto populate based on today's date that will show how many days we have to pay the bill. Example: today is 2/19/2014, bill is due 2/22/2014 (Column C), column D should read 3 (I would prefer is the number is black for "we have days left to pay", red for "we're behind")
*Extra bonus for Column D, if the column goes blank after a date is entered into Column B* - but not necessary
Column E - I would like if the date the bill was paid (Column B) is greater than the date the invoice is due (Column C) to show "Overdue" in the cell.
View 9 Replies
View Related
Jun 19, 2014
I'm using the code below to extract information from a 'Source' (Remaining Allocation Data) to a 'Destination' (All CTO Expired Assignments) sheet.
[Code] ......
The code works except for this part of the script
[Code] ....
What I'm trying to do is as follows:
Extract records where the FinDate is less than the CurrentDate, (i.e. 19/06/2014) and,
Is equal to and no greater than 28 days prior to the Current Date (i.e 22/05/14)
I've tried all sorts of formulas to try and get this to work including the 'DateAdd' function, but I've so far been unsuccessful.
View 2 Replies
View Related
May 18, 2008
the formula below prints monday to friday when i drag it down. Probably a very easy question but how would i change it so when i drag it down it includes saturdays so the only date missed out is Sunday.
It picks the date from cell a4. the code is from here: http://www.cpearson.com/excel/DateTimeWS.htm
=IF(WEEKDAY(A4)=7,A4+2,IF(WEEKDAY(A4)=6,A4+3,A4+1))
View 4 Replies
View Related
Sep 15, 2009
I am creating a tracking spreadsheet and I will need to f/u on a process 30/60/90 days out from a particular date. Example: CPAP Therapy began 1/22/09 and I need to follow-up by 2/22/09. How do I create formula to add 30/60 or 90 days out from the setup date?
View 6 Replies
View Related
May 25, 2014
I am now trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.
View 1 Replies
View Related
Jul 25, 2014
I have added 3 tables data .. also I had created a sample solution calc for emp1 and project1 ... I need to calculation the ratio between the months based on the working days and allocate the efforts accordingly.
View 2 Replies
View Related
Oct 8, 2013
I have a spreadsheet that contains dates in format mm/dd/yyyy. Lets call this Column C(Paydate). In Column A I have a date that needs to be a 2 business days before the paydate. If this date in column A winds up being a Saturday or Sunday, the function needs to return the previous Friday. If the date is any weekday then it should return that weekday
For example:
C1 = 10/18/2013(a Friday) then A1=10/16/2013
C2 = 10/14/2013(a Monday) then A2= 10/11/2013(the previous Friday since 2 days before 10/14/2013 is a Saturday)
C3 = 10/15/2013(a Tuesday) then A3= 10/11/2013(the previous Friday since 2 days before 10/15/2013 is a Sunday)
View 4 Replies
View Related
Feb 11, 2010
I'm documenting the steps of a process with each step accounting for a specific amount of business days. How do I determine the specific business day based on the number of days it takes to complete a process? For example: Start date then 45 business days from that date the next step begins...then 3 business days from that date the following step begins and so on.
View 5 Replies
View Related
Mar 17, 2014
excel.jpg
how to make my network days stop counting when I insert a value in the completed column (in this case H3). I have a Date Received column (A3), a due day column (G3) and the last column with the date (N3). My remaining days column keeps counting after I filled the completed cell (H3) and won't stop counting after. I need a formula to stop after the completed cell is fill up.
View 5 Replies
View Related
Aug 29, 2013
At the end of each month, my agency collects data about clients served in our programs. One of the many pieces of information they want is the number of "bed days" a client was residing within our programs for the given month.
For example:
Jon Doe entered the program on 7/16/13 and discharged on 8/15/13. I would like to know how to calculate the number of days in July that Mr. Doe was residing in the program. (The date of discharge is not included.)
I recently took over the responsibility of completing reports such as this one at my office. The previous person who completed the monthly reports would count the days by hand for each client, but I know there must be a better way.
View 6 Replies
View Related
May 26, 2014
i am trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.
View 4 Replies
View Related
Jan 7, 2010
I have a monthly start and end date e.g 2/01/2010 – 30/01/2010. I want to a formulate the below so I don’t have to do it manually each day. Start date is in E1 and end date E2
I have to change on another sheet how many Monday’s we have had so far in the month range and this is for each day of the working week (Mon, Tues,Wed,Thurs,Frid). So, so far this week we would have
(B11)Monday – 1
(E11)Tuseday - 1
(H11)Wednesday – 1
(K11)Thurdsay – 1
(N11)Friday – 0
By this time next week I would have
(B11)Monday – 2
(E11)Tuseday - 2
(H11)Wednesday – 2
(K11)Thurdsay – 2
(N11)Friday – 1
View 9 Replies
View Related
Jan 2, 2014
I have a table that looks like this (its basically a historical data of a stock exchange):
Date
Index
January 4, 2010
[Code]....
The List continues till the current Date.
I want to calculate Average Index Values of a Date of each month within a Date Range.
Example: Calculate Average Index Values for 3rd of Each month from 1st Feb 2010 to 3rd Jan 2011. Formula should calculate Average of the Index Values for 3rd Feb 2010, 3rd March 2010, 3rd April 2010, 3rd May 2010, 3rd June 2010, 3rd July 2010, 3rd Aug 2010, 3rd Sept 2010, 3rd Oct 2010, 3rd Nov 2010, 3rd Dec 2010, 3rd Jan 2011.
Both the Date and the Date Range is variable. Also, the Index Value for selected Date of one or more month may not be available as that being a holiday. In that case, the formula needs to use the last available Index Value before that Date. e.g. If Index Value for 3rd Oct 2010 is not available, system will use the Index Value of 2nd Oct 2010.
View 1 Replies
View Related
Nov 20, 2008
Is there a way to use goal seek in VBA that won't trigger a full model calculation?
I would like to (somehow) perform goal seek, but only recalculate range("A1:B50") say on a single worksheet (where both the input value and the final calculated value is included in that range), as opposed to calculating the whole model inbetween each iteration.
Also, all dependencies between the input value and the final calculated result are contained in that range.
View 5 Replies
View Related
Aug 31, 2007
i'm trying to find a way to distribute days per month between 2 dates. I have found a great exemple that should to de trick but there is still a problem left in it. it gives in the next year (this case '08) an +31 value and a negative value
View 4 Replies
View Related
Mar 20, 2014
I am assessing the impact of product price increases on volume (qty) and sales (£/$).
The prices are changed sporadically and at no set intervals. For example pries were changed on the 15th Jan and 13th Feb this year.
We have set reporting dates (calender months) so i am hoping to be able to divide the report which shows sales & qty's during the 15th Jan - 13th Feb segment and apportion them to the correct months.
I have the start & end dates of the calender months in cells A4:B18 and each time a new report is run (ie 15th Jan or 13th Feb, these dates go across the top i.e. cell C3 = 15th jan & D3 = 13th Feb.
I would like to return a % in cell C4 which relates to the amount of total days in the segment that relate to Jan (ie. 29 days in the segment, 16 relate to Jan so 55.2%).
Cell C5 would then return a % which relates to the amount of total days in the segment that relate to Feb (29 days in the segment, 13 relate to Feb so 44.8%).
Cells D4&D5 would return the next reporting segment and how many days in Jan/Feb respectively (the answer will be 0 but a constant formula acrosss all would be perfect. tried to give as much info as poss.
View 2 Replies
View Related
Apr 21, 2006
Let's say I have thousands of employees, but I need to determine who worked for me during a particular date range, and all I have to go on is their start date in one column and their end date in another column.
If:
A1 contains beginning date of employment
B1 contains ending date of employment
C1 contains specified beginning date (criteria)
D1 contains specified ending date (criteria)
View 4 Replies
View Related