Set Up A 6 Day Work Week

Aug 10, 2006

I normally use the WORKDAY function in order to create an involved scheduling
program. However, I have no idea how to create a formula that would count
Saturdays as a workday. I usually type in one date and then the dates kick
out to an end date several months later. How do I create a formula to
include Saturdays on a daily projection (e.g. A1=8/12/06, A2=8/14/06,
A3=8/15/06,etc...)?

View 9 Replies


ADVERTISEMENT

Subtract Two Dates To Get Number Of Week Days - Networkdays Does Not Work

Dec 10, 2013

I am trying to find a formula that will return the number of week days between two dates. My specific situation is that my job sets up work orders (WO) to be completed by our staff. We have 3 dates - the date the WO was created, the date the WO is due to be completed, and the date the WO was actually completed.

I would like to subtract the Complete date from the Due date. Generally, this should always equal zero because our staff should be completing WOs on the due date! But obviously that doesn't always happen. There are times that they complete them late, and times they complete them early (yay!).

The problem with NETWORKDAYS is that even when they are completed on time, the result is 1. This formula counts instead of subtracts. I adjusted the formula to =NETWORKDAYS(A3,A4)-1 which works fine for those WOs completed on time or completed late. But for those completed early, it adds (or subtracts, really) 2 days. So for a WO completed a day early, instead of it showing -1, it shows -3. I've attached an example of WOs and the NETWORKDAYS formula I've used so you can see.

Subtract Days.xls

I'm really looking for something that will subtract week days, not count them.

View 3 Replies View Related

Capture And Calculate Data Based On Work Week In VBA Or Formulas

Jul 21, 2014

I have a requirements to capture the data and calculate the qty based on the defined work week. How to to this in vba macro or a formulas. I'll giving a sample data as reference. In my sample data i have already the formulas
but i wanted to automate the work week calculation specially if the number of days in a month has been change.

Btw, the values of every column is came from other worksheet. i copy paste this data as my sample.

For ex : Today is July and it has 31 days, the 31 days will be distributed to the defined workweek and calculate the contents of the corresponding column.

here is the distribution of columns per week as reference.

(31 days)
wk1 - Day1 to Day8 (8 colums)
wk2 - Day9 to Day16 (8 colums)
wk3 - Day17 to Day24 (8)
wk4 - Day25 to day 31 (7) columns

(30 days)
wk1 - Day1 to Day8 (8 colums)
wk2 - Day9 to Day16 (8 colums)
wk3 - Day17 to Day23 (7)
wk4 - Day23 to day 30 (7) columns

View 1 Replies View Related

Count Formula- Spreadsheet That Is Being Used For Tracking Work Completed Each Day In A Week

Apr 9, 2009

I have a spreadsheet that is being used for tracking work completed each day in a week. Each day has 5 columns and 10 rows of data to potentially be entered, some of the data is text and some is numerical. Can anyone help me come up with a formula that will count the text and the numerical entries for each day? I tried to use a nested if statement but it exceeded the number of nestings available. The range of cells for the first group is B6:F16.

As a side question, will count work for a range of data or only one column or row at a time?

View 9 Replies View Related

Calculate Work Hour Phone Time By Day, Week & Month

Aug 21, 2008

I am trying to figure out a way to count the minutes used from 8am-5pm Monday-Friday. I have this years worth of data. I would like to do it by month and by week and by day. I use office 08 for the mac and its my understanding that it doesn't have VBA. I would also like to be able to figure out if on a certain date a employee made over x amount of phone calls in a day. But have several employees. I have columns that are labeled date, employee, minutes used.

View 2 Replies View Related

Auto Open Macro To Find Correct Week Tab & Day/date In 52 Week Worksheets

Jan 19, 2010

I am new to VBA & not sure of the full understanding of code copied from a workbook which worked on the same principle but with Monthly (12) tabs. I thought if modified to show weeks, the macro would be able to locate the current week tab & day/date within - but upon opening, the cell stops at WK19 & column O - rather than WK43, Column N (which changes daily).

Sub Auto_Open()
week(1) = "WK1"
week(2) = "WK2"
week(3) = "WK3"
week(4) = "WK4"
week(5) = "WK5"
week(6) = "WK6"
week(7) = "WK7"
week(8) = "WK8"
week(9) = "WK9"
week(10) = "WK10"
week(11) = "WK11"
week(12) = "WK12"
week(13) = "WK13"
week(14) = "WK14"
week(15) = "WK15"
week(16) = "WK16"
week(17) = "WK17"
week(18) = "WK18"
week(19) = "WK19"
week(20) = "WK20"
week(21) = "WK21"
week(22) = "WK22"
week(23) = "WK23"
week(24) = "WK24"......................................

View 9 Replies View Related

Auto-updating Formula For Week Over Week Change?

Dec 11, 2013

I was wondering if there's a way to add a formula to calculate week over week % change automatically every week when I enter in new data. see the attached excel file for reference.

What I would like to have is the ability for the formulas in c5 and f5 to be able to auto-update to the newest week and the previous week's data instead of manually having to update it each week. So if I were to add a new row with data for week beginning 12/2, the formula in c5 and f5 would automatically update to calculate the week over week variance. I tried researching prior to asking the question on this forum, and I think it may be possible to do it using the index match function, but I'm not sure how to apply it in this case.

View 3 Replies View Related

Delete And Insert Record Week On Week

Aug 6, 2008

I have a comparison model that looks at two weeks of data. I am trying to get around the deletion and insertion of records week on week. With the code below, I can currently find and correct the deletions and insertions to the list, and then resort the list so that the comparison will work.

Sub CheckForNewProjsRemovedProjects()
Dim MyCell As Range, oCell As Range, NewCell As Range
Dim Rng1 As Range
Set Rng1 = Range("A1:A" & Range("A" & Rows.Count).End(xlUp).Row)
' Columns("B:B").Select
Range("B1:B" & Range("B" & Rows.Count).End(xlUp).Row).AdvancedFilter Action:=xlFilterCopy, CopyToRange:=Range( _
"C1"), Unique:=True
For Each oCell In Rng1
For Each MyCell In Range("C1:C" & Range("C" & Rows.Count).End(xlUp).Row)
If MyCell.Value = oCell.Value Then................

View 9 Replies View Related

Week Number Caluclating Hours For Week

Mar 6, 2010

I have a running time sheet daily. It has 2 columns for Labor and 2 columns for travel
i.e. travel From / To 1300-1400 calculate 1 hour then travel home 1600-1700 1 hour this is calculated by the date entry 01/02/10 I have another calculation that tracks by the date i.e. 01/02/10 then Next job which all works fine.

The problem becomes how do I calculate a weekly total labor and travel by the date So added another column called weekly hour’s labor and use the Weeknum to determine which week is which day/date so the first Monday in January 2010 is week 2

2 problems
Having many multiple day / date entries are the same date x 7 days Monday –Sunday
(Relies on the date entered and the weeknum) 01/03/10 each line is complete however the dates carry over as does the time

When trying to calculate each row x 3 same date time then the value will be incorrect I need to calculate
Say 9.5 hour labor from the date 01/03/10 not 28.5 hours and then calculate the total weekly hours
01/03/10, 9.5 hours labor, 3 hours travel
01/03/10, 9.5 hours labor, 3 hours travel
01/03/10, 9.5 hours labor, 3 hours travel

i do have work and travel times for each job on the same line (separate columns) but I display the total here by date to summarize the totals
i have tried sum products and sumif to avail. I am using Windows XP SP2 with MS Office 2007

how do i calculate weekly hours by date and weeknum ?

Total Work per day

Total Travel per day

Daily....................

View 9 Replies View Related

Formula To Tell When Its Week 1 Or Week 2 Of A Any Given Month

Jun 16, 2014

I'm trying to write a formula that will tell me when its week one or week two, week three and week 4 based on a given date of any month.

I'm using weekday formula but no luck.

View 6 Replies View Related

Comparing Files From Week To Week

Feb 5, 2009

I have to download a report every week and have been manually checking the report weekly for changes.

View 5 Replies View Related

Formatting Date: Add The Month And The Text "Week" Before The Week Number

Nov 24, 2009

I have a column where I am convering the Date into a Fiscal week number.

For example 10/6/2009 is Work week 41
Now I want to show October Week 41

I need to add the month and the text "Week" before the week number. what is the formula I use.

View 3 Replies View Related

Copy Week Total In Weekly Sales Worksheet To Appropriate Week In Monthly Sales

Oct 14, 2009

I need to copy the values of a range on the weekly sales worksheet to the monthly sales worksheet. The last column is the total on the weekly sales. Part of the heading of the total column is the week ending date (e.g. 10/17/2009. On the Monthly Sales I have the months in columns by week ending (e.g. 10/17/2009).

Range I4:I28 to the monthly sales worksheet by date.

View 10 Replies View Related

Work Out A Formula For My Spreadsheet Which I Use To Work Out Cutting Lists For Timber Frames

Jan 11, 2009

i need to work out a formula for my spreadsheet which I use to work out cutting lists for timber frames. I need it to work out if the width of a job is for eg 2400mm i need to work out how many timber studs I need so the space between each stud is between 400mm and 500mm and this will need to work for a range of different sizes of frames. I have it written at the moment and it just devides the width by 400 and gives me a amount of studs but it would work much better if it could space them between 400 & 500.

View 4 Replies View Related

Work Accurately With Times To Calculate The Work Progress Of The People In The Workshop

Mar 3, 2009

In a project i am compiling i need to work accurately with times to calculate the work progress of the people in the workshop thus....here goes....

I have in work book #1 (7) sheets mon to fri + complete week + a sheet where all job numbers are collected.

From monday to friday the workmen log their times as a start time and a end time. This has to be then calculated to a total hours:mins spent per job, wich in turn then has to be calculated to a total hours:mins spent per day. And the on the complete week sheet recalculated as a total time worked per week.

View 9 Replies View Related

How To Get A Macro To Work With Any Work Book Name

Aug 24, 2009

i have a made a macro that copies info to a new sheet now that is working great but if i change the name of the work book it wont work any more so i need the macro to work with what ever name i give the workbook

the current name is

AVERAGE PRICE (update 2009) Mimmos Armico 170809.xls

i have attached the code in notepad ...

View 8 Replies View Related

Make To Display (0), Instead Of (-0,02) When I Just Do Other Work Than Cad Work

Feb 13, 2010

In column J, Cad Hrs. How to make to display (0), instead of (-0,02) when I just do other work than Cad Work? I need to separate type of work according to price hour, overtime, and so on.

View 2 Replies View Related

Convert Date To Year/week Of Year/day Of Week

Apr 6, 2007

Is it possible to format cells to convert a date format of month/day/year to = year/week #/day of week? For example, 04/05/07 (April 5, 2007) would read as 7145, (7=last digit of year/ 14 = week number / 5 = day of week....Sunday being the first day of week)

View 9 Replies View Related

Copying A Certain Range In A Work Sheet To Another Existing Work Sheet Using VBA

Dec 29, 2009

I have a range of cells in a work sheet "sheet 1 " my objective is to filter this range according to certain criteria (i ve succeeded to do this ) yet what i want to do now is copy this data to another existing worksheet in a certain range .

note :the existing worksheet to which i 'll copy the filtered data has some cells out of the range that i dont want to over write ..

Simply :how to copy a selected range of cells in a work sheet to already existing work sheet in a specific range aswell .

View 9 Replies View Related

Copy A Formula Across Several Work Sheet And Have The Formula Always Take Data From Previous Work Sheet

Jan 2, 2009

I am want to copy a formula across several work sheet and have the formula always take data from previous work sheet.

2) I am working with this formula =C12+INDIRECT((MID(CELL("filename",A1),FIND("]",CELL("filename",A1))+1,256)-1)&"!"&"C12")

and it comes from this thread http://www.excelforum.com/excel-gene...orksheets.html. I have included a worksheet attachment that has explanations

View 2 Replies View Related

First Day Of Week

Jun 21, 2006

How can i find the first day of a week

I have the week number and i need the date of monday of that week

Ex: Week number:24
First day of week(Monday):12-06-2006

View 5 Replies View Related

Day Of The Week

Jun 27, 2006

I need the name of the day of the week from a date that has to be put together. This is going into a label on a UserForm.

I have a named range called wbDate. It is the month & year. The day of the month is the value of a TextBox (TBDay) on a UserForm. When I tried to combine these items, I used this

vToday = Month("wbDate") & " " & TBDay.Value & ", " & Year("wbDate")

vToday is dimmed as variant.

I am getting a type mismatch error and I'm not sure how to correct it.

What I am aiming for eventually, is the name of the day of the week.

View 4 Replies View Related

Filter For Day Of The Week

Feb 11, 2014

In example file i wrote different dates along the column. How i can i write a filter in Table for showing only Thursdays from those dates?

File: [URL] .....

View 7 Replies View Related

Add Totals By Week

Oct 9, 2008

Does Excel know week numbers? e.g. Week 40 is Sunday 10/5/2008 to Saturday 10/11/2008. Here's what I have...

Column A Column G
date $ Amount

my data example...

10/5/2008 $10.00
10/5/2008 $20.00
10/8/2008 $12.00
10/11/2008 $8.00
10/12/2008 $25.00
10/13/2008 $75.00

What I want the formula to do is look in Column A find all of the dates that are in week # whatever and then look in column G and add all of those $ amounts. So the result would be...

Week 40 $50.00
Week 41 $100.00

View 3 Replies View Related

Month Day Day Of Week

Nov 2, 2008

1 2 3 4 5 6
11/1 11/2 11/3 11/4 11/5 11/6
sat sun mon tues wed thur

what i am trying to do is to be able to put a date in a cell and it would fille in the month day and day of week

=$D$1
=$D$1+E5-1
=TEXT(WEEKDAY(D6),"ddd")

cells are not correct in the formulas just copied them. i got this to work in a set up xls file when used it in the real setting i get ###.

View 3 Replies View Related

Group By 'week'?

Apr 6, 2009

I created a pivot table with daily dates listed from 1/1/2009- 3/31/2009. 3 months worth. I see i can group this data by hours, days, months, quarters and years but what i really need to do is group this by WEEK. Does anyone know a formula I could use to accomplish this?

View 3 Replies View Related

Evaluating The Day Of Week ?

Jun 5, 2009

Can somebody have a look at the workbook that I've attached.

I have set up a timeshhet calculator for work but the thing is, the hourly rates of pay are dependent upon the day of the week the Operative is working, and the time of the day.

We split the shifts AM & PM and the rates are decided as per the worksheet contained within the workbook "Rates".

The problem I am having is how to get the timesheet to understand the days.

For example, if an Op works the Sat night or Sun night, then the rate should reflect x1.5. If it's Sat/Sun daytime, then it's x1.25.

Again, and as per the "Rates" sheet (see top for the rate multiplier) Mon - Fri 09:00 - 17:00 is flat rate/standard hrs. If the work Mon - Fri evenings, then the rate is x1.25.

How can this be done?

View 10 Replies View Related

Looping Through Day Of Week

Mar 17, 2009

I'm trying to set up a simple macro to loop through some number of dates on a sheet and blank out fields next to every instance of Saturday and Sunday. The only problem I'm having is actually finding the values "Saturday" and "Sunday"

Given a date in this format: 01/01/2009
I can convert to "Thursday"

Problem is, the vba code still "sees" 01/01/2009

I've tried copy / paste special / paste values to no avail.
I've tried changing it via VBA (a few different methods, including strings, formats, etc) with no luck. Even tried referencing my date cells from another spreadsheet and pasting the values back in. Can't seem to get 01/01/2009 to be "Thursday"

View 4 Replies View Related

How To Set Monday As First Day Of Week

Jan 26, 2014

Outlook allows you to easily specify, but eExcel always treats Sunday as the first day of the week by default. Yes you can manipulate that within formulas and functions, but if you use the autofilter in excel and choose "this week" (or "next week", or "last week") excel considers Sunday as the first day of the week. I would like to know how (or if) this can be changed to Monday as the first day of the week.

View 5 Replies View Related

[VBA] Day Of Week Filtering

Sep 16, 2007

I've been trying to write code to filter a list of date base on day of week (Mon, Tue, etc)

My problem is that i can't find a way to code the filter criteria... since the date does not contain any week of day constant. i don't want to create another column in my sheet to show the week of day constant and filter this instead.

Here's my not yet finished code...

Sub DayOfWeek()
Dim sAnswer As String
Dim bWkDay As Byte
Dim loMyData As Range
Dim iFilterCriteria As Integer
Dim Dateserial As Integer
Application.ScreenUpdating = False

sAnswer = InputBox("Please select day to display data (first 3 letter of the day, eg. mon)", Title:="Select day to display")

View 9 Replies View Related