Calculating Average Days Overdue Per Department?
Jan 20, 2014
I have a file that's almost 3000 rows of data I have attached a test file for the purpose of this request. I am trying to figure out the average days overdue per department whose due dates have not already passed.test (1).xlsx
View 2 Replies
ADVERTISEMENT
Jun 17, 2014
I have the following:
A1 = Date item is due. (DD/MM/YY format)
A2 = Time the item was delivered (HH:MM:SS format)
B1 = Actual Date item was delivered.
B2 = Actual Time item was delivered.
I'd like C1 to count the number of days the item was late. - taking into account that 16:00:00 is the deadline on each date.
For example:
Due Date: 17/06/14 @ 16:00:00
Arrival Date: 17/06/14 @ 16:01:00
Days Late = 1
Due Date: 17/06/14 @ 16:00:00
Arrival Date: 18/06/14 @ 15:00:00
View 10 Replies
View Related
Jun 17, 2014
I have the following:
A1 = Date item is due. (DD/MM/YY format)
A2 = Time the item was delivered (HH:MM:SS format)
B1 = Actual Date item was delivered.
B2 = Actual Time item was delivered.
I'd like C1 to count the number of days the item was late. - taking into account that 16:00:00 is the deadline on each date.
For example:
Due Date: 17/06/14 @ 16:00:00
Arrival Date: 17/06/14 @ 16:01:00
Days Late = 1
Due Date: 17/06/14 @ 16:00:00
Arrival Date: 18/06/14 @ 15:00:00
Days Late = 1
Due Date: 17/06/14 @ 16:00:00
Arrival Date: 18/06/14 @ 16:01:00
Days Late = 2
View 3 Replies
View Related
Nov 24, 2009
to calculate how many days of each different leave type have been taken for each Cost Code within an Excel 2003 spreadsheet. What adds to the problem is that the data extracted from our system comes to +/- than 50 000 lines. So doing this manually is out of the question.
I have attached a spreadsheet containing an extract of the information (DATA Tab) to better understand. Under the Summary Tab I have the format in which the information must be presented. For each Cost Code/Department I need to calculate how many e.g. Annual Leave/Sick Leave/Other Leave etc. was processed for each month from January to end of October.
Has anyone dealt with something similar? I would really appreciate any assistance as this problem is way above my Excel skills (not that it’s actually above average in any case... ;-)
View 9 Replies
View Related
Mar 9, 2009
I am producing a spreadsheet that will track returned defects. Column B is where I input the department variable. In a new table on the same sheet I need a formula that will count department names and give me a total for the returns for each department.
View 6 Replies
View Related
Sep 15, 2008
What I would like to do is insert a formula into column E that would calculate the number of days from when the count is at 50 to when the next count is i.e. for part 6689841 the time between when the count was 50 and when it was at 20, so the difference between 21/01/2008 and 08/08/2008 in the above example. It does not matter what the count number is (it could be any number except 50), I'm only concerned with every time the count is at 50 how long it is until the next count and to show the result in days.
View 9 Replies
View Related
Apr 2, 2014
I know how to calculate the duration elapsed between start and finish time. But how can I display the total time if for eg it's ends up being 300hrs?
I need the hours spent in the building per day and then the grand total per month.
View 1 Replies
View Related
Dec 12, 2008
I have a spreadsheet where I record individual staff start time, end times and the length of their break. From this I caculate the hours they worked for the day.
E holds Start, F holds End and G holds Break length. Thus using the following forumula gives me the number of hours and minutes:
View 4 Replies
View Related
Mar 9, 2007
I am trying to calculate the number of days that items are were held in inventory as of a given date. See below for some sample data.
'As Of' - the date in question
# Holdings - Using sumproduct to find items bought on or after the date AND sold after the date
Held Days - ? Total number of days that the six items were sitting in inventory as of the date.
As Of #ItemsHeld Days
5/21/98 6
ItemBoughtSoldTotal Inventory Days
19/3/919/3/961827
21/2/921/2/971827
31/2/921/2/971827
43/2/928/21/951267
55/1/925/1/971826
65/1/925/1/971826
View 9 Replies
View Related
Nov 3, 2008
If I had two dates in two separate cells , so E2 is the 01/10/08 and F2 is 06/10/08 and I want to work out that their is a difference of five days what would the sum be? Also is there anyway I could factor into that sum what is pure working days as opposed to weekends?
View 9 Replies
View Related
Apr 11, 2014
I am trying to determine a formula that will tell me what the date will be 61 days and 90 days from a selected date. For example:
A1: 04/11/2014
A2: (Date 61 days from date in A1)
A3: (Date 90 days from date in A1)
Is this possible??
View 6 Replies
View Related
Dec 3, 2013
I am trying to calculate the time elapsed. I have included a caption to show my formula. The problem I have is that some times are showing > 60 minutes instead of increasing the hour. When my day go over the midnight hour I get a negative number.
View 11 Replies
View Related
Feb 4, 2010
I recently manage to create a spreadsheet. On the spreadsheet what I am looking to do is once I change the year in cell U1 from 2010 to 2011 to automatically change the days and the date number, and where Sat and Sun preferably to auto-fill in yellow the whole column within the table as you can see in the spreadsheet.if not then just do not display Sat/Sun columns at all..
View 5 Replies
View Related
Aug 5, 2008
I need a formula that will allow me to put a date in cell a2, and in cell a3 put the the number of days between 2 dates. Example.. For example (A2) shows 08/06/08, a3 to show the number of days from 08/06/08 to 08/14/2008--(a3 )14 and (a4) to shows the number of days from 08/06/08-10/05/2008 ---(a4) 60 days.
View 5 Replies
View Related
Mar 9, 2009
I am trying to calculate dates that will happen 16 days from date specified in column A (A23:A200), based off a certain entry in Column B (B23:B200), which is named in cell P5. I can get the date by doing the specified date + 16, e.g. =IF($B$23:$B$200=$P$5,$A23+16,"")
The trouble I am running into is not having the date populate until it has reached 16 days from the dates in column A, show blank if possible until 16 days from date in column A. The dates in column A will always be previous to todays date.
View 2 Replies
View Related
Aug 15, 2010
how can i calcaulate working hours between two days.
Working Hours 07:30 - 14:30
e.g. mm/dd/yyyy
start time 01/04/2010 17:34:58
stop time 01/05/2010 08:23:35
View 9 Replies
View Related
Oct 23, 2007
I have a static date and military time in B6 (5/10/07 18:00) I have to write various formulas to reflect 1 month (whatever calendar month it ends up in, so not necessarily 30 days) minus 7 days and then the same formula plus 7 days. How is this written?
View 9 Replies
View Related
Oct 8, 2008
I need to create a formula that calculates the number of days a person has worked within a quarter, if they have also left the organisation within the same quarter.
For example, I have someone who left on 26/08/08. I need to establish how many working days this person actually worked within the quarter (01/07/08 - 30/09/08). I need to do this for a large number of staff, so would appreciate it if anybody can let me know whether there is a formula that would calculate this.
View 9 Replies
View Related
Feb 7, 2007
is there a way to calculate the number of days between two dates using the excel cells
example.....how do i put in formulas so excel will calulate the number of days between May 3rd and september 19?
i want to enter may 3 in say a1 then sept 19 in a2 a3 should says days between em
View 3 Replies
View Related
Oct 17, 2009
my spreadsheet is setup with two dates: A date for when someone joins our group A date for when they are released/leave
I want to be able to see exactly how many years/months/days transpired between these two dates. I have tried lots of different formulas with no success.
View 12 Replies
View Related
Jan 1, 2009
I'm using Excel 2003, and successfully working out start date (T2 in the formula below) plus duration in days (U2) minus any non-working days listed in a seperate worksheet. =WORKDAY(T2,U2,Holidays!C6:C17)
Each 'task' is on a seperate row, and the lead officer is named in Column E. How can I get the work day function to include the non-working days for each officer as well as the global non-working days in the seperate worksheet? I thought about using a vlookup, but that only matches the first non-working day for each officer rather than all of the non-working days.
View 2 Replies
View Related
Mar 16, 2009
I'm trying to calculate the length of a work order to develop an average and future proposal estimates.
For example:
Job received = A1
In work = B1
Job completed = C1
Total days to complete = D1
I know I can enter in D1 C1-A1 and get the correct result but I want the field to calculate A1-TODAY() until a completion date is entered. This would display the number of days the job has been in work until completed. Once completed use the C1 for calculation.
Sorta like
If(C1=">=0" then (A1-Today()) else C1-A1)
I will then use conditional formatting with block colors to indicate whether it is a completed job or in work job.
View 10 Replies
View Related
Jan 1, 1970
It should be deplaying dates of weekly days in Monday, Wednesday and Friday excluding sundays. Or Tuesday, Thursday Saturday excluding Sunday. e.g
Mondays, Wednesdays and Fridays of June
June 1, 2006
June 3, 2006
June 6, 2006
Tuesdays, Thursdays and Saturdays of June
June 2, 2006
June 5, 2006
June 7, 2006
This should be happening after entering any date on the first cell of the List and should accommodate up to 3 months
View 14 Replies
View Related
Aug 24, 2012
I'm building a schedule in excel and am having trouble with the calculation of total hours when lapsing a day, or more specific, adding it into my current equation. For example; Monday they clock in at 5pm and work till 1am. I have found a couple of ways to get the desired out come from this on it's own. I just add the value of a day if the out time is less than the in time, or if the out time minus the in time is less than 0.
However, I need to add this calculation into an equation that is already calculating time elapsed within a single day, turning that into a decimal number and then checking if the total time elapsed is less than 6 hours, if false it subtracts a thirty minute break. Here is the current equation I'm using, I'm sure that there is an if(or, or if(and I could use to make it work when the time lapses 12am while also performing the 6 hour check to subtract the break.
=IF(((F7-INT(D7))*24)-(D7-INT(F7))*24
View 2 Replies
View Related
Mar 14, 2013
I've managed to sort the first half of this issue, in that I can calculate the number of days within a given month which fall inside specified to and from date parameters..
The formula I've used is thus :
Code:
=IF(EOMONTH(A13,0)EOMONTH($I$9,0),0,IF(EOMONTH(A13,0)>$I$9,$I$9-(EOMONTH($I$9,-1)),EOMONTH(A13,0)-(EOMONTH(A13,-1))))))
This examines a date value (A13 in this case) and assess whether any days within that month are between the two date parameters specified in H9 and I9.
H9 = 01/01/2011
I9 = 15/05/2011
Jan-11
31
[Code]....
What I need to do now is specify a second set of date parameters in H10 and I10 and add those into the assessment. The dates will NOT overlap.
So, for example, if I were to set H10 as 01/07/2011 and I10 as 15/07/2011, the results would appear as below
Jan-11
31
Feb-11
28
[Code].....
View 3 Replies
View Related
Dec 31, 2013
Calculating Number of Business Days Between Two Dates?
View 9 Replies
View Related
Apr 19, 2006
I have a spreadsheet where I have an intial date of issue of a warrant. Once this warrant has been executed, then a further column is populated with the date. The data I need to work out (Preferably without using macros if possible) is, if there is no execution date the length of time from issue to todays date, but if there is an execution date then length of time from issue to execution. I can do either on their own, but i would like to have only one column showing this info and if possible to update each time the sheet is opened
View 6 Replies
View Related
Jan 30, 2014
I am using the following formula in Column E to calculate the difference between an employees start time, and their previous shift end time in order to work out how many hours rest they have had:
=IF(A4=0,"",IF(I4=0,"",MOD(I4-B4,1)))
My Current Formula works fine for same day calculations, but if an employee finishes work at 18:00 on Friday and starts work at 22:00 Saturday night, Excel calculates the Total Rest hours as 04:00, when in fact they have had 28:00 hours rest...
Is there a way of calculating the hours difference between two dates?
I have attached a sample of my spreadsheet to illustrate
View 5 Replies
View Related
Aug 29, 2013
At the end of each month, my agency collects data about clients served in our programs. One of the many pieces of information they want is the number of "bed days" a client was residing within our programs for the given month.
For example:
Jon Doe entered the program on 7/16/13 and discharged on 8/15/13. I would like to know how to calculate the number of days in July that Mr. Doe was residing in the program. (The date of discharge is not included.)
I recently took over the responsibility of completing reports such as this one at my office. The previous person who completed the monthly reports would count the days by hand for each client, but I know there must be a better way.
View 6 Replies
View Related
Oct 8, 2009
I have several worksheets with thousands rows (independent variables) and hundreds columns (all dependent variables). Each line basically gives me hundreds values for each independent variable - see below:
...
C9 39.65 653.95 5.28 163.56 99.56 14.49 ... ...
E9 7535.92 21500.56 2835.88 3122.98 7225.34 5371.25 ... ...
G9 111568 298021 12940 31645 181797 36996 ... ....
...
I need to know how the values in each row are distributed, and I ideally plot a 2D column graph of the distribution. Is there a way to do that and create/program a macro (with relative button on the workboook) that does it automatically once clicked?
Very often there are outlying values (bigger or smaller by a factor of 1000 or even more), mistakes, which I would like to identify and fix possibly
View 10 Replies
View Related