I am trying to count the number of dates in a column that are within the last 180 days. I tried using COUNTIF and it did not work. Formula which I thought should work: =COUNTIF(A3:A32,>(A40)). My workaround is shown in Column B, but this method adds one column for each participant.
View 5 Replies
ADVERTISEMENT
Jan 15, 2009
Today I am having a very annoying problem that really has me stumped – I need to work out the lag between a Due Date and Delivered Date
But as people sometimes manage to deliver on the Due Date it needs to show a zero (as in they got it in on time) but using the formula below the result is a 1 and I want a zero
Can anyone help me please? I have tried putting assorted -1s in to the formula and it looks like it might work until I copy down and find that if a person delivered one day early the result shows -3 for example!
View 7 Replies
View Related
Apr 13, 2007
vba excel?
I wish to calculate the days between the starting date (column A) and ending date (column B). For the first 7 days are excluding all the holiday and weekend and the rest of it until the ending date are counted.
View 9 Replies
View Related
Mar 17, 2009
I have a question, does anyone now how to count between dates, for exemple :
01-02-2009
15-02-2009
22-02-2009
25-02-2009
03-03-2009
11-03-2009
And i wont only to count between 01-02-2009 / 28-02-2009, the result it will be 4.
View 14 Replies
View Related
Mar 28, 2014
Need a formula (E1) to determine the number of days that have passed between two given dates (C1 & D1) ONLY when the Status of a given report (B1) is "Late"
B1 = Status (Pending; On Hold; Late; Completed) (i.e "LATE")
C1 = Status Date (i.e. 28 Mar 14)
D1 = Deadline (date) (i.e. 25 Mar 14)
E1 = Total Days Late (= ?)
Note: I'm using Office for Mac 2011
View 1 Replies
View Related
Jan 5, 2007
I have a range of dates. i would like to count the number of days that are earlier than the date =TODAY().
Do i use the COUNTIF function?
View 9 Replies
View Related
Jan 23, 2014
I need to count the actual number of days between 2 dates but excluding Sunday...
For example,
Start Date-----End Date-------# of Days
01/Jan/14-----23/Jan/14-------20 days (excluding Sunday)
In some cases, Holiday also to be removed i.e. 01-Jan-2014 is holiday, then the # of days should be 19 days.
If I use Networkdays formula, then system results excluding both Saturday and Sunday. But I want to remove only Sunday.
View 5 Replies
View Related
Nov 12, 2008
I need to figure out how to tell Excel to count the number of invoices on a worksheet older than 30 days and display that number in my Summary worksheet. Here's a quick example:
Worksheet '1234' has 10 invoices, 6 of which are more than 30 days old (invoice dates are in column B). Worksheet 'Summary' needs to display the total number of invoices and the number older than 30 days.
View 2 Replies
View Related
Jan 22, 2008
I want to be able to count the number of days in a specific year between two dates.
Suggested formula input: DaysInYear(Date1,Date2,Year)
Examples:
DaysInYear(3/3/2005,3/3/2006,2006) should return 62 (31 in Jan, 28 in Feb and 3 in Mar.)
DaysInYear(3/3/2005,3/3/2007,2006) should return 365
View 4 Replies
View Related
Apr 26, 2011
I work only on Wednesdays and Thursdays. I'd like to calculate the number of my working days between two dates.
NETWORKDAYS seems like the right place to start, but I can't think of how to tell it to ignore Mondays, Tuesdays and Fridays as well as the weekend days.
View 5 Replies
View Related
Aug 4, 2008
I have been using a formula to count the number of days between 2 dates and if the date was older than 12 months it would work fine.
The data that i was using has been changed and they have decided to change the format of the dates and dropped the year reference no all i have to work with is dates like 27-07 this represents 27th July i can format this date to work fine unless the date falls before 1 jan this year all i get is lots of numbers and it stuffs up the whole calculation.
The formula i am using to compare the dates is
=DATEDIF(N31,$D$1,"d")
View 9 Replies
View Related
Feb 28, 2008
I am trying to compile a count of dates using a numerical reference which adds x consecutive dates onto the initial start date based on the number in a cell.The dates added cannot fall on a weekend.
The start date for each calculation begins in D4 with the corresponding number of days to add onto this date in K4. In the example below 8/11/2007 -- 2 means that the 8th and 9th of Nov get one added to their count. As the next row also has 9th Nov as a start date one more is added to 9th Nov. As the 10th and 11th were a weekend they are skipped and the count starts again from the next Monday. I have enclosed a simplified worksheet with some sample data.
Example:
D4 --------- K4
8/11/2007 -- 2
9/11/2007 -- 3
Expected output:
AE4---------AF4
8/11/2007 -- 1
9/11/2007 -- 2
12/11/2007 --1
13/11/2007 --1
View 5 Replies
View Related
Feb 13, 2013
I wanted to determine the number of days between two dates. Specifically, if the initial date is in one month, and the second is in a different month and an output would result a number of days in each month until the final date. BUT I have a large amount of data to do this for in a list view, way to put a formula in excel and just drag down the entire list to get the required information. see below for an example.
The result I'm looking for is the separate the months and only show the relevant months between the two dates in one cell or the adjacent. Something similar to the table outlined below.
Input Data
Result
Start Date
[Code]....
View 3 Replies
View Related
Aug 7, 2014
Trying to count how many days from a set range of dates are within another range.
So for example, the first two dates, 7/29/2014 - 8/5/2014 would be 6
7/31/20148/6/2014 are the set dates
Count Days Within Range.xlsx
View 4 Replies
View Related
May 27, 2012
There are dates in column C and I need to count how many days are coming due within 90 days of each date based on the today() function but do not exceed the 90 days.
Countif Today()+90
View 5 Replies
View Related
Mar 14, 2014
I am making process TAT(Turn Around Time) which required following information. In Excel 2007.
1-Count number of days between two dates where working days are (Sun to Thursday). So required to exclude (Friday,Sat + Holidays)
A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 22
D1-Days between two dates 21
E1 To E10-Holidays
2-Count number of days between two dates where working days are (Sat to Thursday). So required to exclude (Friday + Holidays)
A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 27
D1-Days between two dates 26
E1 To E10-Holidays
Note : Any weekend (off days) dates listed in holidays should not effect the query.
View 9 Replies
View Related
Feb 23, 2014
Here is my set up:
A2 to BF2 is a range of dates
A3 to BF3 are sales. Days without sales are 0.00
I want to pick a range of dates and find the number of days without sales between those dates. So, a formula that will look to a start date in A1 and an end date in B2, and then count the number of days that did not have sales between. Index/Match/Countif/Dateif I can't seem to make anything work.
View 3 Replies
View Related
Sep 28, 2011
I need a formula to count how many days hours & mins between 2 dates but included in the formula need to ensure it only counts business days.
Column A 02/09/2011 13:00
Column AO 02/09/2011 13:02
I need in Column AP to show 0 00:02
The formula I have tried using is - =IF(AO3="","",AO3-A3) which doesnt work as instead of showing 0 00:02 it shows 1 00:02. I dont want it to count as 1 day just 2 mins.
Once that has been worked out I need to include WORKDAYS formula to only count working days. I have created the list on 'Controls' Tab Column A10:A47.
merge these together to create the one formula?
View 6 Replies
View Related
Jun 16, 2008
I have been using: =DATEDIF(A1,B1,"md") & " days" to calculate the difference, in days, between two dates in a speadsheet, however, the number of formulae in the spreadsheet now is cumbersome so I'm trying to put it together in VB.
View 2 Replies
View Related
Jan 27, 2006
Basically I have 2 columns each with a list of dates in no particular order (and containing blank cells too), one planned date column and one actual date column.
What I need to do is plot this on a graph, and since the number of dates has no set limit and I dont want to have to plot maybe 100 dates on the x axis, so i want to group them by week before plotting them, i.e. 10 dates for week ending 10th jan, 25 dates for week ending 17th jan etc
I have a pivot table that counts how many of each date occurs, i.e. 10 x 2nd jan, 7x 3rd jan etc etc but it does not split them into weeks.
im sure theres an easyish way of doing it so i can get the 2 lines on the graph for no. of planned dates each week and no. of actual dates each week, i just cant see it.
View 13 Replies
View Related
Feb 4, 2010
In Cells B2:B100, i have dates that which have been entered using a combo box (the dates type is for e.g. 14th March 2010 format)
I want a formula that will count the cells that have dates between 1st April 2010 to 30th June 2010 in cells B2:B100
Also, I would like a formula that counts weekend dates between 1st April 2010 to 30th June 2010?
View 9 Replies
View Related
Jun 4, 2014
So, it is for a hotel, I need to know to know between a Check-in and a check-out date, each day (monday, saturday) there is. In depending it is for one night or 12.. I will try to be clear: Depending on the channel of booking and the day of week we have a % of commission different. so I want to put the price in one cell and it is calculate for each date in order at the end I have the right net profit (because the right commission has been applied). Of course to complicate the commissions do not apply in the same order depending the channel and there are fixed costs which are count one time or repeat by the amount of nights. For the these things what i did seems work.
After, my boss would like to link the dates with another excel file which say for each date which "level of price" (price point) is applied and function of this Price Point we have the price applied per room type and offer
But for now, I didn't find anything what can say to me between 2 dates what dates are between...
View 2 Replies
View Related
Jun 18, 2014
How to find the difference between 2 dates in days ,eg,12/10/14 and 14/10/14 = 2 days on a spreadsheet.
View 4 Replies
View Related
Oct 9, 2007
a count formula.
Right, Column A on my sheet is the date that the work was completed. First thing is I need to be able to count how much work was completed per month. (I dont know why we have it all in one big sheet rather than monthly sheets but thats too logical!)
Secondly, column I is the number of days that piece of work took to complete. I need to be able to have a formula that looks at the month the work was completed, then total up the number of days that the work took.
(Example, if I have three bit of work completed in October, 1 took a total of 20 days, 1 took 15 and 1 took 10 it would = 45 days)
I know that this should be possible as I've had Excel doing more complex formulas than this.
View 14 Replies
View Related
May 24, 2007
I have a start date (say 01/04/07) and I need to add a number of days to it to get the start of the next financial period. Unfortunately, I need to ignore a small list of dates (bank holidays, etc).
View 9 Replies
View Related
Nov 10, 2008
I am trying to set up a function to derive a number of days between 2 dates.
Within the table I have an on hire date, and off hire date, and an optional suspend hire date range in 2 other columns - ie. there are 4 columns with dates in.
On hire is in column B; offhire in C; suspend hire in G and recommence hire in H. The optional suspend hire date range will always fall within the main hire date range.
Column I calculates the number of days for the suspend hire period.
My key cut off date is in cell C4.
There are 3 different scenarios I need the function to cover.
1 - if the cut-off date (in C4) is later than recommence hire, calculate the number of days from hire start to cut-off date, less suspend hire period days.
2 - if the cut-off date (in C4) falls within the suspend hire period, calculate the number of days from the hire start to the begining of the suspend hire period.
3 - if the cut-off date (in C4) falls before the suspend hire period, calculate the number of days from the hire start to the cut-off date.
This is the fuction I have written:-
=IF($C$4>H10*($C$4-B10-I10),
IF(AND($C$4>G10,$C$4
View 9 Replies
View Related
Apr 8, 2009
I have a formula in column E: =NOW() for the date.
I need a Formula in Column H from H11:H300 such that:
i) when a date is entered in G11 the number in Cell H11 should be a difference between G11 and D11 as in rows 11, 13, &14 and
ii) Until a date is entered in cell G11 the difference should be between E11 and D11 as in ROW 12
Below is an example of what I want.
D E F G H8 Date Days9DateStatus as of Expected ActualTOTAL10out of order8-Aprin orderin order114-Mar8-Apr14-Mar101210-Mar8-Apr29134-Mar8-Apr6-Apr33141-Mar8-Apr31-Mar30
View 9 Replies
View Related
Jul 3, 2007
I couldn't find a solution to my problem in the forum: Is there are formula that will allow me to calculate number of days between two dates? The date format is eg. 07/06/07
View 3 Replies
View Related
Jul 25, 2007
I have a simple formula to work out the number of dates between to dates
ie: =U6-T6
This works out the days between 9 may and the 31may as 22 days
but i want to show the correct number of days including the 9may so this would be 23 days.
I tried this =U6-T6+1 which was fine but all the empty cells now show the value 1 in them.
View 5 Replies
View Related
Aug 20, 2007
I am trying to create a spread sheet in excel that will show a number of days past due counting from the due dates. see the attached xls file for details.
View 5 Replies
View Related