Excel 2003 :: What Date Will Be 45 Working Days After Today
May 20, 2012
I need a function to work out what the date will be 45 WORKING days after today(), this function needs to exclude Saturdays, Sundays and any Public Holidays i.e. there could be either 10 or 12 weekend days added into the calculation depending on when today() is plus any additional Public Holidays.
I am using Excel 2003 although it will need to work in Excel 2010 shortly.
View 4 Replies
ADVERTISEMENT
Jan 17, 2013
Cell B1 contains a date, then B2 contains a formula that says:
=IF(A1>TODAY(),A1,A2)
A1 contains a green tick and A2 contains a red cross.
What I am trying to add is that if B1 contains no date then B2 needs to be blank.
I tried using =IF((A1="",0),(A1>TODAY(),A1,A2) to get it to show a 0 if there was no data but this doesn't work.
I am using Excel 2003.
View 4 Replies
View Related
Apr 25, 2014
I'm in Excel 2010, and the cell with the date I want to work from is H22.
I'm trying to get the difference of the (date+12 months)-TODAY() to appear in months and days.
Here's the latest thing I tried (that doesn't work):
=IF(DATEDIF(H22,TODAY(),"y")>=1,DATEDIF(H22,TODAY(),"y")&" yrs, "&DATEDIF(H22,TODAY(),"ym")&" mths,
"&DATEDIF(H22,TODAY(),"md")&" days",IF(DATEDIF(H22,TODAY(),"ym")>=1,DATEDIF(H22,TODAY(),"ym")&" mths, "&DATEDIF(H22,TODAY(),"md")&" days",DATEDIF(H22,TODAY(),"md")&" days"))
I should also probably note that the date in H22 is the result of another function.
=EDATE(G22,12)
View 5 Replies
View Related
May 27, 2012
There are dates in column C and I need to count how many days are coming due within 90 days of each date based on the today() function but do not exceed the 90 days.
Countif Today()+90
View 5 Replies
View Related
Jun 25, 2010
I am having difficulty calculating the number of total overlapping days between several date ranges (6 of them to be precise)
I am using Excel 2003 and my data looks like this:
Sent Out (A) - Received (B)
01/06/2010 13:00 - 30/06/2010 13:00
02/06/2010 13:00 - 16/06/2010 13:00
09/06/2010 13:00 - 10/06/2010 13:00
21/06/2010 13:00 - 25/06/2010 9:44
23/06/2010 13:00 - 25/06/2010 10:56
23/06/2010 13:00 - 29/06/2010 13:00
I really can't wrap my head around the idea of calculating overlap (in network days) between six date ranges and was wondering if any of you would have a solution to this problem.
View 10 Replies
View Related
Jan 6, 2014
I am having difficulty calculating the number of total overlapping days between several date ranges for each item in another sheet which has unique items
I am using Excel 2003 and my data looks like this:
Sheet-1 Sheet-2
Item - Sent Out (A) - Received (B) Unique Item Number of days excluding overlap days
1234 01/06/2010 - 30/06/2010 1234 -
4321 02/06/2010 - 16/06/2010 4321 -
1234 09/06/2010 - 10/06/2010
4321 21/06/2010 - 25/06/2010
1234 23/06/2010 - 25/06/2010
4321 23/06/2010 - 29/06/2010
I have used the below formula found from the earlier post but need to add a condition calculating the days for each item.
=SUM(IF(MMULT((NETWORKDAYS(ROW(INDIRECT(MIN(INT(A2:A7))&":"&MAX(INT(B2:B7)))),2)<6)
*(ROW(INDIRECT(MIN( INT(A2:A7))&":"&MAX(INT(B2:B7))))>=TRANSPOSE(INT(A2:A7)))
*(ROW(INDIRECT(MIN(INT(A2:A7))&":"&MAX(INT(B2:B7))))<=TRANSPOSE(B2:B7))+0,ROW(A2:A7)^0),1))
View 6 Replies
View Related
Apr 8, 2009
I am trying to get the results of the number of days between today and a future date. I am using ="cell containing futuredate"-today() and it gets me the correct number of days. The problem comes in when I have yet to populate the future dates. I am getting -39991 (numeric value between today and jan 01 01) and because I am also using conditional formatting this is even more of a problem. Is there a way get excel to display nothing if it is a negative number? or to give a specified resut if the number becomes negative such as Expired or something of that nature?
View 3 Replies
View Related
May 19, 2009
I need a formula that will calculate the number of days from a date entered into cell A1 to today's date. Whether it's before or after todays date. Example:
5/10/2009 to today is -9
5/22/2009 to today is 3
View 2 Replies
View Related
Sep 18, 2008
I have a worksheet that has a sent date and expected delivery date I need create a macro that will alert me if today's date is within 5 days of expected delivery date.
View 14 Replies
View Related
Mar 16, 2014
I am looking to have a dropdown list (1-30 days) to add the selected number of days to today's date. The number selected in cell B2 adds that number of days to today's date in C2.
View 3 Replies
View Related
May 18, 2006
I need to calculate on a spreadsheet the number of days between a specific date and the date the spread sheet is opened. I need to know the number of days a merchandise has been stored.
View 5 Replies
View Related
Feb 21, 2014
I'm trying to create a new column which calculates the number of days from the today's date to the due date of an invoice. Also a Column that an invoice is/was overdue.
Column A - Clerk inputs date that invoice was received
Column B - Clerk inputs the date that the bill was paid
Column C - Auto populates the due date of the invoice (20 days after the invoice is received)
Column D - I want a number of days to auto populate based on today's date that will show how many days we have to pay the bill. Example: today is 2/19/2014, bill is due 2/22/2014 (Column C), column D should read 3 (I would prefer is the number is black for "we have days left to pay", red for "we're behind")
*Extra bonus for Column D, if the column goes blank after a date is entered into Column B* - but not necessary
Column E - I would like if the date the bill was paid (Column B) is greater than the date the invoice is due (Column C) to show "Overdue" in the cell.
View 9 Replies
View Related
Jul 8, 2014
If cell a1 equals todays date add cell b2s value to it and put the new date back into cell a1.
View 6 Replies
View Related
Jan 25, 2010
I have a workbook in excel 2003 which I had been running the following macros (listed below). We recently upgraded to Excel 07, and neither are working. When I try to run them, the "debug" option highlights the following line in the sort macro "Range("A2:z" & lastcell).Sort key1:=.Columns(1)". This is driving me crazy, as the macros worked perfectly under the older version of Microsoft. Is there an issue with crossfunctionality between '03 and '07'.
Private Sub Worksheet_change(ByVal target As Excel.Range)
If target.Column = 1 Then
ThisRow = target.Row
startRow = 1
i = 1
Set ws = ActiveSheet
maxRow = Cells.SpecialCells(xlLastCell).Row
maxCol = Cells.SpecialCells(xlLastCell).Column
ActiveSheet.UsedRange.Interior.ColorIndex = xlNone
Do While i
View 9 Replies
View Related
May 25, 2014
I am now trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.
View 1 Replies
View Related
Jun 11, 2014
I have spent too many hours Googling and trial with mostly error in attempting this. I formatted the very first cell A1 for today's date =TODAY(); this is also dirrectly above the column with all the dates in it. I just want an entire row's contents to turn red if it is 15 days old or older. This =$A1<TODAY()-15 somewhat works, but it only turns the date cell red, not the whole row. It also makes blank cells turns red, which I would like to remain blank (another formula is needed I imagine).
View 3 Replies
View Related
May 26, 2014
i am trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.
View 4 Replies
View Related
Feb 2, 2014
I need cell (O4) to display days overdue or days remaining on an assigned task based on subtracting due date (M4) from todays date, but only perform days subtraction function if (M4) is not blank and only if task complete cell (N4) is less than 100.
Have the conditional blank cell figured out, but nesting another condition for the less than 100 complete cell. So in other words, I don't want cell (O4) to subtract days and display any error, irrelevant data if there is not any due date entered or the task is entered as complete...
View 3 Replies
View Related
Dec 17, 2008
I have a worksheet where in column B I have a vendor name, column E I have a date value and in column AF I need to calculate a due date based on 7 working days for vendor A and 14 days (not working days) for vendor B. I've tried to write an IF statement but can't do it. Can anyone suggest the right combination of IF/AND statements that would do this? I attach the workbook should my useless attempt at explaining my problem be unclear...
View 3 Replies
View Related
Feb 21, 2012
when I use the above key stoke nothing happens in excel. It won't get me into vba editor??
using Dell laptopInspiron N4010 and office 2003
View 2 Replies
View Related
Mar 14, 2014
I am making process TAT(Turn Around Time) which required following information. In Excel 2007.
1-Count number of days between two dates where working days are (Sun to Thursday). So required to exclude (Friday,Sat + Holidays)
A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 22
D1-Days between two dates 21
E1 To E10-Holidays
2-Count number of days between two dates where working days are (Sat to Thursday). So required to exclude (Friday + Holidays)
A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 27
D1-Days between two dates 26
E1 To E10-Holidays
Note : Any weekend (off days) dates listed in holidays should not effect the query.
View 9 Replies
View Related
Dec 1, 2006
how do i get the previous days working date in VBA, how can i get VBA to determine wether we are in the week, and how will i get it to know its a monday to retrieve fridays date?
View 3 Replies
View Related
Nov 12, 2013
why my undo just won't ever work. Excel 2003.
View 1 Replies
View Related
Apr 8, 2013
I am using Excel 2010. The template only has 5 working days in it, but I need to set 6 working days (Saturday is also working day). Wondering, how to get this working without spoiling the functions. Also the date format is in US , need to change to UK without disrupting the Formula/Functions.
View 12 Replies
View Related
Jan 6, 2010
I am trying to use the NETWORKDAYS function in excel to calculate the working days for my company. the problem is I m located in UAE and here Saturdays and Fridays are official days off for my company. Now the problem is that the excel have this built in function that Sunday and Saturdays are weekend days. I want to customize the function for my local days off for my company.
View 14 Replies
View Related
Aug 8, 2014
By chance I have opened a sheet with some macro and after that 'right click' is not working in any of the excel sheets (even newly created ones) in sheet names tab.
i.e., I can't delete/rename/insert etc in any sheet by rightclicking the sheet name.
Even the Edit->'delete sheet' is disabled. However, Insert->worksheet is enabled.
How to make the right click enabled. (excel version 2003)
View 5 Replies
View Related
Jul 25, 2014
I have added 3 tables data .. also I had created a sample solution calc for emp1 and project1 ... I need to calculation the ratio between the months based on the working days and allocate the efforts accordingly.
View 2 Replies
View Related
Sep 12, 2013
I've got a spread sheet at work that is shared between 4 people. It's password protected and its been protected so only four of us can edit it. It was working fine until yesterday for no reason the auto filter stopped working. The drop down arrows are still there but nothing happens when you click on them?
The sheet was made on excel 2003 but one of the users uses the newer excel which we will all eventually get.
View 2 Replies
View Related
May 20, 2012
(Excel 2003, using Format/Cells)
I have selected a range of multiple rows and columns. I can change the alignment, cell color, where border lines appear, and the color of border lines.
However, I can not change the border line style. No matter what style I select, when drawn on the sheet it apppear as a thin solid line. I've tried all the dashed/dotted line options, but they appear to have no effect.
Ultimately, I want to color alternating rows of cells, and (since coloring hides grid lines) I want to add border lines the same color and style as the hidden grid lines.
View 2 Replies
View Related
Sep 23, 2013
Excel 2003
On one of our computers at work, Excel is acting especially strange. The conditional formatting in Excel on one of our computers is not working. In addition, we cannot fill a cell with any color or change the color of the writing. We can click a color for the letters and type it in, but immediately after another cell is highlighted, the writing goes black again. When we try to highlight multiple cells with the cursor, the cells are black instead of the normal color. This happens to not just spreadsheets that are new, but existing spreadsheets on our shared drive from only this one computer as well. No other computers are affected this way. All other computers show the spreadsheets fine and do not have any functionality issues.
View 5 Replies
View Related