Sumif To Include Start Date

Jul 23, 2014

I am trying to find a formula for column D on the PO Costs EOY sheet. My criteria is as follows:

1. Column b on PO Costs EOY= Column A on Fabric and accessories
2. The order date in Column A is equal or in between the dates on rows 3 and 4 in fabric or basket accessories
3. I do not want to include in the some anything before order date, ie, if the order date is 8/8, i only want to sum 8/9 and greater.

The order date will always be on the last day of the week. So the sum would start the follow week.

View 3 Replies


ADVERTISEMENT

Calculate Start / Stop Time And Also Include Date

Mar 13, 2014

I have a small project at work where I am being asked to put a simple spread sheet that will calculate a start/stop time - and also include the date. For example:

Start time 5pm, date: 3/13. The spread sheet to auto calculate what the stop time and date will be if a specific amount of hours is to be calculated. For example in this case, 12 hours. From calculating in my head that would be 5am the following day. However, how can I get this in excel to work and therefore all i would have to do is enter the start time and date, + 12 hrs, and excel would calculate the time/date after the additional 12 hrs.

View 3 Replies View Related

Start/Stop Timer For Hours Worked To Include Break Time

Oct 15, 2007

I have a timesheet where user updates start and end time for various tasks.

I have placed a time capture button in the excel sheet (which is simply a macro saying =now() function)

The user clicks it before starting and after finishing the task. The start and end times are captured in adjacent cells.

If the user starts the work, and goes on a lunch break say for 20 min, comes back finishes the task and captures end time, the time difference will not consider break time which is non productive.

How can I incorporate something like 'pause' option so that before he goes for lunch he can temporarily pause the time.

View 9 Replies View Related

Removing Date And Seconds From Cells That Include Date And Time

Apr 30, 2014

I have only one column (A) with thousands of cell entries. Each Cell contains a date and time. (x/xx/xxxx 12:34:56)

For example, Cell A1 = 1/24/13 18:45:22

I want the new cells to only have the time, but have the seconds removed (and not simply hide the seconds). This is because I'll need to run Conditional Formatting to find every cell with a similar time - but I only need similar times within the same minute...it doesn't matter if the seconds are off.

The new cell should just be A1 = 18:45

The real reason I need this is because I need to find every entry that has the same time (with hour and minutes), which I figure I'd use conditional formatting for. My problem is that many entries have the same time but the seconds are off.

Example:
1/22/13 12:23:11
1/24/13 18:45:22
1/24/13 18:45:36
1/26/13 22:33:41

In this example, I'd want Conditional Formatting to highlight cell A2 and A3 because they have the same time of 18:45 (not including the seconds). I figured the best way to go about this would be to remove the date and remove the seconds, and run the search that way. However, any way to accomplish goal without deleting the date and seconds would be just as useful.

View 4 Replies View Related

Compute The FuTure Date When Start Date,Lead Date,Weekly Offs,Leaves And Holidays

Nov 15, 2008

First and foremost I would like to congragulate you on this wondeful piece of code in the below link...

The query was to get a future date excluding Fridays and Holidays...

http://www.excelforum.com/excel-work...rkingdays.html

I have a similar query and therefore I pasted this link...

I actually wanted to get a future date using a Dynamic two day off as my the offs keep on changing as well as incorporate Holidays and Leaves if any..

Now Holidays would be official Public Holidays and
Leaves would be taken by the employee..

The code needs to pick the Leaves + Holidays and different offs maybe even more than 2 offs...

View 7 Replies View Related

How To Auto-Populate Date Range (working Days Only) From Start Date And End Date

May 25, 2014

I am now trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.

View 1 Replies View Related

Calculate Next Due Date Based On Start Date Frequency And Current Date?

Mar 9, 2014

I'm trying to workout how to take a known initial date a repeating frequency and work out the next due date from today.

Example

Initial Date :- 1st of January 2014

Frequency :- every 5 weeks

Current Date :- 9th of March 2014

Next Due date should be :-12th of March 2014 (if I worked it out correctly from my paper calendar)

I want to use a cell formula to do this for different initial dates and varying frequency periods (the frequency will always be whole weeks i.e. 1,2,3,4,5,6,7,8,8,10)

View 4 Replies View Related

Editing Macro To Include Multiple Rows And Include Text Formatting For Leading Zeros

Apr 2, 2014

I need the values that are copied from the template to copy over in text form from the "Data" Tab. Secondly, the master sheet has multiple lines for each vendor. For the area highlighted in red I'd like for it to copy all cells in column C for the vendor and search the vendor by name. Then, move to the next sheet.

View 10 Replies View Related

Create Calculator To Show Start And End Date Based On Specific Date Provided

Jan 12, 2014

I am trying to create a calculator which will show start date and end date based on the specific date provided.

EX: column A has January 1, 2013, column B has Wednesday, Column C should have a start date which supposed to be 4 days ago (December 28).

View 6 Replies View Related

Calculate Start Date From Finish Date Minus 14 Working Hours

May 7, 2014

I needs a formula (not VBA) to calculate the required start date.

I have to do a job of 14 working hours and this job must be finished on 05-may-2014 13:00

My working week is from monday u/i friday and every day I work from 08:00-16:00

At what time do I have to start the job to get it done in time.

The formula should give this result: 01-may-2014 15:00

View 3 Replies View Related

How To Auto Populate Date Range (working Days Only) From Start And End Date

May 26, 2014

i am trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.

View 4 Replies View Related

Automating Out Current Loan Period From Start Date And Today Date In IMPT Function?

Jun 12, 2014

Trying to automate the period part of the impt function

To calculate current value of loan i have the below formula below with the 3 being the current period

=IPMT(4.3%/12,3,5*12,-7000)/(4.3%/12)

What i would like to do is for the period to be self calcuating from current date and the loan start date. I can return a value in days using start date - today() and aware month function returns the month number but stuggling to find a way to work out cumulative month from the start date.

View 4 Replies View Related

Vbcodes To Select Start Date Then Begins Highlight Until End Date

Oct 28, 2006

i need VB to select the start date of booking and autohighlights the "blank booking slot cells" until the end date that is input in Excel. You can visualise this as a room booking system. The left most column is the dates and the first row represents the different rooms type. E.g. if one guest books the Twin Deluxe No. 123 room on 23 Oct 2006 until 25 Oct 2006. We wish the VB can essentially help us identify the start date then begins highlighting the three slots for 23, 24 and 25 Oct on the column for the Twin Deluxe Room 123.

View 4 Replies View Related

Calculate End Date From Start Date & Number Of Weeks

Jun 26, 2007

Take a look at the attachment file. Those highlighted in yellow are entered by the user. What is the formula to calculate the End date in (A6) after the user has entered the start date (A2) & the number of weeks (A4)?

View 5 Replies View Related

Count Number Of Date Ranges Include Certain Month?

Oct 30, 2013

I have a a set of date ranges. The start and stop date of the ranges are listed in seperate columns. I need to count how many of those date ranges include a specific month/year. Example data is below.

Start
Stop
Month/Year

[Code].....

View 4 Replies View Related

Highlight-Select Start Date To End Date

Oct 28, 2006

We are doing a project on a booking system and wish to use VB codes to autohighlight the slots from the start date until the end date.

View 9 Replies View Related

Find Start Date And End Date In Range

Jul 30, 2007

This is a sub that uses the Find method to find a series of dates and copy them to another worksheet. The following error comes up: Object variable or With block variable not set. I have tried using a set command etc. but other errors end up coming up.

Private Sub CommandButton7_Click()

On Error Goto errorHandler
Dim startDate As String
Dim stopDate As String
Dim startRow As Integer
Dim stopRow As Integer
startDate = InputBox("Enter the Start Date: (mm/dd/yy)")
If startDate = "" Then End
stopDate = InputBox("Enter the Stop Date: (mm/dd/yy)")
If stopDate = "" Then End
'startDate = Format(startDate, "mm/??/yy")
'stopDate = Format(stopDate, "mm/??/yy")
startRow = Me.Columns("A").Find(startDate, _
LookIn:=xlValues, lookat:=xlWhole).Row
stopRow = Me.Columns("A").Find(stopDate, _
LookIn:=xlValues, lookat:=xlWhole).Row
Me. Range("A" & startRow & ":A" & stopRow).Copy _
Destination:=Worksheets("Report").Range("A1")
End

errorHandler:
MsgBox "There has been an error: " & Error() & Chr(13) _
& "Ending Sub.......Please try again", 48

End Sub

View 9 Replies View Related

Excel 2003 :: Include Text Criteria In Date Range Formula

Dec 20, 2012

Having a hard time putting this one together..Trying to do: Create a formula that counts how many cells in Column L, that fall within a date range and also have a specific category of "text" (Column E). What I've tried:=COUNTIF($L$4:$L$166,"

View 5 Replies View Related

SumIF With Dates: SUM All Expenses After The Posted Date Including That Date

Feb 13, 2009

In the expense log, Column C is a list of Dates and Column I is a list of expenses. I want to Sum the expenses in the 'Expense Log 09' to a new sheet based on a Date entered in H24 on the new sheet. I have tried the formula as shown below and Get the result #NAME?

=SUM(IF(Expense Log 'Expenses Log 09'!C8:C100,H24,'Expenses Log 09'!I8:I100)). I would Like to SUM all expenses After the posted date including that date.

View 5 Replies View Related

Add Days Between Start Date And End Date?

Jun 2, 2014

What I am trying to accomplish is, to add days from the start date (daily) and to stop adding at the end date.

Example:
(Column A) Start Date: 1/9/13
(Column B) End Date: 1/8/14

View 6 Replies View Related

Enter Start Date And End Date?

Mar 12, 2014

when I enter a start date and end date, it should autopopulate the columns with the dates in the middle including start date and end date.

View 1 Replies View Related

Autofill From Start Date To End Date

May 26, 2006

I have one column( date) which I wanna set date range from VBA macro. The problem is I wanna use Autofill to fill from the start date to the specific end date, but with Autofill func I cannot do this.

I attached a sample to explain my problem. Please take a look and give me a hint to do this.

View 6 Replies View Related

SumIF A Date Is With In 90 Days Of Todays Date Before Or After

Oct 29, 2009

I have todays date in cell A2. I have a range of dates in a row 4 and numbers below each date in row 6. What i want is to Sum the numbers below the dates in row 6 if the date in row 4 is with in 90 days before or after the date in cell A2.

Example......

The answer i should get is 4 since only 3 dates fall 90 days before or after todays date.

View 3 Replies View Related

Getting The Date For The Start Of The Week

Jun 4, 2008

I have this column with a value like 04/06/2008. I will want another of the column to auto generate the date for the start of the week like 02/06/2008 which is a Monday.

View 14 Replies View Related

Start End Date Calculation

Nov 12, 2008

Need a formula that will generate the ending date of task, adding therefore if needed the number of weekend(s) in between the start and end date to the End date.

Let us say: task is starting in 2008/11/11 the duration of the task is 7 days. So, we should get an End Date= 2008/11/19.

2008 11/11 11/12 11/13 11/14 11/15 11/16 11/17 11/18 11/19
Tue Wed Thu Fri Sat Sun Mon Tue Wed

View 3 Replies View Related

Start And End Date Query

Nov 25, 2013

I've attached a sample of something I'm working on and the layout it's currently in.

I have a list of customers and an amount per month, in the sample, I want to be able to use a formula that will select which month the customer first has an amount >0 and in the end date column, I want to see when the customer then stopped showing an amount >0.

I have a massive list of these customers and sorting them each month is difficult.

DaveStart and End Month Sample.xlsx

View 2 Replies View Related

Start And END Date -- Status

Jan 24, 2010

1. If I enter a date in B3, then D3 will be S, and if I enter date in C3, D3 will be left blank while E3 result is D (Done). To have a clear view, I have attached the excel sheet.

View 3 Replies View Related

Calculate End Date Using Start Date And Number Of Days Excluding Specific Days

Nov 22, 2013

I want to calculate the end date of my German courses. This is how it works:

A course consists of 60 LU*. The course can occur i. e. three times a week: Monday, Wednesday and Friday. In each day the course lasts 2 LU, which means 6 LU each week. There is no course on Tuesday, Thursday, Saturday, Sunday and on holidays. Therefore this type of course that begins on 18-Nov-2013 will end on 03-Feb-2014.

Another course which occurs Tuesday, Thursday and Saturday, and respectively has 2 LU on Tuesday, 2 LU on Thursday and 3 LU on Saturday and starts on 03-Dec-2013 will end on 06-Feb-2014.

Therefore I want to create a worksheet where I set the start date, choose the days and respectively the LU amount on those days. The end date shall be calculated according to these criteria.

The workday function on excel cannot do this and I do not have any programming skills to work with VBA.

Legend:
*LU = lesson units; 1 LU is 45 minutes

Holidays:
28-Nov-13
29-Nov-13
08-Dec-13
09-Dec-13
25-Dec-13
31-Dec-13
01-Jan-14

[Code] ...........

View 7 Replies View Related

Return Start And Finish Date?

May 25, 2014

I am trying to return start and finish date of events depending on when resources are allocated.

View 4 Replies View Related

Calculate The 6th Month From Start Date?

Dec 25, 2013

I need a formula to calculate a date 6 months forward from the start date. However, in the calculated 6th month, I need it to the day before the start date.

ie: start date: 26/12/13 -- End date: 25/06/14

View 3 Replies View Related







Copyrights 2005-15 www.BigResource.com, All rights reserved