Return Start And Finish Date?
May 25, 2014I am trying to return start and finish date of events depending on when resources are allocated.
View 4 RepliesI am trying to return start and finish date of events depending on when resources are allocated.
View 4 RepliesI needs a formula (not VBA) to calculate the required start date.
I have to do a job of 14 working hours and this job must be finished on 05-may-2014 13:00
My working week is from monday u/i friday and every day I work from 08:00-16:00
At what time do I have to start the job to get it done in time.
The formula should give this result: 01-may-2014 15:00
I can calculate total hours when a user enters a start date/time and a finish date/time. The kick is I only want to include hours from 2:00 PM to 12:00 AM (10 hour period). So assuming all the start and end times will be in this range, how can i calculate work hours over multiple days? For example: Start date/time = 2/26/13 2:30 PM and end date/time = 2/28/13 10:30 PM. I want my calculated hours to show 28 hours.
View 1 Replies View RelatedI have a user form with textBox1 = start time (entered as "[h]:mm") and text Box2 = finish time (entered as "[h]:mm"). I would like textBox3 to display the difference between the start time and finish time as a general number!
For example
Start time: 21:00
Finish time: 06:30
Hours worked: 9.50
Start time: 12:30
Finish time: 23:00
Hours worked: 10.50
I have a spreadsheet containing milestones for several different projects. The number of milestones per project varies.
I need to get the max date for each project using VBA.
Simple Example: 'Project Name' is in column A and the 'Scheduled Finish Date' is in column B.
Project X has 5 milestones with the following Scheduled Finish Dates: (8/15, 8/16, 8/17, 8/18, 8/19) Project Y has 3 milestones with the following Scheduled Finish Dates: (8/20, 8/21, 8/22) Project Z has 6 milestones with the following Scheduled Finish Dates: (8/23, 8/24, 8/25, 8/26, 8/27, 8/28)
I need the macro to return 8/19 for Project X, 8/22 for Project Y and 8/28 for Project Z.
I am trying to get the start time and finish time for breaks.
I have 4 columns Name, status, start, finish. In the name column there are multiple names, under status there 6 different status's. and under the time columns there are in and out times dependant on status. I am trying to us index match match. I have tried vlookup and hlookup as a nested function. I keep getting errors.
NameStatus MessageStart TimeFinish Time
Cameron WilliamsTech All & Billing12:31:4812:31:52
=index(starttime,match(name,namefield(match,"on lunch",starttime)))
[Code]......
I am working on an excel spreadsheet for work and I have to show a chart that shows the time of day a space is in use. Right now I am having to mark all of these by hand which takes me forever because I have a couple thousand lines of information.
I need to mark the hours in use based off the start and finish time.
For Example:
1) If the start time was 7:00 and the end time was 10:45 then the markers would only mark 7am and 10am
2) If the start time was 7:15 and the end time was 10:00 then the markers would only mark 7am and 9am
3) If the start time was 7:30 and the end time was 10:30 then the markers would only mark 7am and 10am
4) If the start time was 7:45 and the end time was 10:15 then the markers would only mark 8am and 9am
I was given the formula and it works to count the whole hour but now I need the formula tweaked and I don't know how...I need the formula to account for quarterly hours...and I don't know how to fix it.
Attached is an example of the spreadsheet of what I currently have and of what I need. Book1.xlsx
I have a number of processes that I would like to calculate the finish times of.
For example, Process A may take 18 hours to complete, Process B may take 28 hours to complete and Process C may take 125 hours to complete etc
However these processes only run during certain times, i.e. 9am to 5pm.
Ideally I would like to setup a spreadsheet that when given the start time and process time calculates the (date and) time the process will finish.
I can get it to work on a 24 hour day but I've been tearing my hair out trying to take out the none-working part of the day (the 5pm to 9am).
I need to create a range of cells in Column A. I know the first cell, A2. The final occupied cell will vary. Once I have the range object I would like to step through and analyse each cell in turn using a For/Each loop.
The code I have so far is:
Public all_structures As Range 'Range required for for/each loop Column
Public last_structure As Range 'Last cell in Column
Public molcell As Range 'Current cell in range
' Establish range of cells in Column A
Set last_structure = Range("A2").End(xlDown)
Set all_structures = Range(Range("A2"), Range(last_structure)) ***
' Loop through each structure in turn
For Each molcell In all_structures
Loop code In here
Next molcell
When I run I get an error message of "Run-time error '1004': Method 'Range' of object '_Global' failed". It does not like the line marked ***.
test.xlsx
I need to calculate the time elapsed between start and finish dates. I've figured the TODAY function, as explained here but I'm referring solely to dates in cells. How to?
I have 2 dates+ times.
1 the contract start date and time.
2 the contract end date and time.
Can I calculate the number of working hours between these two using a formula?
So if I have a 10 hour working day (08:00-18:00), Mon-Fri and the two Dates/Times can I calculate the number of working hours?
Example
Start 06-Mar-07 10:00
End 14-Mar-07 14:00
This is 2 part days and over a weekend.
I've just started working on an FTE calculator and wish to populate a 12 month calendar with FTE depending on the start and finshed dates.
FTE Calculator non nursing.xlsx
I've attached the file. In Column D the user would select the month the staff start and in the Column E the month the staff will finish. I would like the fte that is calculated in Column Z then to populate in the 12 columns AB:AM (Jul to Jun) with corresponding month start and finish.
Anyone know why the NETWORKDAYS() function will return a value of 1 if the start and end date are the same? Does the function always assume that the start_date is at 12:00AM and the end_date is at 11:59PM, because it seems to also show that there are 3 days between 11/04/08 and 11/06/08.
View 9 Replies View RelatedI have been trying to search for either a function or VBA that will perform the following:
If I enter I want all months >=1/1/07 and <=3/31/07 it would tell me that the months in between are January, February and March and so on with all dates.
I have a workbook that is generated from the system(AS400)but it wont subtract the time finish -time start. I get a #Value error in the cells I tried two different formulas.
View 2 Replies View Related1-The employee takes 13 minutes to build each piece
2-The employee starts at 7:15 am
3-The employee goes to lunch from 12:15 pm to 1:00 pm
4-I need to give the employee a date line of time of when pieces should be finished. Taking into account the time he/she takes lunch.
I would like a solution for the automatic calculation of the end date and end time for project tasks. I have already spent hours on the issue, thanks for any help on this.
The parameters are:
A1 = Start time 08:00
B1 = End Time 17:00
A2 = break lunch 12:00
B2 = back from lunch 13:00
Task parameters
A5 = start date 01/03/10 (entered manually)
B5 = start time 10:00 (entered manually)
C5 = duration 02:00 (hrs entered manually)
D5 = "end date" >>> (to be calculated exluding breaks and holidays)
E5 = "end time" >>> (to be calculated exluding breaks and holidays)
the next line should be filled in automaitically according to the hours needed and the previous end date & time
A6 = "start date" >>> (after line 5: to be calculated exluding breaks and holidays)
B6 = "start time" (after line 5: to be calculated exluding breaks and holidays)
C6 = duration 14:00 (entered manually)
D6 = "end date" >>> (to be calculated exluding breaks and holidays)
E6 = "end time" >>> (to be calculated exluding breaks and holidays)
and so on for every new line down.
First and foremost I would like to congragulate you on this wondeful piece of code in the below link...
The query was to get a future date excluding Fridays and Holidays...
http://www.excelforum.com/excel-work...rkingdays.html
I have a similar query and therefore I pasted this link...
I actually wanted to get a future date using a Dynamic two day off as my the offs keep on changing as well as incorporate Holidays and Leaves if any..
Now Holidays would be official Public Holidays and
Leaves would be taken by the employee..
The code needs to pick the Leaves + Holidays and different offs maybe even more than 2 offs...
I am now trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.
View 1 Replies View RelatedI'm trying to workout how to take a known initial date a repeating frequency and work out the next due date from today.
Example
Initial Date :- 1st of January 2014
Frequency :- every 5 weeks
Current Date :- 9th of March 2014
Next Due date should be :-12th of March 2014 (if I worked it out correctly from my paper calendar)
I want to use a cell formula to do this for different initial dates and varying frequency periods (the frequency will always be whole weeks i.e. 1,2,3,4,5,6,7,8,8,10)
I am trying to create a calculator which will show start date and end date based on the specific date provided.
EX: column A has January 1, 2013, column B has Wednesday, Column C should have a start date which supposed to be 4 days ago (December 28).
i am trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.
View 4 Replies View RelatedTrying to automate the period part of the impt function
To calculate current value of loan i have the below formula below with the 3 being the current period
=IPMT(4.3%/12,3,5*12,-7000)/(4.3%/12)
What i would like to do is for the period to be self calcuating from current date and the loan start date. I can return a value in days using start date - today() and aware month function returns the month number but stuggling to find a way to work out cumulative month from the start date.
i need VB to select the start date of booking and autohighlights the "blank booking slot cells" until the end date that is input in Excel. You can visualise this as a room booking system. The left most column is the dates and the first row represents the different rooms type. E.g. if one guest books the Twin Deluxe No. 123 room on 23 Oct 2006 until 25 Oct 2006. We wish the VB can essentially help us identify the start date then begins highlighting the three slots for 23, 24 and 25 Oct on the column for the Twin Deluxe Room 123.
View 4 Replies View RelatedI have a created a form (1st one) and by reading bits from here I have managed to get it to do everything I need bar one thing. Is it possible to have the cursor return to the start of the form (Textbox) after clicking the OK button? The ok button write every thing to the sheet and the i have to tab past my other commann buttons.
View 2 Replies View RelatedTake a look at the attachment file. Those highlighted in yellow are entered by the user. What is the formula to calculate the End date in (A6) after the user has entered the start date (A2) & the number of weeks (A4)?
View 5 Replies View Relatedif A1 is a start date and B1 is the end date, I want C1 to return the number of months there are between the start and end dates?
View 9 Replies View RelatedI need help in simulating the functionality of the OFFSET function with some of standard Excel functions which are shown at this webpage (I will be using this converter to generate the webpage from the sheet):
Spreadsheet Converter Supported Functions
I ask this because I need to create an interactive online calculator which absolutely needs to have the ability to allow the user to select the RANGE of the data to be analyzed. I included an example sheet with the offset function in the pink cell…Do you think any other standard excel function can be used to simulate its functionality?
I am trying to return the first occurrence of a variable text string with-in brackets for all data on the spreadsheet using the "RIGHT" excel function, the text to search is in column D.
Example for cells D2 & D3 reads:
D2:Adv Costs (27a) - would return "27a"
D3:Designer Unit (60) (Base) (50abc) - would return "50abc"
I want to make a "return" button that follows the user from the start sheet to other sheets and acts as a "return to the start sheet" button. I tried just recording a macro and cut/pasting the button from one sheet to the next, but apparently when you do this the button name changes.
View 6 Replies View Related