I needs a formula (not VBA) to calculate the required start date.

I have to do a job of 14 working hours and this job must be finished on 05-may-2014 13:00

My working week is from monday u/i friday and every day I work from 08:00-16:00

At what time do I have to start the job to get it done in time.

The formula should give this result: 01-may-2014 15:00

View 3 Replies


ADVERTISEMENT

How To Calculate Work Hours From Only A Start And Finish Date And Time

Feb 28, 2013

I can calculate total hours when a user enters a start date/time and a finish date/time. The kick is I only want to include hours from 2:00 PM to 12:00 AM (10 hour period). So assuming all the start and end times will be in this range, how can i calculate work hours over multiple days? For example: Start date/time = 2/26/13 2:30 PM and end date/time = 2/28/13 10:30 PM. I want my calculated hours to show 28 hours.

View 1 Replies View Related

Number Of Working Hours Between 2 Dates Including Start And Finish Times

Mar 22, 2007

I have 2 dates+ times.

1 the contract start date and time.

2 the contract end date and time.

Can I calculate the number of working hours between these two using a formula?
So if I have a 10 hour working day (08:00-18:00), Mon-Fri and the two Dates/Times can I calculate the number of working hours?

Example
Start 06-Mar-07 10:00
End 14-Mar-07 14:00

This is 2 part days and over a weekend.

View 9 Replies View Related

Adding Date And Time Minus Not Working Hours

Sep 11, 2011

I have a data of complaints where I need to present it to the Management in such a way that the SLA period of 8 hours does not pass. Our office working hours are 7 AM till 7 PM. The complaint received should be escalated to concern section within 8 Hours of SLA time. I have the list of dates with received time. The complaint which could not be escalated today would be escalated next day. In this case is should deduct 12 Hours (7 PM to 7 AM, Non-working hours) from the time. How can I insert escalation date so as that it would deduct non working hours from it.

View 5 Replies View Related

Return Start And Finish Date?

May 25, 2014

I am trying to return start and finish date of events depending on when resources are allocated.

View 4 Replies View Related

How To Auto-Populate Date Range (working Days Only) From Start Date And End Date

May 25, 2014

I am now trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.

View 1 Replies View Related

Mark The Hours On A Start And Finish Time

Mar 25, 2014

I am working on an excel spreadsheet for work and I have to show a chart that shows the time of day a space is in use. Right now I am having to mark all of these by hand which takes me forever because I have a couple thousand lines of information.

I need to mark the hours in use based off the start and finish time.

For Example:
1) If the start time was 7:00 and the end time was 10:45 then the markers would only mark 7am and 10am
2) If the start time was 7:15 and the end time was 10:00 then the markers would only mark 7am and 9am
3) If the start time was 7:30 and the end time was 10:30 then the markers would only mark 7am and 10am
4) If the start time was 7:45 and the end time was 10:15 then the markers would only mark 8am and 9am

I was given the formula and it works to count the whole hour but now I need the formula tweaked and I don't know how...I need the formula to account for quarterly hours...and I don't know how to fix it.

Attached is an example of the spreadsheet of what I currently have and of what I need. Book1.xlsx

View 2 Replies View Related

Calculate Next Due Date Based On Start Date Frequency And Current Date?

Mar 9, 2014

I'm trying to workout how to take a known initial date a repeating frequency and work out the next due date from today.

Example

Initial Date :- 1st of January 2014

Frequency :- every 5 weeks

Current Date :- 9th of March 2014

Next Due date should be :-12th of March 2014 (if I worked it out correctly from my paper calendar)

I want to use a cell formula to do this for different initial dates and varying frequency periods (the frequency will always be whole weeks i.e. 1,2,3,4,5,6,7,8,8,10)

View 4 Replies View Related

How To Auto Populate Date Range (working Days Only) From Start And End Date

May 26, 2014

i am trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.

View 4 Replies View Related

Calculate Time Elapsed Between Start And Finish Dates

Dec 13, 2013

test.xlsx

I need to calculate the time elapsed between start and finish dates. I've figured the TODAY function, as explained here but I'm referring solely to dates in cells. How to?

View 1 Replies View Related

Calculate End Date From Start Date & Number Of Weeks

Jun 26, 2007

Take a look at the attachment file. Those highlighted in yellow are entered by the user. What is the formula to calculate the End date in (A6) after the user has entered the start date (A2) & the number of weeks (A4)?

View 5 Replies View Related

Nested IF Command: Calculate Today's Date Minus

Apr 19, 2009

The range B7:K7 contains columns of "dates" and "characters" like "A", "B" and "C" . Range D2 = Today's date. If Range C7 is blank then it should calculate Today's date minus Column B7 (i.e D2-B7) so on:

B7 = "01-Apr-2009", C7 = "02-Apr-2009", D=7 = Status as "(A)"
B7 = Submitted Date, C7 = Received Date, D7 = Status
Difference Between Today's Date and "B7" date is required if "C7" is Blank date. Otherwise it should search next group (E, F)

=IF(AND(ISBLANK(C7),NOT(ISBLANK(B7))),D2-B7,IF(AND(ISBLANK(F7),NOT(ISBLANK(E7))),D2-E7,IF(AND(ISBLANK(I7),NOT(ISBLANK(H7))),D2-H7,IF(AND(ISBLANK(L7),NOT(ISBLANK(K7))),D2-K7,"--")))))

-- Excel File is attached.

View 4 Replies View Related

Subtract Start Time From Finish Time Return Hours Worked As Number

May 5, 2006

I have a user form with textBox1 = start time (entered as "[h]:mm") and text Box2 = finish time (entered as "[h]:mm"). I would like textBox3 to display the difference between the start time and finish time as a general number!

For example
Start time: 21:00
Finish time: 06:30
Hours worked: 9.50

Start time: 12:30
Finish time: 23:00
Hours worked: 10.50

View 9 Replies View Related

Calculate Hours Between Date And Time Within Business Hours?

Apr 4, 2013

find a formula that will calculate the hours between the two below values but only take in to consideration the business hours (from 9 to 17) and exclude any weekends?

08/03/2013 13:32:00
02/04/2013 09:32:50

View 4 Replies View Related

Minus Break Time Minutes Off Working Hours?

Jun 15, 2014

basically I am trying to make a time calculator for work, I want it to automatically add the hours up but then also minus break times and then give me a whole paid total hours worked that week.

CALCULATOR.xlsx

View 1 Replies View Related

Calculate End Date Using Start Date And Number Of Days Excluding Specific Days

Nov 22, 2013

I want to calculate the end date of my German courses. This is how it works:

A course consists of 60 LU*. The course can occur i. e. three times a week: Monday, Wednesday and Friday. In each day the course lasts 2 LU, which means 6 LU each week. There is no course on Tuesday, Thursday, Saturday, Sunday and on holidays. Therefore this type of course that begins on 18-Nov-2013 will end on 03-Feb-2014.

Another course which occurs Tuesday, Thursday and Saturday, and respectively has 2 LU on Tuesday, 2 LU on Thursday and 3 LU on Saturday and starts on 03-Dec-2013 will end on 06-Feb-2014.

Therefore I want to create a worksheet where I set the start date, choose the days and respectively the LU amount on those days. The end date shall be calculated according to these criteria.

The workday function on excel cannot do this and I do not have any programming skills to work with VBA.

Legend:
*LU = lesson units; 1 LU is 45 minutes

Holidays:
28-Nov-13
29-Nov-13
08-Dec-13
09-Dec-13
25-Dec-13
31-Dec-13
01-Jan-14

[Code] ...........

View 7 Replies View Related

Calculate Hours Worked, Minus Weekends

Nov 11, 2009

to calculate how long a ticket is open in our system before being resolved. I don't want to count weekends, and if the ticket is 'suspended', I don't want to count that either. There is also the factor that the ticket 'un-suspend' date may be later than the ticket 'closed' date. Which is the bit that's throwing me.

So, I have the following fields

Ticket Open, Ticket Closed, Ticket Suspended Date, Ticket Unsuspended Date

A sample ticket might be (using above fields)

02/11/09 09/11/09 04/11/09 30/11/09

That 'should' equal two days (16 hours) as the Unsuspend date falls after the close date so it was suspended from the 4th until closure.

Now I want to know, in hours (8 hour day) how long that ticket took to resolve (i.e close), remembering you can't count the time it was suspended, or any time that fell over a weekend. Also not all tickets are suspended.

View 13 Replies View Related

Formula To Calculate How Many Hours Minus 30 Mins For Lunch

Jan 12, 2009

If a person does a full day I want the formula to calculate how many hours minus 30 mins for lunch i.e. 7:30 - 4:00 = 8 hours. I have done this and it works fine, the problem comes when a person does a half day i.e. 7:30 - 11:30, this will read 4.5 hours. If this is the case I don't want the 30mins deducted so it should be 4.0 hours worked.

I have high lighted a column in the work sheet (yellow) whereby the user puts an 'x' in the appropriate cell if they are working a half day.

The probem is I cannot incorperate the two formulas in one cell (the Actual hours cell) I have the one formula in the actual hours cell and the other bolted on the end thus giving two different readings.

View 14 Replies View Related

Calculate Time Spent On Ticket Minus Non-Business Hours?

Jun 6, 2012

I have a requirement of calculating time spent on ticket, basically a difference between the time a ticket was logged and when it was resolved.

First, working days are Saturday through Wednesday, i.e weekends are Thursday & Friday.

Second, there are different resolver groups or teams which work on a ticket. These teams have different working hours, some work from 07:30 to 15:30 on weekdays, and others work 24/7. Each ticket will be assigned only to one resolver group.I also need to consider holidays.

So, my requirement is to check the resolver group for each ticket, and decide the working hours based on it. After this check has to be done for holidays, and then difference between logged time and resolved time needs to caluculated in minutes.

Tickets can be logged at any time of the day / week, it may not always be logged during working hours only. in such cases calculate should consider next business day / hour as the start time.

Raw data for tickets is available in =Sheet1!$A$1:$E$21

Ticket NoResolver GroupLogged DateResolved DateTime Spent123456
Team A5/21/2012 1:56:28 PM5/29/2012 2:10:53 PM343543Team B5/21/2012 9:31:02 PM5/27/2012 3:41:22 PM853732
Team C5/22/2012 2:28:06 PM5/26/2012 2:34:31 PM

[Code].....

View 4 Replies View Related

Calculate The 6th Month From Start Date?

Dec 25, 2013

I need a formula to calculate a date 6 months forward from the start date. However, in the calculated 6th month, I need it to the day before the start date.

ie: start date: 26/12/13 -- End date: 25/06/14

View 3 Replies View Related

FORMULA To Calculate Start Date

May 2, 2013

if I've worked in the company for 9.0384 years, how can I calculate that my start day was 04/20/04?

View 3 Replies View Related

Subtract X Working Hours From Date & Time

Jun 20, 2008

I am trying to subtract 8 hours from a date/time. What I need to do is to capture that lead time using only weekdays, and working hours of 8am-5pm.

For example:

Date/Time
6/23/2008 9:18AM (Monday)

Subtracting 8 hours from this scenario would give me
6/20/2008 10:18AM (friday)

View 3 Replies View Related

WORKDAY Function To Calculate The Start Date

Jun 11, 2009

As everyone realizes that WORKDAY function can return a working date that exclude weekends and any dates identified as holidays. However, what if I want to return a working date excluding my designated holidays but including weekends?

For example,

Holidays are 1 Jun 2009, 2 Jun 2009 and 4 Jun 2009

Start Date: ???
Finish Date: 8 Jun 2009
Duration: 5 days

The Start Date should be 30 May 2009.

Seems like I am not able to use WORKDAY function to calculate the start date.

View 11 Replies View Related

Calculate Start / Stop Time And Also Include Date

Mar 13, 2014

I have a small project at work where I am being asked to put a simple spread sheet that will calculate a start/stop time - and also include the date. For example:

Start time 5pm, date: 3/13. The spread sheet to auto calculate what the stop time and date will be if a specific amount of hours is to be calculated. For example in this case, 12 hours. From calculating in my head that would be 5am the following day. However, how can I get this in excel to work and therefore all i would have to do is enter the start time and date, + 12 hrs, and excel would calculate the time/date after the additional 12 hrs.

View 3 Replies View Related

Calculate What Months An Employee Worked By Start And End Date

May 15, 2009

I am working on a sheet that will allow a user to enter a start month (from a pre-defigned drop down list) and an end month (again from ddl). What I need to calculate is in what months the employee worked in so I can calculate their salary cost by quarter.

It can populate other cells in order to do the calculation if needed. So, for example if an employee started in May, and worked until December, I need to calculate that he worked 2 months in Q1, 3 months in Q2, 3 months in Q3, and 0 months in Q4. Our fiscal year is April to March.. ;-) I have thought of several options, but none of them have worked 100%.

View 2 Replies View Related

Calculate Holidays Remaing Based On Start Date

Nov 21, 2007

I want to create a formula that will do the following Each worker is entitled to 21 days holiday per year this will run from 8 Jan 08 to 7 Jan 09. But if a worker starts say 15 Apr 08 he would be entitled to less than 21 days. I would just like to be able to put his start date in a cell and then automatically generate how many days holiday he would be entitled to from 15 Apr to 7 Jan.

View 2 Replies View Related

Compute The FuTure Date When Start Date,Lead Date,Weekly Offs,Leaves And Holidays

Nov 15, 2008

First and foremost I would like to congragulate you on this wondeful piece of code in the below link...

The query was to get a future date excluding Fridays and Holidays...

http://www.excelforum.com/excel-work...rkingdays.html

I have a similar query and therefore I pasted this link...

I actually wanted to get a future date using a Dynamic two day off as my the offs keep on changing as well as incorporate Holidays and Leaves if any..

Now Holidays would be official Public Holidays and
Leaves would be taken by the employee..

The code needs to pick the Leaves + Holidays and different offs maybe even more than 2 offs...

View 7 Replies View Related

How To Calculate Hours Between 2 Or 3 Days Exclude Non-Working Hours

Dec 29, 2013

I'm having difficulty to calculate hours between 2 or 3 days exclude non working hours.

Attached is the example of start date with time & end date with time.

The situation is like "when the case log in till the case assist in working hours." so i will get the hours from case log to case assist.

Testing.xlsx‎

View 8 Replies View Related

How To Calculate Future Dates From Start Date On A Monthly Cycle

Sep 16, 2009

I'm trying to combine monthly calculations with "today" and with "workdays"

Example:

start date = 01/01/2009

today's date 09/16/2009

formula result = 10/01/2009 ; or if 10/01/2009 is a Sunday, result = 09/29/2009 (not 02/01/2009, 03/01/2009, etc)

=edate gives me a month but it doesn't skip weekends or calculate beyond today's date

View 14 Replies View Related

Calculate Days And Hours In Date Range

May 11, 2014

Is there a way to calculate how many days and hours there are in a date range IE 5/11/2014 to 10/31/2014 = days and hours

View 2 Replies View Related