Calculate Start Date From Finish Date Minus 14 Working Hours
May 7, 2014
I needs a formula (not VBA) to calculate the required start date.
I have to do a job of 14 working hours and this job must be finished on 05-may-2014 13:00
My working week is from monday u/i friday and every day I work from 08:00-16:00
At what time do I have to start the job to get it done in time.
The formula should give this result: 01-may-2014 15:00
View 3 Replies
ADVERTISEMENT
Feb 28, 2013
I can calculate total hours when a user enters a start date/time and a finish date/time. The kick is I only want to include hours from 2:00 PM to 12:00 AM (10 hour period). So assuming all the start and end times will be in this range, how can i calculate work hours over multiple days? For example: Start date/time = 2/26/13 2:30 PM and end date/time = 2/28/13 10:30 PM. I want my calculated hours to show 28 hours.
View 1 Replies
View Related
Mar 22, 2007
I have 2 dates+ times.
1 the contract start date and time.
2 the contract end date and time.
Can I calculate the number of working hours between these two using a formula?
So if I have a 10 hour working day (08:00-18:00), Mon-Fri and the two Dates/Times can I calculate the number of working hours?
Example
Start 06-Mar-07 10:00
End 14-Mar-07 14:00
This is 2 part days and over a weekend.
View 9 Replies
View Related
Sep 11, 2011
I have a data of complaints where I need to present it to the Management in such a way that the SLA period of 8 hours does not pass. Our office working hours are 7 AM till 7 PM. The complaint received should be escalated to concern section within 8 Hours of SLA time. I have the list of dates with received time. The complaint which could not be escalated today would be escalated next day. In this case is should deduct 12 Hours (7 PM to 7 AM, Non-working hours) from the time. How can I insert escalation date so as that it would deduct non working hours from it.
View 5 Replies
View Related
May 25, 2014
I am trying to return start and finish date of events depending on when resources are allocated.
View 4 Replies
View Related
May 25, 2014
I am now trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.
View 1 Replies
View Related
Mar 25, 2014
I am working on an excel spreadsheet for work and I have to show a chart that shows the time of day a space is in use. Right now I am having to mark all of these by hand which takes me forever because I have a couple thousand lines of information.
I need to mark the hours in use based off the start and finish time.
For Example:
1) If the start time was 7:00 and the end time was 10:45 then the markers would only mark 7am and 10am
2) If the start time was 7:15 and the end time was 10:00 then the markers would only mark 7am and 9am
3) If the start time was 7:30 and the end time was 10:30 then the markers would only mark 7am and 10am
4) If the start time was 7:45 and the end time was 10:15 then the markers would only mark 8am and 9am
I was given the formula and it works to count the whole hour but now I need the formula tweaked and I don't know how...I need the formula to account for quarterly hours...and I don't know how to fix it.
Attached is an example of the spreadsheet of what I currently have and of what I need. Book1.xlsx
View 2 Replies
View Related
Mar 9, 2014
I'm trying to workout how to take a known initial date a repeating frequency and work out the next due date from today.
Example
Initial Date :- 1st of January 2014
Frequency :- every 5 weeks
Current Date :- 9th of March 2014
Next Due date should be :-12th of March 2014 (if I worked it out correctly from my paper calendar)
I want to use a cell formula to do this for different initial dates and varying frequency periods (the frequency will always be whole weeks i.e. 1,2,3,4,5,6,7,8,8,10)
View 4 Replies
View Related
May 26, 2014
i am trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.
View 4 Replies
View Related
Dec 13, 2013
test.xlsx
I need to calculate the time elapsed between start and finish dates. I've figured the TODAY function, as explained here but I'm referring solely to dates in cells. How to?
View 1 Replies
View Related
Jun 26, 2007
Take a look at the attachment file. Those highlighted in yellow are entered by the user. What is the formula to calculate the End date in (A6) after the user has entered the start date (A2) & the number of weeks (A4)?
View 5 Replies
View Related
Apr 19, 2009
The range B7:K7 contains columns of "dates" and "characters" like "A", "B" and "C" . Range D2 = Today's date. If Range C7 is blank then it should calculate Today's date minus Column B7 (i.e D2-B7) so on:
B7 = "01-Apr-2009", C7 = "02-Apr-2009", D=7 = Status as "(A)"
B7 = Submitted Date, C7 = Received Date, D7 = Status
Difference Between Today's Date and "B7" date is required if "C7" is Blank date. Otherwise it should search next group (E, F)
=IF(AND(ISBLANK(C7),NOT(ISBLANK(B7))),D2-B7,IF(AND(ISBLANK(F7),NOT(ISBLANK(E7))),D2-E7,IF(AND(ISBLANK(I7),NOT(ISBLANK(H7))),D2-H7,IF(AND(ISBLANK(L7),NOT(ISBLANK(K7))),D2-K7,"--")))))
-- Excel File is attached.
View 4 Replies
View Related
May 5, 2006
I have a user form with textBox1 = start time (entered as "[h]:mm") and text Box2 = finish time (entered as "[h]:mm"). I would like textBox3 to display the difference between the start time and finish time as a general number!
For example
Start time: 21:00
Finish time: 06:30
Hours worked: 9.50
Start time: 12:30
Finish time: 23:00
Hours worked: 10.50
View 9 Replies
View Related
Apr 4, 2013
find a formula that will calculate the hours between the two below values but only take in to consideration the business hours (from 9 to 17) and exclude any weekends?
08/03/2013 13:32:00
02/04/2013 09:32:50
View 4 Replies
View Related
Jun 15, 2014
basically I am trying to make a time calculator for work, I want it to automatically add the hours up but then also minus break times and then give me a whole paid total hours worked that week.
CALCULATOR.xlsx
View 1 Replies
View Related
Nov 22, 2013
I want to calculate the end date of my German courses. This is how it works:
A course consists of 60 LU*. The course can occur i. e. three times a week: Monday, Wednesday and Friday. In each day the course lasts 2 LU, which means 6 LU each week. There is no course on Tuesday, Thursday, Saturday, Sunday and on holidays. Therefore this type of course that begins on 18-Nov-2013 will end on 03-Feb-2014.
Another course which occurs Tuesday, Thursday and Saturday, and respectively has 2 LU on Tuesday, 2 LU on Thursday and 3 LU on Saturday and starts on 03-Dec-2013 will end on 06-Feb-2014.
Therefore I want to create a worksheet where I set the start date, choose the days and respectively the LU amount on those days. The end date shall be calculated according to these criteria.
The workday function on excel cannot do this and I do not have any programming skills to work with VBA.
Legend:
*LU = lesson units; 1 LU is 45 minutes
Holidays:
28-Nov-13
29-Nov-13
08-Dec-13
09-Dec-13
25-Dec-13
31-Dec-13
01-Jan-14
[Code] ...........
View 7 Replies
View Related
Nov 11, 2009
to calculate how long a ticket is open in our system before being resolved. I don't want to count weekends, and if the ticket is 'suspended', I don't want to count that either. There is also the factor that the ticket 'un-suspend' date may be later than the ticket 'closed' date. Which is the bit that's throwing me.
So, I have the following fields
Ticket Open, Ticket Closed, Ticket Suspended Date, Ticket Unsuspended Date
A sample ticket might be (using above fields)
02/11/09 09/11/09 04/11/09 30/11/09
That 'should' equal two days (16 hours) as the Unsuspend date falls after the close date so it was suspended from the 4th until closure.
Now I want to know, in hours (8 hour day) how long that ticket took to resolve (i.e close), remembering you can't count the time it was suspended, or any time that fell over a weekend. Also not all tickets are suspended.
View 13 Replies
View Related
Jan 12, 2009
If a person does a full day I want the formula to calculate how many hours minus 30 mins for lunch i.e. 7:30 - 4:00 = 8 hours. I have done this and it works fine, the problem comes when a person does a half day i.e. 7:30 - 11:30, this will read 4.5 hours. If this is the case I don't want the 30mins deducted so it should be 4.0 hours worked.
I have high lighted a column in the work sheet (yellow) whereby the user puts an 'x' in the appropriate cell if they are working a half day.
The probem is I cannot incorperate the two formulas in one cell (the Actual hours cell) I have the one formula in the actual hours cell and the other bolted on the end thus giving two different readings.
View 14 Replies
View Related
Jun 6, 2012
I have a requirement of calculating time spent on ticket, basically a difference between the time a ticket was logged and when it was resolved.
First, working days are Saturday through Wednesday, i.e weekends are Thursday & Friday.
Second, there are different resolver groups or teams which work on a ticket. These teams have different working hours, some work from 07:30 to 15:30 on weekdays, and others work 24/7. Each ticket will be assigned only to one resolver group.I also need to consider holidays.
So, my requirement is to check the resolver group for each ticket, and decide the working hours based on it. After this check has to be done for holidays, and then difference between logged time and resolved time needs to caluculated in minutes.
Tickets can be logged at any time of the day / week, it may not always be logged during working hours only. in such cases calculate should consider next business day / hour as the start time.
Raw data for tickets is available in =Sheet1!$A$1:$E$21
Ticket NoResolver GroupLogged DateResolved DateTime Spent123456
Team A5/21/2012 1:56:28 PM5/29/2012 2:10:53 PM343543Team B5/21/2012 9:31:02 PM5/27/2012 3:41:22 PM853732
Team C5/22/2012 2:28:06 PM5/26/2012 2:34:31 PM
[Code].....
View 4 Replies
View Related
Dec 25, 2013
I need a formula to calculate a date 6 months forward from the start date. However, in the calculated 6th month, I need it to the day before the start date.
ie: start date: 26/12/13 -- End date: 25/06/14
View 3 Replies
View Related
May 2, 2013
if I've worked in the company for 9.0384 years, how can I calculate that my start day was 04/20/04?
View 3 Replies
View Related
Jun 20, 2008
I am trying to subtract 8 hours from a date/time. What I need to do is to capture that lead time using only weekdays, and working hours of 8am-5pm.
For example:
Date/Time
6/23/2008 9:18AM (Monday)
Subtracting 8 hours from this scenario would give me
6/20/2008 10:18AM (friday)
View 3 Replies
View Related
Jun 11, 2009
As everyone realizes that WORKDAY function can return a working date that exclude weekends and any dates identified as holidays. However, what if I want to return a working date excluding my designated holidays but including weekends?
For example,
Holidays are 1 Jun 2009, 2 Jun 2009 and 4 Jun 2009
Start Date: ???
Finish Date: 8 Jun 2009
Duration: 5 days
The Start Date should be 30 May 2009.
Seems like I am not able to use WORKDAY function to calculate the start date.
View 11 Replies
View Related
Mar 13, 2014
I have a small project at work where I am being asked to put a simple spread sheet that will calculate a start/stop time - and also include the date. For example:
Start time 5pm, date: 3/13. The spread sheet to auto calculate what the stop time and date will be if a specific amount of hours is to be calculated. For example in this case, 12 hours. From calculating in my head that would be 5am the following day. However, how can I get this in excel to work and therefore all i would have to do is enter the start time and date, + 12 hrs, and excel would calculate the time/date after the additional 12 hrs.
View 3 Replies
View Related
May 15, 2009
I am working on a sheet that will allow a user to enter a start month (from a pre-defigned drop down list) and an end month (again from ddl). What I need to calculate is in what months the employee worked in so I can calculate their salary cost by quarter.
It can populate other cells in order to do the calculation if needed. So, for example if an employee started in May, and worked until December, I need to calculate that he worked 2 months in Q1, 3 months in Q2, 3 months in Q3, and 0 months in Q4. Our fiscal year is April to March.. ;-) I have thought of several options, but none of them have worked 100%.
View 2 Replies
View Related
Nov 21, 2007
I want to create a formula that will do the following Each worker is entitled to 21 days holiday per year this will run from 8 Jan 08 to 7 Jan 09. But if a worker starts say 15 Apr 08 he would be entitled to less than 21 days. I would just like to be able to put his start date in a cell and then automatically generate how many days holiday he would be entitled to from 15 Apr to 7 Jan.
View 2 Replies
View Related
Nov 15, 2008
First and foremost I would like to congragulate you on this wondeful piece of code in the below link...
The query was to get a future date excluding Fridays and Holidays...
http://www.excelforum.com/excel-work...rkingdays.html
I have a similar query and therefore I pasted this link...
I actually wanted to get a future date using a Dynamic two day off as my the offs keep on changing as well as incorporate Holidays and Leaves if any..
Now Holidays would be official Public Holidays and
Leaves would be taken by the employee..
The code needs to pick the Leaves + Holidays and different offs maybe even more than 2 offs...
View 7 Replies
View Related
Dec 29, 2013
I'm having difficulty to calculate hours between 2 or 3 days exclude non working hours.
Attached is the example of start date with time & end date with time.
The situation is like "when the case log in till the case assist in working hours." so i will get the hours from case log to case assist.
Testing.xlsx
View 8 Replies
View Related
Sep 16, 2009
I'm trying to combine monthly calculations with "today" and with "workdays"
Example:
start date = 01/01/2009
today's date 09/16/2009
formula result = 10/01/2009 ; or if 10/01/2009 is a Sunday, result = 09/29/2009 (not 02/01/2009, 03/01/2009, etc)
=edate gives me a month but it doesn't skip weekends or calculate beyond today's date
View 14 Replies
View Related
May 11, 2014
Is there a way to calculate how many days and hours there are in a date range IE 5/11/2014 to 10/31/2014 = days and hours
View 2 Replies
View Related