Jan 14, 2007

The union has instated a new policy here and new hires now have a 120 working day probationary period. That comes out to about 6 months. ( 168 days minus the 48 days off) . what I’m looking for is a formula that will calculate each date that has passed as one starting at a –48 … also adding in to the equation that every day sick counts against that 120 and everyday of OT counts as positive brining them closer to the 120 they need.

I can figure out the math part of adding and subtracting the days. But what I can’t figure out is how do I get it to read each date as one starting from the date in cell b3

Example cell b3 has 9/25/06 cell b4 has 3/12/07 all the days that have passed count as one.

The total starts as a –48( due to the days off) with the verabial, d8 is a negative and d9 is a positive. To be added in to the total.

View 5 Replies


ADVERTISEMENT

Count How Many Days Coming Due Within 90 Days Of Each Date Based On Today Function

May 27, 2012

There are dates in column C and I need to count how many days are coming due within 90 days of each date based on the today() function but do not exceed the 90 days.

Countif Today()+90

View 5 Replies View Related

Excel 2007 :: Count Number Of Days Between Two Date Where Off Days Are Friday / Saturday And Holiday

Mar 14, 2014

I am making process TAT(Turn Around Time) which required following information. In Excel 2007.

1-Count number of days between two dates where working days are (Sun to Thursday). So required to exclude (Friday,Sat + Holidays)

A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 22
D1-Days between two dates 21
E1 To E10-Holidays

2-Count number of days between two dates where working days are (Sat to Thursday). So required to exclude (Friday + Holidays)

A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 27
D1-Days between two dates 26
E1 To E10-Holidays

Note : Any weekend (off days) dates listed in holidays should not effect the query.

View 9 Replies View Related

Countif To Count If Falls With In 90 Days Of Todays Date

Oct 29, 2009

What i have is a list of dates in a row. I want to set up a countif formula to count the number of date that fall with in 90 days of todays date. I'm planning on placing todays date in a cell in the upper left hand corner (cell A2) above the list of dates. This way i can just type in todays date and the spreedsheet will count the number of dates, in the list, that fall with in 90 days of the date i type into cell A2

View 2 Replies View Related

Find Count Of Days Within Another (separate) Date Range

Mar 20, 2014

I am assessing the impact of product price increases on volume (qty) and sales (£/$).

The prices are changed sporadically and at no set intervals. For example pries were changed on the 15th Jan and 13th Feb this year.

We have set reporting dates (calender months) so i am hoping to be able to divide the report which shows sales & qty's during the 15th Jan - 13th Feb segment and apportion them to the correct months.

I have the start & end dates of the calender months in cells A4:B18 and each time a new report is run (ie 15th Jan or 13th Feb, these dates go across the top i.e. cell C3 = 15th jan & D3 = 13th Feb.

I would like to return a % in cell C4 which relates to the amount of total days in the segment that relate to Jan (ie. 29 days in the segment, 16 relate to Jan so 55.2%).

Cell C5 would then return a % which relates to the amount of total days in the segment that relate to Feb (29 days in the segment, 13 relate to Feb so 44.8%).

Cells D4&D5 would return the next reporting segment and how many days in Jan/Feb respectively (the answer will be 0 but a constant formula acrosss all would be perfect. tried to give as much info as poss.

View 2 Replies View Related

Date Formula- To Count The Number Of Days Between 2 Dates

Aug 4, 2008

I have been using a formula to count the number of days between 2 dates and if the date was older than 12 months it would work fine.

The data that i was using has been changed and they have decided to change the format of the dates and dropped the year reference no all i have to work with is dates like 27-07 this represents 27th July i can format this date to work fine unless the date falls before 1 jan this year all i get is lots of numbers and it stuffs up the whole calculation.

The formula i am using to compare the dates is

=DATEDIF(N31,$D$1,"d")

View 9 Replies View Related

Formula To Count Number Of Days In Date Range - Split Per Month

Jan 23, 2012

I have a large spreadsheet which holds lots of data with date ranges that i need to performs different actions to. Any way to identify the number of days, per calender month, that falls in a date range.

sample data...

Start Date
End Date
Old Value
New Value

08/03/2010
18/06/2010
16758.2
16758.1

[Code] .......

I need to break down the total number of days per month

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

24
30
31
18

[Code] ......

As you can see this also laps into a new year, which poses my next problem, ill probably just add more columns on to the end of the table for that though...

I will later apply different calculations to these cells but in short need to get a calculation for the number of days per month first.

(in short spreading the new value out accross the year then multiplying it by the days... i also need to apply a further daily volume cal to it).

View 8 Replies View Related

Stop Count Of Days When Date Is Entered On Specific Cell - Excel

Mar 17, 2014

excel.jpg

how to make my network days stop counting when I insert a value in the completed column (in this case H3). I have a Date Received column (A3), a due day column (G3) and the last column with the date (N3). My remaining days column keeps counting after I filled the completed cell (H3) and won't stop counting after. I need a formula to stop after the completed cell is fill up.

View 5 Replies View Related

Calculate End Date Using Start Date And Number Of Days Excluding Specific Days

Nov 22, 2013

I want to calculate the end date of my German courses. This is how it works:

A course consists of 60 LU*. The course can occur i. e. three times a week: Monday, Wednesday and Friday. In each day the course lasts 2 LU, which means 6 LU each week. There is no course on Tuesday, Thursday, Saturday, Sunday and on holidays. Therefore this type of course that begins on 18-Nov-2013 will end on 03-Feb-2014.

Another course which occurs Tuesday, Thursday and Saturday, and respectively has 2 LU on Tuesday, 2 LU on Thursday and 3 LU on Saturday and starts on 03-Dec-2013 will end on 06-Feb-2014.

Therefore I want to create a worksheet where I set the start date, choose the days and respectively the LU amount on those days. The end date shall be calculated according to these criteria.

The workday function on excel cannot do this and I do not have any programming skills to work with VBA.

Legend:
*LU = lesson units; 1 LU is 45 minutes

Holidays:
28-Nov-13
29-Nov-13
08-Dec-13
09-Dec-13
25-Dec-13
31-Dec-13
01-Jan-14

[Code] ...........

View 7 Replies View Related

Count Days HH:MM Using Network Days

Sep 28, 2011

I need a formula to count how many days hours & mins between 2 dates but included in the formula need to ensure it only counts business days.

Column A 02/09/2011 13:00

Column AO 02/09/2011 13:02

I need in Column AP to show 0 00:02

The formula I have tried using is - =IF(AO3="","",AO3-A3) which doesnt work as instead of showing 0 00:02 it shows 1 00:02. I dont want it to count as 1 day just 2 mins.

Once that has been worked out I need to include WORKDAYS formula to only count working days. I have created the list on 'Controls' Tab Column A10:A47.

merge these together to create the one formula?

View 6 Replies View Related

How To Auto-Populate Date Range (working Days Only) From Start Date And End Date

May 25, 2014

I am now trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.

View 1 Replies View Related

Date Countdown: Results Of The Number Of Days Between Today And A Future Date

Apr 8, 2009

I am trying to get the results of the number of days between today and a future date. I am using ="cell containing futuredate"-today() and it gets me the correct number of days. The problem comes in when I have yet to populate the future dates. I am getting -39991 (numeric value between today and jan 01 01) and because I am also using conditional formatting this is even more of a problem. Is there a way get excel to display nothing if it is a negative number? or to give a specified resut if the number becomes negative such as Expired or something of that nature?

View 3 Replies View Related

Calculate The Number Of Days From A Date Entered Into Cell A1 To Today's Date

May 19, 2009

I need a formula that will calculate the number of days from a date entered into cell A1 to today's date. Whether it's before or after todays date. Example:

5/10/2009 to today is -9

5/22/2009 to today is 3

View 2 Replies View Related

Counting Days Positive Or Negative Between Date (inserted Value) To System Date?

Mar 19, 2012

how can i count the positive days to a inserted date value or the past days (negative value) to the system date (today).

View 5 Replies View Related

Macro To Alert If Today's Date Is Within 5 Days Of Expected Delivery Date

Sep 18, 2008

I have a worksheet that has a sent date and expected delivery date I need create a macro that will alert me if today's date is within 5 days of expected delivery date.

View 14 Replies View Related

Calculate Number Of Days Between Two Date Within A Current Month Including End Date

Apr 2, 2009

I have two columns of dates, leave start and end dates (when people start leave i.e. annual leave). Would need to introduce column(s) to calculate how many days fell within the month including the end date and excludes weekends.

For example, if the staff on leave from 31st March to 6 April, i need to show that the number of leave taken as 1 day in March and 4 days in April.

View 9 Replies View Related

How To Auto Populate Date Range (working Days Only) From Start And End Date

May 26, 2014

i am trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.

View 4 Replies View Related

Count Last 10 Days

Sep 22, 2006

I have a spreadsheet with a list in column A, and starting from column D in row 1 are daily dates e.g. 01/10/06, 02/10/06, 03/10/06. On a daily basis an x is added manually to the spreadsheet where the list criteria matches the specific date e.g

A B C D E F
1 01/10/06 02/10/06 03/10/06
2 M123 x x
3 M456 x x
4 M789 x x

What i would like to do in column C is to measure how many x's are in the last 10 days for each row. I have used formulas in the past to do something similar but I can't find them. Sorry I can't upload a sample but firewall won't allow.

View 8 Replies View Related

Extract Character From Date Format & Number Of Days Between Date

Jan 17, 2010

I have two questions regarding date format and hope you can provide input.

1) say 01/01/2010 displays as Jan-10 and i need a new column to state it as JAN. What function should i use to achieve it?

2) i need to state the difference between first day and last day of the month. What function should i use to achieve it?

View 2 Replies View Related

If Date Cell Less Than Todays Date Calculate Difference In Days

May 13, 2008

I have column B with a heading "Days Remaining" and column L with a heading "Deadline". starting with row 5, I need to be able to enter a date in L5 and see the days I have left, from that day untill today, on B5. I need to then be able to enter a date into L6 and see a result in B6 and on and on. Then I need to be able to insert or delete a column and have the formulas still work in the columns with the heading "Days Remaining" and "Deadline"

View 7 Replies View Related

How To Count Amount Of Days

Sep 1, 2008

Is there a formula to count the amount of days, for example.....a1=8/1/08 b2=8/10/08 then c1=9 days....

View 4 Replies View Related

Count Days Not At Site

May 8, 2014

I have the vacation sheet so I can track my vacation hours used and available. The last thing I need is a way to count the number of days I'm not at my site. It doesn't matter why (Training, Holiday, Travel or Vacation) I need to track total days of site.

View 4 Replies View Related

Count Days Formula

Dec 31, 2006

I would like to have a formula in a spreadsheet of personal bills that counts down the number of days until each one is due each month.

In one column, I have a digit in each cell to represent the day of the month each month that the bill is due. Someone helped me with a formula that can count down days to a date that is a higher number than the present day of the month, but can I get a formula to count the days from, say, December (or any month) 28th to a due date of the 6th (of the next month)?

View 9 Replies View Related

Count How Many In A Month Days

Jun 27, 2007

I need to count how many in a month per day X number is =. I originally used Countif -

=COUNTIF(B3,">25252525=36")+COUNTIF(V3,">=36")+COUNTIF(X3,">=36")+COUNTIF(Z3,">=36")

The formula above works, but i end up with several long strings of Countif. I'd like to know if there is a way wherein i can use a shorter formula.

View 9 Replies View Related

How Can I Count Workable Days

Jan 15, 2009

when I try to calculate the worked days between two dates using the formula "Networkdays" in excel, the result just count the days from Monday to Friday.

Example:

If I want to calculate the workable days from 12/1/08 (Start_date in cell A1) to 1/14/09 (End_date in cell A2) by using the formula: =NETWORKDAYS(A1,A2)

the result will be 33 days, but due to fact that I also need to count Saturdays, the result that I need must be 39 days.

View 9 Replies View Related

Count Days Between Two Dates

Apr 13, 2007

vba excel?

I wish to calculate the days between the starting date (column A) and ending date (column B). For the first 7 days are excluding all the holiday and weekend and the rest of it until the ending date are counted.

View 9 Replies View Related

Count Days In Specified Month

Jul 27, 2007

I am using the following array to determine the total dollar of contracts reviewed in one month.

=SUMPRODUCT(($C$5:$C$3002>$H18)*($C$5:$C$3002<$I18)*(D$5:D$3002))

Column C has the actual Date
Column H the beginning of the month
Column I the end of the month and
Column D the dollar amount

Now I would like to count the number of contracts that fall in the following categories in a given month. The minimum number is in Column N and the maximum in Column O.
1-499,999
500,000-2,499,999
2,500,000-4,999,999
5,000,000-12,499,999
12,500,000-24,999,999
25,000,000-64,999,999
65,000,000+

I can get the count for each category but am having difficulty with the count in the specific month. Does any one have any suggestions - other than a pivot table?

I am attaching a small sample.

View 4 Replies View Related

Count Dates Within Last X Days

Sep 6, 2007

I am trying to count the number of dates in a column that are within the last 180 days. I tried using COUNTIF and it did not work. Formula which I thought should work: =COUNTIF(A3:A32,>(A40)). My workaround is shown in Column B, but this method adds one column for each participant.

View 5 Replies View Related

Formula For Date Minus Date = Number Of Days

Nov 15, 2008

I was wondering if anyone knows how I could enter a date in one cell, then another date in a second cell and in a third cell have it have it so it minuses the first date from the second and calculates the difference outputted in number of days.

Example: 04/31/08 - 04/01/08 = 30 (days)

View 2 Replies View Related

Number Of Days To Add To Date Based On Weekday Of Date

Apr 23, 2008

I need to create a formula that states a delivery date when the order date is entered in an adjacent column. Items ordered on Monday, Tuesday and Wednesday will be delivered the Friday of the following week, eg. ordered 23rd April 2008, delivered on the 2nd of May 2008. Items ordered on Thursday or Friday will be delivered on a Friday 2 weeks later, eg. ordered on the 24th April, delivered on the 9th of May 2008

View 4 Replies View Related