Formula To Get Inclusive Dates In Between Start And End Date

Jan 21, 2014

I have a table where I assigned Months (Jan-Dec), Current Month YTD (e.g. Nov YTD) and Dec YTD in the column field. Company Name and Year in rows.

For a particular company for example, Co.AAA. The Start Date is Oct 1, 2009 and the contract will end on Sep 30, 2014.

If my current reporting month is Nov 2013, From the table, I need to get the sum up the data that correspond from this dates inclusive in start and end date of Co.AAA.

Inclusive Dates are:
Dec YTD 2013
Dec YTD 2012
Dec YTD 2011
Dec YTD 2010
Dec 2009
Nov 2009
Oct 2009

If this is not possible, what other solution I can use to get the correct number?

View 9 Replies


ADVERTISEMENT

Days Between 2 Dates Inclusive

Jul 25, 2007

I have a simple formula to work out the number of dates between to dates
ie: =U6-T6

This works out the days between 9 may and the 31may as 22 days
but i want to show the correct number of days including the 9may so this would be 23 days.

I tried this =U6-T6+1 which was fine but all the empty cells now show the value 1 in them.

View 5 Replies View Related

Return Months Between Start Date & End Dates

Jul 6, 2007

I have been trying to search for either a function or VBA that will perform the following:

If I enter I want all months >=1/1/07 and <=3/31/07 it would tell me that the months in between are January, February and March and so on with all dates.

View 3 Replies View Related

How To Calculate Future Dates From Start Date On A Monthly Cycle

Sep 16, 2009

I'm trying to combine monthly calculations with "today" and with "workdays"

Example:

start date = 01/01/2009

today's date 09/16/2009

formula result = 10/01/2009 ; or if 10/01/2009 is a Sunday, result = 09/29/2009 (not 02/01/2009, 03/01/2009, etc)

=edate gives me a month but it doesn't skip weekends or calculate beyond today's date

View 14 Replies View Related

VBA / Function To List All Dates Between Start And End Date Excluding Sundays

Feb 8, 2013

I need the VBA/UDF to produce a column of dates between a start date and end date, excluding Sundays.

I can see lots, excluding weekends, but very little for just Sundays.

View 4 Replies View Related

Selecting Entire Date Range To Be Lookup Based On Start And End Dates

Mar 6, 2013

I have an excel sheet where I would like a user to enter a start date and end date(say Feb 1, 2013 to Feb 28,2013). And these dates will be able to change to whatever month the user wishes to look up in a specific date range(column A has 365+ dates). This post is closely related to [URL]... but I cannot figure out how to get it to work from my case.

So working off the same worksheet, I have the beginning date in AC35 and the end date in AC36 in which the user enters. I would like the dates that fall in this entire month, including the beginning and ending dates to be referenced when looking for the specific day that contains a value I have in S35.

In other words, I have data in columns A through N. The dates are in column A and S35 is a value obtained from using Max(L185:L526) where L185:L185 is manually selected each time I want a different month. I don't want this to be a manual process of scrolling down the spreadsheet to get the next month.

View 12 Replies View Related

Calculate Future Dates From Start Date With Varying Time Period/cycle

Sep 11, 2009

I need to determine a formula which will allow me to calculate a future date based upon a current date with varying time periods.

For example:

I have a bill which is paid on the 15th and last business day of each month. I would like to be able to see the next due date regardless of what day of the week it is.

I have a bill which is paid every other Tuesday. I would like to know the next due date without having to enter +14 for every due date in the future. In other words, it is preferable to be able to open the spreadsheet and automatically see the next due date, not use autofill to repeatedly add +14 to a previous date which would limit the # of future due dates that could be calculated.

I have a bill which is paid on the last business day of each month, not the last Friday of each month. I would need excel to return a value for the last day of the month which = Monday-Friday, regardless of what day of the week it may be as long as it isn't Saturday or Sunday(holiday exclusion would be nice but not required).

View 14 Replies View Related

Multiple IF's And AND Inclusive Formula (all In One Cell) That Would Look At The Above Table And Depending Upon The Price Paid

Oct 24, 2008

.............................24............30............36
300014999..........9.00%.......11.00%.....12.00%
1500099999........9.50%.......11.50%.....12.50%
100000249999.....9.00%......11.00%.....13.00%

I need an all inclusive formula (all in one cell) that would look at the above table and depending upon the price paid (3000-14999 or 15000-99999 or 100000-249999) and depending upon what monthly term they choose (24, 30, or 36), the appropriate finance charge would be used to calculate a total cost (9-13%). The only way I know to do this is by using IF's and AND's, but there are simply too many arguments and I cannot properly write the formula.

View 4 Replies View Related

FORMULA To Calculate Start Date

May 2, 2013

if I've worked in the company for 9.0384 years, how can I calculate that my start day was 04/20/04?

View 3 Replies View Related

Array Formula - Finds Date Then Start Adding Values Until Specified Sum Reached

Jul 23, 2014

I have an Excel workbook with two sheets "DataSheet" and "Actual Peaks", "DataSheet" contains a column with dates and a column with values. "Actual Peaks" has a bunch of dates listed in a column. For each date in 'Actual Peaks', another column goes back to the "DataSheet" finds the date, then starts adding values until a specified sum is reached, once the sum is reached, it returns the date at which the sum was reached. However, I have found that sometimes it is off by a day or two.

See the attached workbook for a much clearer example : Excel_forum help 7-23-14 DD validation.xlsx‎

View 7 Replies View Related

Compute The FuTure Date When Start Date,Lead Date,Weekly Offs,Leaves And Holidays

Nov 15, 2008

First and foremost I would like to congragulate you on this wondeful piece of code in the below link...

The query was to get a future date excluding Fridays and Holidays...

http://www.excelforum.com/excel-work...rkingdays.html

I have a similar query and therefore I pasted this link...

I actually wanted to get a future date using a Dynamic two day off as my the offs keep on changing as well as incorporate Holidays and Leaves if any..

Now Holidays would be official Public Holidays and
Leaves would be taken by the employee..

The code needs to pick the Leaves + Holidays and different offs maybe even more than 2 offs...

View 7 Replies View Related

How To Auto-Populate Date Range (working Days Only) From Start Date And End Date

May 25, 2014

I am now trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.

View 1 Replies View Related

Calculate Next Due Date Based On Start Date Frequency And Current Date?

Mar 9, 2014

I'm trying to workout how to take a known initial date a repeating frequency and work out the next due date from today.

Example

Initial Date :- 1st of January 2014

Frequency :- every 5 weeks

Current Date :- 9th of March 2014

Next Due date should be :-12th of March 2014 (if I worked it out correctly from my paper calendar)

I want to use a cell formula to do this for different initial dates and varying frequency periods (the frequency will always be whole weeks i.e. 1,2,3,4,5,6,7,8,8,10)

View 4 Replies View Related

Difference Between Start And End Dates

Jul 27, 2009

I need to compute the no. of days between start and end dates and spread no. of days on each month. I've attached a spreadsheet with examples and further explanation.

View 3 Replies View Related

INDEX Value Between Start And End Dates

Sep 2, 2012

I have some Start & End dates with some values. Based on lookup dates I like to get third column values.

Start Date
End Date
Places

Jul 1 2011
Jul 25 2011
A

Jul 5 2011
Aug 25 2011
B

Jul 7 2001
Jul 15 2011
C

Jun 29 2011
Jul 5 2012
D
A2:A5 Start Dates
B2:B5 End Dates
C2:C5 Places

E2:E3 is lookup dates, Jul 6 2011 & Jul 7 2011

So return values from column C fall under these dates.

Answer is A, B, C

I tried this formula

=IFERROR(INDEX(C:C,SMALL(IF(MMULT(ISNUMBER(MATCH(A$2:B$5,ROW(INDIRECT(E$2&":"&E$3)),0))+0,{1;1}),ROW(C$2:C$5)),ROW(A1))),"")

But this wouldn't work as expected. Only return C. I am using excel 2007.

View 4 Replies View Related

Retrieve Name Between Start And End Dates

Sep 14, 2009

I want, based on a given date let's say 6 months ago from today (03/01/09), a formula that tells me the name of the person that finished Between the started and the GIVEN date (03/01/09). The result should be: Name2

I can also use a formula that shows, condition results such as: True..."OK", false "out of range".

View 9 Replies View Related

Find Start & End Dates

Jul 11, 2007

I have a list of employees and the dates on which they were absence from work for a set period (i.e. one month). Some employees have been off for a day, some for longer. This data has been pulled from a large datasheet and now needs formatting to add in the start and end dates of absence, ready to upload to a payroll system.

The Problem:
I have been able to get a macro working on a simple list of names, however the problem arrises where I have 2 employees off on the same day - I was using a loop to find the date last used, but this no longer works.

My Request:
A copy of the worksheet in question can be found here : http://www.carpe-luna.com/other/AbsenceQueryHelp.xls

But I'll try and describe the layout as much as possible
This is how my raw data is set up. (Up to row 50 but potentially more)

A.........B...........C..............D...........E.........F
EmpNo.....EmpName.....Start Date.....End Date....NoDays....NoHours
612.......Paul........26/01/07.............................12......
612.......Paul........27/01/07.............................12......
615.......Ian.........27/01/07.............................12......
758.......Peter.......16/01/07.............................12......
758.......Peter.......17/01/07.............................12......
758.......Peter.......18/01/07.............................12......
...........................................

View 9 Replies View Related

Date Formula For Rolling Dates?

Jun 25, 2014

formula to input to excel to get the dates rolling down in A cell i want it to go A1(1/1/2014) A2(1/1/2014) then a3(2/1/2014) a4(2/1/2014) a5(3/1/2014) a6(3/1/2014) i have a lot of these dates to put into excel

View 5 Replies View Related

Identifying Start And End Dates In A Series

Jul 11, 2007

i am trying to both identify the start date and the end date of a series in excel.

if you will, picture a spreadsheet with two rows with data. the top row is comprised of dates in mm/dd/yy (end of month) format. the bottom line is percentages . . . a corresponding % for each date directly above. these percentages add to 100%. in two separate formulas, I would like to identify:

1. the date in which the first %>0 occurs (start date)
2. the date in which the cumulative addition of all months %'s equate to 100% or the date in which the last %>0 occurs (end date)

keep in mind many if not most of the %'s will be 0%.

View 13 Replies View Related

Running Reports With Start / End Dates

Aug 21, 2012

Running reports with start and end dates, example I need dates to Start 10/01/2010 and end date of 09/30/2011, retrieved date has some dates before 10/01/2010 so I need a formula to change that date to equal 10/01/2010 and the same for the end date need to have that date change to 09/30/2011.

View 3 Replies View Related

XIRR With Moveable Start Dates?

Jun 5, 2014

I am trying to automate calculation of IRR for a range of scenarios.

I have a bunch of problems with this:

1. On a full cycle basis, the project start dates are not equal which means that in certain scenarios I get 0% return as the first cash flow is zero.

2. On a point forward basis, negative cash flows may start after T0 (i.e. now)

I have circumvented this on NPV basis by using a Sumproduct of individual cashflows, discount factors (full cycle cashflows are inflated to T0) and a proportional period factor (where T

View 1 Replies View Related

Unique Start And End Dates For Chart

Jan 12, 2008

I have searched for a 'simple' solution to this but I only ever seem to find complex and indepth examples.

I summarise web hit information then chart it so I can look for trendlines. I get good info from the stat company so I can see where folk are coming from, search engine, weblink etc etc.

Once I have summarized it I have date running along the column headers then it is broken down through the rows so I have

Total Hits
Total Paid Advertising
Total Search Engine

And so on for my rows

As the days go on the data gets harder and harder to read so I was hoping I could use some kind of OFFSET function to select my data. So if my dates run from 2/11/07 to today I would like to perhaps say to Excel that I might want to see 20/11/07 to 20/12/07 in my chart.

I have plenty space to put the start and end date and I have a basic block of data.

View 9 Replies View Related

How Do You Subtract Start/end - Dates/times In Vba?

Dec 8, 2009

How do you subtract start/end - dates/times in vba?

I know how to do it with formulas, but can't grasp it with vba. My range will always change, so I'm trying to avoid formulas (Cutting rows etc...)

I need Col D-Col B (end date-start date) and Col E - Col C (end time - start time)

Would doing the calculation on the userform be the best way, or trying to do the calculation with the ws code?

View 9 Replies View Related

List All Dates Between Start _date & End_date

Dec 30, 2009

i had a worksheet with the dates in Column A.I want to return the dates that fall between the two dates (Start_date- Column B-List of Dates) & (End_date Column C-List of Dates) in Column D.I had been trying with this but could not find a function to return the dates.

I tried using the filter >> Custom Filter >>>.Got the result.But i want to know the formula for the same.

View 14 Replies View Related

Return The Number Of Months There Are Between The Start And End Dates

Nov 13, 2006

if A1 is a start date and B1 is the end date, I want C1 to return the number of months there are between the start and end dates?

View 9 Replies View Related

Changing Calendar Start And Stop Dates

Jun 20, 2007

The company I work for does not use the usual calendar dates and uses a modified calendar. As an example, the month of January is Dec 31 thru Jan 27, February is Jan 28 thru Feb 24 and so on. I need to group data using a pivot table and summarize data by month, but as I just described above, calendar months will not work. Is there a way to modify what Excel sees as monthly dates?

View 9 Replies View Related

Simple Date Comparison Formula - When Two Dates Are Equal To Each Other

Feb 10, 2014

Report I generate once a month that checks to see if tasks are done on or before their due date. Sometimes it works, and others it doesn't...

The basic formula is: [Code] .....

If they closed their task by or before the due date, the condition should be true and it should output "Compliant" beside their task. Otherwise their "Over Due".

The forumla works except when they close their task ON the due date. No matter how I tweak the forumla, it thinks the condition is false as if it cannot tell when the two dates match.

View 1 Replies View Related

Conditional Formula: Calculate The Difference In A Date Between Two Dates

Jan 28, 2009

I'm trying to make a formula to calculate the difference in a date between two dates. For exaple, in my business we have a due day for something. So the due date could be Feb 10, we need to know if it was done on time, late, or early. So I've gotten it to display late by doing this: =IF(B2>A2, "Late", (A2-B2)) But then I can't figure out how to incorporate this: =IF(B2=A2, "On Time") or =IF(B2<A2, "Early").

I would like to displaly this all in one cell. So if the due date is Feb 10 and it's turned in Feb 8 it's early, turned in Feb 10 it says on time, turned in Feb 11 it's late. I also tried this but it didn't work: =OR(IF(B2>A2,"Late")*IF(B2=A2,"On Time")*IF(B2<A2,"Early"))

View 3 Replies View Related

Date Conversion Formula For Dates Formatted With Period

Aug 19, 2012

How to create the formula for dates formatted with periods.

Dates are as follows:

01.07.12 - should return as 1-Jul
01.08.12 - should return as 1-Aug
02.08.12 - should return as 2-Aug

View 4 Replies View Related

2 Columns With Dates - Formula To Show What Column Has Date?

Apr 15, 2013

I have 3 columns (Name, Pass Date, Fail Date) Each name will only have 1 date in either column B or C.

I want a formula that will say "if there is a date in the pass column (B) then this name is a pass, if there is a date in the Fail column (C) then this name is a Fail"

View 3 Replies View Related