Manpower Resource Planner
Jan 21, 2008
In the past the Manpower Company has put out a yearly spreadsheet allowing an employer to keep track of employee time off. They are not making one this year. Looking at last years sheet, all the calculations are locked. Has anyone seen this sheet in the past and know how it works? You can put in something like v8 in a dated cell and excel subtracts 8 hours from a yearly vacation total. The v in front of the 8 stands for vacation and you can also put in a p for personal time etc..
View 9 Replies
ADVERTISEMENT
Aug 13, 2009
I have a copy of a year planner that calculates the days of the month and adjusts them according to the year input into the header area.
Would anyone please modify it so that the first column reads August and the last column reads July (instead of Jan to Dec) and still maintain the calculations as required?
View 14 Replies
View Related
Apr 8, 2012
I have 7 teams (82 staff in total) staff who work for several production line. we currently record all leave on the wall calender. I want start recording these on a spreadsheet and I wonder if any of you have already designed a annual leave planner that I could have a copy?
Staff can request for 1/2 annual leave as we all full day. Each Team is listed on a seperate sheet and if a team has more than 2 person on leave, it will go red.
View 3 Replies
View Related
May 29, 2008
I have one workbook with two worksheets (Jan-JUly and Aug-Dec). I am using a userform to add data into worksheet ("Jan-July"). But I do not have any clue - How do I update the other worksheet (same data like name,join year etc)worksheet("Aug-Dec") at the same time. I used two worksheets because worksheet doesn't support 370 columns, and to make my life easy. UserForm add data into Column A to M (worksheets Jan-July), rest is done manually. I have also attached the file.
Private Sub dataAddButton_Click()
Dim dataCheck, eMsg As String
Dim strLastRow As Integer
Dim x As Double
strLastRow = xlLastRow("Jan-July")
'get Last Row
With dataInput
'dataInput name of userform
If (.fNameBox.Value <> vbNullString And .fNameBox.Value <> vbNullString And .joinYearBox.Value <> vbNullString) Then
'textbox validation value can not be empty......................
View 2 Replies
View Related
Jul 31, 2013
I love the set up of the "Monthly Meal Planner" template in Excel 2013 and would like to do something similar for another file I want to set up. How do I learn how to make those tabs across the top - "Meal Plan", "Ingredients" etc?
View 3 Replies
View Related
Apr 7, 2009
I wish to have a simple planner displaying the academic year with only mondays' dates.
ROW 3 displays the dates
Column B is Week 1
Cell B3 is the first date (10.08.09)
Cell C3 should read 17.08.09
Cell D3 should read 24.08.09
ETC
I have managed to do it using autofill before but I can't get it to do it now. Is there a preferred way to achieve this?
View 5 Replies
View Related
Aug 5, 2009
i am getting the error run-time error '-2146697211 *800c0005)'': the system cannot locate the resource specified
when running the following:
my guess is because sometimes the internet connection doesnt always work, or the page loads too slow, but 'on error resume next' doesnt work because the line takes awhile to execute and then excel turns off
i believe i saw somewhere here (mrexcel) how to give specific commands a limited time to run. i dont rememeber how to do this though, or any other workaround ...
View 9 Replies
View Related
Mar 18, 2009
I was created an annual leave planner and I would like the box in Colum A to reduce the number of days they have left every time they book leave. I would like it to start off as 25 days leave including UK bank holidays.
View 4 Replies
View Related
Jan 22, 2010
Is there any weekly leave planner that shows the dates of the mondays in the month? eg in Jan we have 4,11,18,2
View 3 Replies
View Related
Feb 7, 2013
I want to write a formula that will sum the hours in a table based on the name of a resource, a task name, and the month it was entered. So my table looks something like this:
Name
Task
Month
Hours
Person 1
Meetings
201201
2
Person 2
Misc
201202
1.5
There are additional columns, and it has over 80,000 rows...
For example, I thought that the formula to sum the hours for Person 1 if the task is meetings and the month is january would be:
SUMPRODUCT((A1:AX="Person 1")*(B1:BX="Meetings)*(C1:CX=201201),D1:DX)
I also tried SUMPRODUCT(--(A1:AX="Person 1"),--(B1:BX="Meetings),--(C1:CX=201201),D1:DX)
View 9 Replies
View Related
Jul 30, 2013
I am trying to create a resource capacity planning per project and I have some issues with some functions. Here is what I did :
1/ I have a workbook for each project with 4 sheets : "Project", "Pivot", "Project Identification", "Capacity"
2/ On the Project sheet I have the volume of man days for resources (rows, can be multiple according to the resource skill) per project phases (columns, always Gate 1 to 6).
3/ On the second sheet I have the pivot table of the first sheet which sum up the volume of man days for each resources per project phases.
4/ On the third sheet I have a project identification table with the columns Date, Week Number, Duration (Weeks), Phase (Gate 1 to Gate 6, so 6 rows). I required the user to enter the date of each Gate, the week number and duration are calculated.
5/ On the last sheet I have my capacity planning with:
- the number of columns is always 52 corresponding to a full year, but can start in the middle of the year, for example start week 30 to end week 29.
- the first row is the weeks numbers, the first cell is the week number of the Gate 1 date, the following cells are the previous cell +1 ( fx=IF(B1>51;1;B1+1) )
- the second row is the phase we are in at that week ( fx=VLOOKUP(B1;'Project Identification'!$B$2:$D$8;3;TRUE) )
- the following rows are the man days for each resources (1 row per resource), this is only the volume of man days for the phase identified in the sheet "Project" divided per the number of weeks for this phase. ( fx=IF(Pivot!$A2="";"";IF(C$2="";"";HLOOKUP(B$2;Pivot!$B$1:$G$4;ROW()-1;FALSE)/VLOOKUP(B$1;'Project Identification'!$B$2:$C$8;2;TRUE))) )
This is working ok if the project execution is within a year (for example from week 20 to week 41). But if the project is over 2 years (for example from week 41 year n to week 12 year n+1) it does not work at year changing.
For example if I have Gate 3 on 19/08/2013, Gate 4 on 30/11/2013, Gate 5 on 29/01/2014 and Gate 6 on 12/02/2014 then on the "Capacity" sheet for week 34 I will have Gate 3 but on week 35 it will switch directly to Gate 6 up to week 52 and then at week 1 I will have "#N/A".
View 3 Replies
View Related
Mar 4, 2010
what i am trying to do is use concatenate in a vlookup to search for a resource number and date, then return another column in the array.
the formula looks like:
=VLOOKUP(CONCATENATE(D7,$H$6),Roster_Allocation,7,FALSE)
but only results in NA.
if i search for the resource number only, i get the correct result.
also, the res# and date are concatenated in the table array. could this be related to the way excel is storing the dates (40241?) even though both concatenated fields look the same?
i have also tried adding a new coumn which has the res# and dates concatenated as the lookup value but still all NA.
View 9 Replies
View Related
May 31, 2006
I'm using Excel 2002.
I have one workbook with data linked to another CSV file (It's about 40000rows). When I open the workbook, "THis workbook contains one or more links that cannot be updated." message appears and asks me to open csv file if I wanna to update (although I set full path for links in cells). I wonder if there's any way to update link without opening csv file? Or Excel can not update link without openning the resource file?
View 3 Replies
View Related
Mar 25, 2014
Resouce Capacity Management .xlsx
How do I make my Pivot Table count/Sum the Threshold of each resource within department is within our 80% to 120% threshold?
View 1 Replies
View Related
Sep 17, 2009
I need a macro to get the values from cells D29 and H24 in the Resource Calculator sheet and populate it into cells N8 and O8 in the Input form.
Users will then be able to change the information in the calculator and click the macro again to populate N9 and O9 and so on.
Is there a way to do this?
I've attached the file for you to see.
View 13 Replies
View Related
Apr 19, 2006
I have the following code for a sheet in my workbook that has 3 charts:
Private Sub Worksheet_Change(ByVal Target As Range)
Application.Calculation = xlCalculationManual
ActiveSheet.ChartObjects("RdteObs").Chart.SetSourceData ThisWorkbook.Names("GSumRdteObs").RefersToRange
ActiveSheet.ChartObjects("RdteWip").Chart.SetSourceData ThisWorkbook.Names("GSumRdteWip").RefersToRange
ActiveSheet.ChartObjects("RdteExp").Chart.SetSourceData ThisWorkbook.Names("GSumRdteExp").RefersToRange
Application.Calculation = xlCalculationAutomatic
End Sub
but whenever the sub runs, I get this error message: "Excel cannot complete this task with available resources. Choose less data or close other applications." Does anyone have an idea what's going on?
View 3 Replies
View Related