Workday Function Use In VBA
Aug 15, 2006
I have a spreadsheet setup that uses the workday function. Shown as follows: =Workday(P$2-1,V2,Z2:Z$11)
P2 is a set date in which the location will not change. Z:Z is a list of Holidays. V2 should offset by 1 row. I want it when a command button is hit it runs that formula untill the rows value = "End". I have found "Working with Workdays" information at MSDN's website http://msdn.microsoft.com/library/default.asp?url=/library/en-us/dnvbadev/html/workingwithworkdays.asp It seems to be for access but I'm trying to use in Excel and I am getting errors/confused. The main error I'm getting is Compile Error: Method or data member not found because of rst.FindFirst.
View 7 Replies
ADVERTISEMENT
Jul 31, 2008
The function is to show the next workday date in cell a1
View 15 Replies
View Related
Jan 3, 2007
This is probably a simple question, but one I can't figure out after several hours. I am creating a spreadsheet focused on certifications.
I need to take the date each initial certification was achieved, and add x years to each cert, which is simple enough.
The sticky part is that the (date + x years) can't logically be a weekend; if it is, I need to subtract one or two days from the result, so that it's the *weekday* immediately prior.
e.g. if my initial certification date is: 1/23/2006 and my certifcation expires in four 4 years:
A47= date(2006,1,23)
h47= 10
=DATE(YEAR(A47)+H47,MONTH(A47),DAY(A47))
Result = Saturday, January 23, 2010
If the result is a Saturday or Sunday, I need to subtract one or two days from the date. In this example, I'd like: Friday, January 22, 2010 as the result.
I've been playing with 'if', et. al., to no avail.
View 9 Replies
View Related
Mar 14, 2007
I am in need of some excel advice relating to date calculations. Basically I need a function that is the equivalent of WORKDAY but for hours instead. I have a series of events that take a certain length of time to complete, most of them less than a day but some more than. By way of example see the screenshot below:
In reality the last three operations would have to take place on the 27th of April, with the Welding operation starting on the end of the 25th around 7pm. The plant is running a 24 hour day, and works 5 days a week. How can I calculate the times in hours offset rather than going day by day? I need to account for
* Weekends
* Fixed Holidays
* Operations running as seamlessly as possible
Any advice welcome. I have attempted to use WORKDAY with the number of days to deduct rounded to the nearest day and then subtracting the operation time but this results in errors where operations would cumulatively go over a working day. The objective is by knowing when the end product is needed and knowing how long each operation takes it is possible to discover when to start manufacture. VBA or Formula code is fine as this will be integrated into a VBA project.
View 6 Replies
View Related
Jun 11, 2009
As everyone realizes that WORKDAY function can return a working date that exclude weekends and any dates identified as holidays. However, what if I want to return a working date excluding my designated holidays but including weekends?
For example,
Holidays are 1 Jun 2009, 2 Jun 2009 and 4 Jun 2009
Start Date: ???
Finish Date: 8 Jun 2009
Duration: 5 days
The Start Date should be 30 May 2009.
Seems like I am not able to use WORKDAY function to calculate the start date.
View 11 Replies
View Related
Aug 8, 2006
I'm at my wits end trying to make a workday formula work, but am having no luck. I've searched the other posts, but did not quite find a match. I'm trying to subtract a number of days from a workday function, but it seems to bypass ignoring the weekends (as is supposed to be done automatically with Workday). Here's the formula I'm trying to use:
=WORKDAY(H5,L5,' Reference Info'!$E$110:$E$117)-(I5/8)
I5/8 is a column with hours - this just calculates a number of days to subtract based on the number of scheduled hours.
The formula will calculate, but it still ignores weekends. I've tried burying the I5/8 within the parenthesis, moving it around in the formula,
View 7 Replies
View Related
Feb 27, 2008
I'm trying to make a schedule of deposits made for the month of March 2008. (Deposits are made on a daily basis.) With this, I wanted to know when the deposit would clear with the bank using the WORKDAY formula given that I have to count 6 banking days after the date of deposit (Saturdays and Sundays excluded).
I'm using Mac and I recently upgraded to Office 2008 (never tried WORKDAY formula in other versions). I am aware of the syntax used for this formula and it works just fine in other cases. But I noticed that with start_dates falling on a Thursday or Friday of the week, Excel would give me a result date that falls on a Sunday, which is odd given that it's supposed to ignore non-working days or weekends. (I haven't even gotten to inputting holidays yet.)
View 6 Replies
View Related
May 26, 2009
Maybe I'm getting a blank, maybe the answer is so easy, but lately I can´t solve this: How do I use conditional format to change cell color if cell value (date) is not workday?
View 4 Replies
View Related
Jul 22, 2009
I have two dates in this format:
start: 17.07.2009 11:00:00
end: 17.07.2009 14:00:00
i need to check if the period in between those is during a workday.
our workday starts at 10:00:00 and finishes at 19:00:00
so my expected result is 3 hours. (1400-1100)
other example:
start: 17.07.2009 11:00:00
end: 18.07.2009 11:00:00
result is 1900-1100 + 1100-1000
= 9 hours
because it is during two workdays...
is there a way to calculate this in VBA?
View 14 Replies
View Related
Nov 18, 2008
If I have a date in cell G6 of 10/7/08, how could I get the workday of 5 in cell H6? I tried the workday function, but have been unsucessful so far.
View 12 Replies
View Related
Jun 11, 2008
Im trying to display dates in excel sheet using macros. can anybody help me how to show Workday(x,x) in VBA.
View 7 Replies
View Related
May 29, 2009
I am having an issue, because aparently workday formula does not work in conditional formattings.
I have the two formulas below to use in conditional formattings, but I can't figure out how to re-write them so that Excel will allow me.
View 5 Replies
View Related
Nov 27, 2012
I'm using the following to return the previous TUESDAY in my Event Date cell F43
=$F$43-WEEKDAY($F$43+4)
It works great but if my event date is a Wednesday I need to return the Tuesday in the week prior not in the Tuesday immediately prior.
That is, If the event falls on Wed 22 May 2013 the cell needs to return Tuesday 14 May 2013 not Tuesday 21 May.
View 3 Replies
View Related
Dec 1, 2006
I need to be able to open a filenamed in the following format.
c:/workbook20060112.txt.
However the lsat part of the string is dyanmic and works with one business days lag (hence format sheet (date, "yyyymmdd") ) is not approriate. i also have the problem that that MS Excel does not have a holiday calendar (so this would not work over bank holidays/easte/exmas ect). The folder also contains archived files as below.
c:/workbook20060112.txt
c:/workbook20061130.txt
c:/workbook20061129.txt
I have been told about a filesearch object as well as a filesystem object. What situations would you use one over the other?
What I want it the most upto data file to pick up, but I dont want to do a loop where it look through all the files or something that counts down from today until it 'hits' the correct file.
View 9 Replies
View Related
Feb 11, 2007
I am trying to create a sheet for a project that will identify dates a project will conclude omitting weekends and holidays. I keep getting an error with the formula I have.
In my spreadsheet:
A1 is the start date
B1 is the number of days after the start date.
The formula I am using:
=WORKDAY(A1,NETWORKDAYS(A1,A1+B1),{""4/6/2007","5/28/2007", "7/4/2007","9/3/2007","11/22/2007","12/25/2007","1/1/2008","1/21/2008","3/21/2008","5/26/2008", "7/4/2008","9/1/2008","11/27/2008","12/25/2008"}"}+0)
The error I get is with the parens (A1,A1+B1). - at least the parens are highlighted in purple.
View 9 Replies
View Related
Feb 15, 2007
I am trying to find a formula that would calculate what workday a date would be.
So if the date is 2/19/2007, I want to know that is the 13th workday.
View 9 Replies
View Related
Jun 17, 2008
My boss has made it clear I can't require our people to use the add-in.
I have searched under WORKDAY as well as under Barry Houdini, since someone said he has come up with plenty of replacements for the Analysis add-in... but I am not finding it.. can someone help?
Using the add-in, this is what I have:
myCell.FormulaR1C1 = "=WORKDAY(RC[1],-RC[2])"
View 9 Replies
View Related
May 21, 2009
I am trying to work out a formula calculating dates.
basically a piece of work / report is due for completion twenty working days from a trigger date. And I need the formula to calculate this due date. Im using the workday function, which calculates a date using the number of working days given after the trigger date.
this would work fine, except that the trigger date needs to be included in the calculation (inclusive). I have tried changing the value for the number of working days to nineteen, which would logically give the right answer (20 days including the trigger day). BUT the bloody thing doesnt work, because the trigger date can be on a weekend or holiday!! so then it calculates 19 days (as it should) but the result is wrong because the trigger day isnt included (as its a holiday/weekend).
View 9 Replies
View Related
Mar 31, 2007
When I use the formula below it works great;
= J10+(1/$D$10)
J10 = 3-1-07
D10 = 1.5 (Production Rate example .2,.5, 1.5 rate per day) The result is:
3-1-07
3-1-07
3-2-07
3-3-07
3-3-07
3-4-07
3-5-07 and so on...
however, when I try to include only workdays, it does not calculate correctly.
= WORKDAY(J10+(1/$D$10),1,Holidays!B75:B88) with the same definitions as above the result is...
3-1-07
3-2-07
3-3-07
3-4-07
View 9 Replies
View Related
Nov 24, 2008
I'm looking for a function similar to =WORKDAY but with a slight variation.
I want the formula to return the date that is the closest non-weekend, non-holiday day that is a specific number of CALENDAR days from the start date. So the formula does not return weekend or holiday days, but does include them when counting the days away from the start date.
For example if the start date was Dec 1st, and I specified 14 days after this date, I would want Dec 15th returned (as the 14th is a weekend).
View 9 Replies
View Related
Jun 19, 2008
I have a spreadsheet with Received Date/Time in C2 and Resolved Date/Tim in D2, Work Start Time in E2, Work End Time in F2. C2 and D2 are in dd/mm/yyyy hh:mm AM/PM format:04/03/2008 10:27 AM06/03/2008 1:06 PM9:00:00 AM5:00:00 PM
I need to be able to calculate the resolution time of each request in hours/mins excluding weekends and public holidays. I've tried using the NETWORKDAYS function but it doesn't seem to pick up multiple days between the Received and Resolved dates/times. I have put the Public Holidays in my spreadsheet ( attached) in AA2-AG2.
View 4 Replies
View Related
Jun 24, 2011
Is there a formula similar to WORKDAY that would include weekends and make something due on the next business day? For example, I have a bill due on 6/1/11 and I need to follow up 5 days later - which would be normally 6/6/11 but the WORKDAY formula makes it 6/8/11 as it is adding 2 extra days.
I am using Excel 2010.
View 14 Replies
View Related
Sep 20, 2009
I have a list of clients that have specific requests waiting to be actioned, with a number of columns relating to client details and the status of the request across the top of the sheet. One of the columns (D) is "Last Contact Date", where I enter in the date that I last followed up with the client or made contact regarding their request. In the next column (E), I want the weekday/workday date 1 month after the Last Contact Date.
I can use "=D2+DAY(30)" to give me the date 30 days later, or "=DATE(YEAR(D2),MONTH(D2)+1,DAY(D2))" to get one month later, however what I want is the nearest WORKDAY after this date.
So, if the date is on a weekend, I need the Monday date instead.
View 5 Replies
View Related
Apr 8, 2014
I'm having trouble using the worksheet copy command in a VBA subroutine. I have the following line in my code:
[Code] ........
When I step through my code and execute this line, the sheet is copied as expected and put in the correct place, but then instead of the next line of code being highlighted, the pointer jumps to the first line of a function (in a different module) in my code.
View 14 Replies
View Related
Mar 20, 2009
Another interesting dilemma to solve. Using this formula:
View 2 Replies
View Related
May 14, 2013
Function Haversine has correct value in debugger but in cell it has the same value as Haversine2. Is this a known bug?
Public Function Haversine(lat1 As Double, long1 As Double, lat2 As Double, long2 As Double) As Double
Dim temp As Double
[Code]....
View 9 Replies
View Related
Apr 13, 2007
In Mr Excel's Pod Cast on April 12th, he showed how to use the OFFSET function to define a range inside a SUM function. Then he had Conditional Formatting that would highlight the range that was being summed. Can anyone tell me what the formula would be inside the Conditional Formatting dialog box to get the OFFSET range to have a certain format?
View 9 Replies
View Related
Jul 23, 2013
I have a function
VB:
Function f1(Matrix As Range)
'Does something and returns f1 = a double
End Function
And a second function which defines and constructs a matrix of doubles to use as an argument in f1 to return a double:
VB:
Function f2(dD As Double)
Dim MatrixRed() As Double
Redim MatrixRed(1 To dD, 1 To 10)
For i = 1 To dD
For j = 1 To 10
MatrixRed(i, j) = i * j
Next
Next
f2 = f1(MatrixRed)
End Function
I get an output error (#VALUE). I think it has something to do with MatrixRed not being a range anymore?
View 2 Replies
View Related
Dec 3, 2013
let me start by saying that I know an example workbook would be useful here, but the part I'm struggling with is the [managementroster.xlsm] file, and there is A. no way I can release it to the internets and B. its so huge/complicated I couldn't even begin to reproduce a portion of it, scrubbed of data, and hope to maintain its functionality in a meaningful manner.
[Code]....
This formula checks a staff number on this spreadsheet, and then goes and looks at the staff number on the roster. Once found, it returns that staff members roster, but changes any manager codes in the MRC list to Mgr, and changes all other roster codes to Free.
I now need this formula, before altering roster codes to Mgr or Free, to only return codes that are a match for another table (or after really. I don't particularly care, so long as only codes are shown that match data from another table). I think an index/match function would do the trick, but this forumula is already at the edge of my excel ability, nesting another function within it is completey beyond me. The relevant cells for the index/match function would be:
This first Match function targets the column. $E3 is the date required, $BA$1:$DN$1 is the range the dates are entered in
Match: Lookup value = $E3
Lookup array = '[ManagementRoster.xlsm]Vacancies!'$BA$1:$DN$1
match type = 0
This second Match function targets the row. $A$4 is the department name, $B$434:$B$452 is the range where all departments are entered
Match: Lookup value = $A$4
Lookup Array = '[ManagementRoster.xlsm]Vacancies!'$B$434:$B$452
match type = 0
Index: array = $BA$434:$DN$452
So I think my final function is
[Code] .....
But I have absolutely NO idea where it would fit within my first formula, or how to code it so that my original formula only reproduces results that are found in both sheets, or anything.
View 2 Replies
View Related
Jul 17, 2008
I have created a List in excel of various tasks. (See attached example.) Each row contains one cell with a function which equals the cell above it and to the right. So the function for cell C3 would be D2. The only importance is that the cell mirrored is always the cell one above and to the right. However, now I would like to be able to rearrange this List, but the “one up and to the right” function will now be all over the place.
Is someone aware of a function which will target a relative location instead of an exact cell?
View 13 Replies
View Related