Workday Holiday Trigger Date

May 21, 2009

I am trying to work out a formula calculating dates.

basically a piece of work / report is due for completion twenty working days from a trigger date. And I need the formula to calculate this due date. Im using the workday function, which calculates a date using the number of working days given after the trigger date.

this would work fine, except that the trigger date needs to be included in the calculation (inclusive). I have tried changing the value for the number of working days to nineteen, which would logically give the right answer (20 days including the trigger day). BUT the bloody thing doesnt work, because the trigger date can be on a weekend or holiday!! so then it calculates 19 days (as it should) but the result is wrong because the trigger day isnt included (as its a holiday/weekend).

View 9 Replies


ADVERTISEMENT

Weekday/workday Date 1 Month After The Last Contact Date

Sep 20, 2009

I have a list of clients that have specific requests waiting to be actioned, with a number of columns relating to client details and the status of the request across the top of the sheet. One of the columns (D) is "Last Contact Date", where I enter in the date that I last followed up with the client or made contact regarding their request. In the next column (E), I want the weekday/workday date 1 month after the Last Contact Date.

I can use "=D2+DAY(30)" to give me the date 30 days later, or "=DATE(YEAR(D2),MONTH(D2)+1,DAY(D2))" to get one month later, however what I want is the nearest WORKDAY after this date.

So, if the date is on a weekend, I need the Monday date instead.

View 5 Replies View Related

Convert Date To Workday

Nov 18, 2008

If I have a date in cell G6 of 10/7/08, how could I get the workday of 5 in cell H6? I tried the workday function, but have been unsucessful so far.

View 12 Replies View Related

Formula That Would Calculate What Workday A Date Would Be

Feb 15, 2007

I am trying to find a formula that would calculate what workday a date would be.

So if the date is 2/19/2007, I want to know that is the 13th workday.

View 9 Replies View Related

WORKDAY Function To Calculate The Start Date

Jun 11, 2009

As everyone realizes that WORKDAY function can return a working date that exclude weekends and any dates identified as holidays. However, what if I want to return a working date excluding my designated holidays but including weekends?

For example,

Holidays are 1 Jun 2009, 2 Jun 2009 and 4 Jun 2009

Start Date: ???
Finish Date: 8 Jun 2009
Duration: 5 days

The Start Date should be 30 May 2009.

Seems like I am not able to use WORKDAY function to calculate the start date.

View 11 Replies View Related

Flag Employee Holiday Date Clashes

Sep 12, 2007

i am trying to create a spreadsheet that will tell me when employees have booked the same days of with other employees in the same department i have attached the part of my workbook which i am having the problem, i then want to email the clash dates

View 9 Replies View Related

Excel 2010 :: Date Formula That Functions Like WORKDAY But Includes Weekends

Jun 24, 2011

Is there a formula similar to WORKDAY that would include weekends and make something due on the next business day? For example, I have a bill due on 6/1/11 and I need to follow up 5 days later - which would be normally 6/6/11 but the WORKDAY formula makes it 6/8/11 as it is adding 2 extra days.

I am using Excel 2010.

View 14 Replies View Related

Adjust Code From Cell Range Trigger To Button Trigger

Jul 1, 2014

I have the code below that is two separate activities and I want to change the second activity from a cell trigger (Set KeyCells = Range("K42:AD42")) to a button trigger. I need to first to remain unchanged.

I'd be ok if this was just one macro that I could assign to a button but because its two and I need to write the second's to clicking a button I'm over my head.

Its occured to me while writing this that because it'll be a range of buttons I'll probably need to make each one an individual code? Is this the case? If so I may have to just keep this as it is.

View 2 Replies View Related

Can Excel Able To Trigger If Due Date Is Set

May 20, 2013

I am preparing a list of calibration items that require yearly calibrated, how can I set the date and prompt me example 1 month ahead when the item is going to due soon.

View 3 Replies View Related

Creating A Date Range Trigger

Jun 5, 2007

hi i am currently trying to construct a date based maintainance sheet

i will try to explain what im trying to do

in one cell date is inputted
the next cell automatically adds +30 to generate next test date

what i am trying to do is get the sheet to
there are 4 testers so its a 3 month cycle for each ie
tester 1 jan
tester 2 feb
tester 3 march
tester 4 april
tester 1 may
tester 2 june

you get the picture? i hope
so if


cell A1 todays date

a2...................................b2......................................c2

21 jan.............................21 feb................................tester 2


inputed ...................... =A1+30
and date
formated
cell


i am trying to get the formula to tell me after the inputed date has been changed who the next tester is

i have tried using the IF command but it wont let me specify a date range ie 1 jan to 31 jan (or in the specified date codes) date range only one specific date with >= or <= which doesnt quite work properly

View 9 Replies View Related

Excel 2007 :: Count Number Of Days Between Two Date Where Off Days Are Friday / Saturday And Holiday

Mar 14, 2014

I am making process TAT(Turn Around Time) which required following information. In Excel 2007.

1-Count number of days between two dates where working days are (Sun to Thursday). So required to exclude (Friday,Sat + Holidays)

A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 22
D1-Days between two dates 21
E1 To E10-Holidays

2-Count number of days between two dates where working days are (Sat to Thursday). So required to exclude (Friday + Holidays)

A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 27
D1-Days between two dates 26
E1 To E10-Holidays

Note : Any weekend (off days) dates listed in holidays should not effect the query.

View 9 Replies View Related

Holiday Pay

Nov 16, 2008

I need a formula to compute holiday pay. I am having problems when there are two holidays during the month and the hire date of the employee is after the first holiday. For instance in November, November 11 and November 26 are holidays. If the employee is hired before November 11, he gets paid for the two holidays. If he is hired after November 11, he only gets the second holiday.

A B C 1 HOLIDAYS 2 HIRE DATE RATE/ 11-Nov-09 3 HOUR 26-Nov-09 4 5 10/15/2009 60.00 6 11/16/2009 60.00 7 11/28/2009 60.00 8

View 9 Replies View Related

WorkDay Function VBA

Jul 31, 2008

The function is to show the next workday date in cell a1

View 15 Replies View Related

Workday Function Use In VBA

Aug 15, 2006

I have a spreadsheet setup that uses the workday function. Shown as follows: =Workday(P$2-1,V2,Z2:Z$11)

P2 is a set date in which the location will not change. Z:Z is a list of Holidays. V2 should offset by 1 row. I want it when a command button is hit it runs that formula untill the rows value = "End". I have found "Working with Workdays" information at MSDN's website http://msdn.microsoft.com/library/default.asp?url=/library/en-us/dnvbadev/html/workingwithworkdays.asp It seems to be for access but I'm trying to use in Excel and I am getting errors/confused. The main error I'm getting is Compile Error: Method or data member not found because of rst.FindFirst.

View 7 Replies View Related

Holiday Pay Calculation

Jan 17, 2007

I have a problem with a cell displaying the correct number of days.

We work a 38 hour week and therefore each day is 7.6hrs

I have a start date and current date and calculate the number of days employed. I know that each day employed is worth 24 minutes, so over the year it calculates to 20 days per annum.

as I have not entered all the hours taken off yet, my current holiday entitlement is 767:04 (hh:mm).

when I process this on the calculator it tells me I have nearly 101 days holiday due, but I can not get excel to display XX:XX:XX (DD:HH:MM)

What would like to know is how many days that equates to using the 7.6 hour days

View 9 Replies View Related

Conditional Format If Not Workday

May 26, 2009

Maybe I'm getting a blank, maybe the answer is so easy, but lately I canīt solve this: How do I use conditional format to change cell color if cell value (date) is not workday?

View 4 Replies View Related

Calculating If A Period Is During A Workday

Jul 22, 2009

I have two dates in this format:

start: 17.07.2009 11:00:00
end: 17.07.2009 14:00:00

i need to check if the period in between those is during a workday.

our workday starts at 10:00:00 and finishes at 19:00:00

so my expected result is 3 hours. (1400-1100)

other example:

start: 17.07.2009 11:00:00
end: 18.07.2009 11:00:00

result is 1900-1100 + 1100-1000

= 9 hours

because it is during two workdays...

is there a way to calculate this in VBA?

View 14 Replies View Related

Workday Function Or Similar

Jan 3, 2007

This is probably a simple question, but one I can't figure out after several hours. I am creating a spreadsheet focused on certifications.

I need to take the date each initial certification was achieved, and add x years to each cert, which is simple enough.

The sticky part is that the (date + x years) can't logically be a weekend; if it is, I need to subtract one or two days from the result, so that it's the *weekday* immediately prior.

e.g. if my initial certification date is: 1/23/2006 and my certifcation expires in four 4 years:

A47= date(2006,1,23)
h47= 10

=DATE(YEAR(A47)+H47,MONTH(A47),DAY(A47))

Result = Saturday, January 23, 2010

If the result is a Saturday or Sunday, I need to subtract one or two days from the date. In this example, I'd like: Friday, January 22, 2010 as the result.

I've been playing with 'if', et. al., to no avail.

View 9 Replies View Related

Macro For Workday Dates

Jun 11, 2008

Im trying to display dates in excel sheet using macros. can anybody help me how to show Workday(x,x) in VBA.

View 7 Replies View Related

Staff Holiday Analysis?

Dec 17, 2012

My boss wants me to take the holiday info from SAGE for 80 employees and create a record on excel. He wants to know what holidays each employee has taken and is due to take throughout the year. As each employee works a different amount of hours and a different shift pattern, SAGE records their holiday entitlement in hours rather than days. I have attached an example of one employees details and if come up with an excel document containing similar information for 80 individuals - all starting on different dates and all having a different amount of holiday entitlement. He wants to be able to look at each employees record for the year and see not only holiday data but sick days too. I don't know where to start with this - I've thought about creating a workbook with 80 pages and create a 12 month calendar for each individual with days off marked on it?

View 4 Replies View Related

Advanced Holiday Calendar

Nov 4, 2007

At my job, employees accrue X hours vacation per 2 weeks worked. This makes it difficult for everyone to plan vacation (IE - will I have enough vacation in January to go on vacation for 2 weeks?) I'm trying to create a calendar in my spare time to help out, but it's turning out to be quite a bigger task than I've ever attempted in excel. Therefore, I'm coming here hoping someone will point me in the right direction.

I found this:
[url]
It does the majority of what I need. However, as it costs money, I'm afraid they've locked down editing of things and I won't be able to add functionality to it. It'd be annoying paying them and then finding out I can't add vacation days earned, as the spreadsheet is locked.

Features I'd like added to the above program:
- Add another checkbox (or similar) to show hours of vacation accrued, as well as an original date and hours to start counting from.
- Highlight days corresponding to what kind of day it is. Weekends = red, holidays = green, vacation = yellow, etc.

What I started with:
[url]
This gives me a calendar with the dates in the right place. I've created macros to identify holidays dates. It's starting to get pretty annoying using conditional formatting on everything to highlight days. Especially since I have to do it for each of the 12 months, as it has a hard-coded month cell in there.

View 9 Replies View Related

UK Bank Holiday Calculator

May 2, 2006

I found a link to a website on one of the forum pages. I had a look in the website and it showed a formula for calculating when Easter falls - I didn't know it could be worked out, but it can!!

I therefore decided to investigate further. I picked up another formula to calculate the first MOnday in May and I have now put together a little spreadsheet that will calculate all bank holidays in the year entered in cell B1. It also takes into account additional bank holidays that exist when Christmas Day and/or Boxing Day fall on a weekend.

View 3 Replies View Related

Holiday Roster Templates

Aug 19, 2007

where I might find some?

View 3 Replies View Related

Workday Formula On A Conditional Formatting

May 29, 2009

I am having an issue, because aparently workday formula does not work in conditional formattings.
I have the two formulas below to use in conditional formattings, but I can't figure out how to re-write them so that Excel will allow me.

View 5 Replies View Related

Counting Back And Returning Workday

Nov 27, 2012

I'm using the following to return the previous TUESDAY in my Event Date cell F43

=$F$43-WEEKDAY($F$43+4)

It works great but if my event date is a Wednesday I need to return the Tuesday in the week prior not in the Tuesday immediately prior.

That is, If the event falls on Wed 22 May 2013 the cell needs to return Tuesday 14 May 2013 not Tuesday 21 May.

View 3 Replies View Related

Filesearch Object With A Datestamp (workday-1)

Dec 1, 2006

I need to be able to open a filenamed in the following format.

c:/workbook20060112.txt.

However the lsat part of the string is dyanmic and works with one business days lag (hence format sheet (date, "yyyymmdd") ) is not approriate. i also have the problem that that MS Excel does not have a holiday calendar (so this would not work over bank holidays/easte/exmas ect). The folder also contains archived files as below.

c:/workbook20060112.txt
c:/workbook20061130.txt
c:/workbook20061129.txt

I have been told about a filesearch object as well as a filesystem object. What situations would you use one over the other?

What I want it the most upto data file to pick up, but I dont want to do a loop where it look through all the files or something that counts down from today until it 'hits' the correct file.

View 9 Replies View Related

Workday And Network Day Formula Challenge

Feb 11, 2007

I am trying to create a sheet for a project that will identify dates a project will conclude omitting weekends and holidays. I keep getting an error with the formula I have.

In my spreadsheet:
A1 is the start date
B1 is the number of days after the start date.

The formula I am using:
=WORKDAY(A1,NETWORKDAYS(A1,A1+B1),{""4/6/2007","5/28/2007", "7/4/2007","9/3/2007","11/22/2007","12/25/2007","1/1/2008","1/21/2008","3/21/2008","5/26/2008", "7/4/2008","9/1/2008","11/27/2008","12/25/2008"}"}+0)

The error I get is with the parens (A1,A1+B1). - at least the parens are highlighted in purple.

View 9 Replies View Related

WORKDAY Formula Replacement W/o Use Of Analysis Add-In

Jun 17, 2008

My boss has made it clear I can't require our people to use the add-in.

I have searched under WORKDAY as well as under Barry Houdini, since someone said he has come up with plenty of replacements for the Analysis add-in... but I am not finding it.. can someone help?

Using the add-in, this is what I have:

myCell.FormulaR1C1 = "=WORKDAY(RC[1],-RC[2])"

View 9 Replies View Related

Function That Is The Equivalent Of WORKDAY But For Hours Instead

Mar 14, 2007

I am in need of some excel advice relating to date calculations. Basically I need a function that is the equivalent of WORKDAY but for hours instead. I have a series of events that take a certain length of time to complete, most of them less than a day but some more than. By way of example see the screenshot below:

In reality the last three operations would have to take place on the 27th of April, with the Welding operation starting on the end of the 25th around 7pm. The plant is running a 24 hour day, and works 5 days a week. How can I calculate the times in hours offset rather than going day by day? I need to account for

* Weekends
* Fixed Holidays
* Operations running as seamlessly as possible

Any advice welcome. I have attempted to use WORKDAY with the number of days to deduct rounded to the nearest day and then subtracting the operation time but this results in errors where operations would cumulatively go over a working day. The objective is by knowing when the end product is needed and knowing how long each operation takes it is possible to discover when to start manufacture. VBA or Formula code is fine as this will be integrated into a VBA project.

View 6 Replies View Related

Workday - Adding Partial Days

Mar 31, 2007

When I use the formula below it works great;

= J10+(1/$D$10)

J10 = 3-1-07
D10 = 1.5 (Production Rate example .2,.5, 1.5 rate per day) The result is:

3-1-07
3-1-07
3-2-07
3-3-07
3-3-07
3-4-07
3-5-07 and so on...

however, when I try to include only workdays, it does not calculate correctly.

= WORKDAY(J10+(1/$D$10),1,Holidays!B75:B88) with the same definitions as above the result is...

3-1-07
3-2-07
3-3-07
3-4-07