Calculating The Radius Of A Curve
Feb 19, 2009I am trying to find a formula to calculate the total size from a to b with the curve being in cluded in the total.
View 14 RepliesI am trying to find a formula to calculate the total size from a to b with the curve being in cluded in the total.
View 14 RepliesI have a data set (Set#1) that consists of a positional rank (1-240) and a dollar value ($46-$1) for each positional rank. It's not a straight line set.
DataSet.JPG
What I need to do is take that curve and apply it to another data set (Set#2) (1-240) and assign a dollar value ($46-$1) to each positional rank.
A "corner cutting" way of doing it would be an Index/Match to simply carry over the dollar value from (for example) #45 from my Set#1 to #45 in my Set#2. This could work reasonably well with data sets of the same size, but mine aren't always the same size, so I need to apply the curve itself. I
I have used ROW function to determine the facets lengths and the number of internal angles and also the radius's
the offset figure is the distance the track or pole is set from the frame this can be adjustable by us or the end user
the radius measurement is a minimum and a maximum that the aluminium can be bent, will probably
be set parametrs to work with
Now bay widows come in all sorts of shapes and sizes
90 degree angle bays
2 bend bays
3 bend bays this is why I am using the row function, once the measurments are entered can excel generate
I have more than 1000000 coordinates with heights to sort through. The aim is to be able to give a specific radius and check all coordinates within this radius if the slope is more than a maximum slope. If this is the case it need to put the value (in this case) 100 in a new column. The reason for this is we have a reasonable flat terrain but the entire area is filled with Anthills. I need to sort the data. Normal ground points (No Anthills) should be labelled/coded as 200 and anthills as 100. This will allow my program to know the difference between the ground and anthills. In the tab "Input Sheet" I have a small portion of co-ordinates starting from row 8 to row 53 (this will have to extend all the way down to the last row in excel). I need to copy each row starting with row 8 (C8:E8) and paste it in row 2 (C2:E2). Column H indicates if the points are forming an anthill and the code needs to change. I have my final answer in the tab "Final Answer" that I require for my program. Is there any way I can write a VBA code that will check all the point instead of doing it manually.
View 4 Replies View RelatedI have a few dates and one Total value. I need to distribute this Total Value in such a way so I can get the same shape S curve (Date vs Value).
View 4 Replies View RelatedI'm trying Calculate Curved Price Rate by SF. phil.freestyle@gmail.com
View 5 Replies View RelatedFor Excel 2007 -
I am looking for a function [or method] to calculate a polynomial curve fit. I can do it on a graph with the existing graph and chart tools, but I need to calculate it myself. Does such software exist somewhere in my Excel 2007 package, or can anyone recommend a freeware program? I am hesitant to download an unknown, un-recommended add-in.
i am getting some data via RS 232 port and plotting it straight to excel, which comes out to be in forms of waves you can say sine waves, now i need to calculate area under the curve, say like if i highlight some area it will automatically calculate the area, or if i select two points on the curve it will calculate the area. please help me out i am really stuck at this part.
View 9 Replies View RelatedI'd like to apply a curve to a column of student exam grades and have the curved grades displayed in the adjacent column. Here is how I'd like to curve:
I like to make a linear function out of two coordinate pairs.
First Pair (x1,y1) = (Highest Exam Grade, 99) = (H,99)
Second Pair (x2,y2) = (Class Exam Average, Desired Exam Average) =(C,D)
Slope = (99-D)/(H-C) = m
Linear Function = Y-y = m(X-x) = Y-99=m(X-H)
Each student grade would = "Y" i.e. Y=m(X-H)+99
How I can find a max in an xy chart curve fit?
View 9 Replies View RelatedDoes anyone know of a statistical formula that would create a normal growth curve?
For example. Let's assume that I want to forcast growth from January through December. I know that in January I will have 100 units. In December, I will have 1,000 units. Is there a formula to predict the the units in Feb-Nov (using a normal growth curve)?
I am trying to calculate the equation of a curve which best fits some data. On the x-axis is date and y-axis the readings. The curve is quadratic, so on the chart I am fitting a 2nd order polyomial and displaying the equation. To prove that the equation the trendline gives me is reasonable, I am applying the equation on the x parameter to get the y parameter estimate and looking to see the error between predicted and actual - see attached.
The equation and the output from it are clearly rubbish, even though on the graph the trendline is a reasonable fit - see attached. Has anyone any ideas why? I think it has something to do with using a date on the x-axis but no idea why. Is there a way to correct for this? I also tried using the following I to calculate the coefficients which came up with a reasonable forecast (although linest should only be used for linear data): =LINEST(C3:C15,B3:B15^{1,2,3})
I am working on Project Planning, I need to create the Progress curve for our Project based on Weight Factor every month.
I need to create the Plan and actual curve based on the dates defined in particular activities. Once the activity progress is calculated every month based on cut off date then it will sum product with corresponding WF to get the progress achieved every month. Presently I am calculating the values every month and pasting the values in Chart data every month. I had created the S Curve and attached here.
Now my objective is to automatically calculate the values for the entire cut off date at one time (From Project Start to End). i.e I don't want to do any manual work in the Chart. I will update only the actual Dates in the file, then the curves need to get automatically updated.
1) I don't want to calculate the progress for individual activities, I would like to calculate the overall progress directly.
2) When I change the Cut off date, then the previous values needs to become static.
I'm trying to find a formula that would spread out a value amongst multiple cells along a bell curve. Say I have $x,xxx. I want to spread that amount out in a certain proportion, regardless of how many cells I'm spreading it throughout.
Say I have a $10,000 project. I want to be able to spread it out like a bell curve in the cells I choose. For instance, if it was a five month project it would be distributed as
January - $1,000
February - $2,500
March - $3,000
April - $2,500
May - $1,000
If I added another month it would change to
January - $833.33
February - $1,666.66
March - $2,500.00
April - $2,500.00
May - $1,666.66
June - $833.33
I already thought of manually adding percentages to each cell, but the formula needs to be dynamic.
Can we draw tangent to a curve in excel graphs..? If yes if i could have some demo....** this.. I am working on finding rate ** change at an instantaneous point and average rate ** change ie: secant line
View 1 Replies View RelatedI need to solve about 450 excel sheets for my project.
The spreadsheet has X and Y data and curve is plotted. I need to split the curves into 3 parts based on slope change.
I can do it manually but I need an excel Macro which does this work.
A sample is attached : Excel forum-Lab data.xlsx
Is it possible in excel to find the equation for a curve?
I have 6 known x,y data points on a curve. I need to find the equation for the curve.
I would like to use excel to plot a growth curve. I would like it to plot the points that correlate to my data without connecting them by a line. I would then like to give excel a formula and have it plot that line on the graph.
View 9 Replies View RelatedI'm trying to graph a bell curve chart using the following data
Hotels per state
Total
AK
4
NH
5
[Code] ......
As you can see I have states and the number of hotels per state what I need not for statistical purposes but more for "pretyness" is to sort this data in a way that what you get is a somewhat of a bell shape curve graph.
I want to create a bell curve for my team's annual appraisal. There are 12 people in my team. The scale is 1-5, where normally rating range from 2.9 to 4.0.
View 1 Replies View RelatedI've managed to figure out how to normalize my data and create several bell curves. However, these charts do not display the mean, std deviation, or confidence intervals. Any way to add these into my charts?
View 7 Replies View RelatedWhat would be the best way to put together a cancel curve on an annual membership model?
View 5 Replies View RelatedI would like to create a histogram from experimental data with the normal distribution curve overlaying the histogram.
View 7 Replies View RelatedIs there a way to generate a normal curve from just the statistical values (mean, std dev, etc)? I used the NORMDIST function but have to manually do the x values and it generates what I would descirbe as a "sample" curve. I would like to make one based on user input.
View 5 Replies View RelatedI'm trying to overlay a Gaussian distribution on some data. The data is a frequency of particle size diameters, ranging from 200-1000 um (see attached). I'm using Excel 2013.
View 1 Replies View RelatedHere's the spreadsheet I am talking about : [URL]
So as you can see each row = one day divided in 2 cycles of 12 hours : every 12 hours the cat gets a new injection of insulin (the columns "U" being the number of units of insulin the cat receives)
Now I want to turn this sheet into two different curves that would look like these : [URL]
As you can see the first graph shows data based on days (x) and insulin dose (y), while the second curves shows data based on days (x), and blood glucose values (y). This is basically the only way we could clearly see how the cat's disease is evolving over a long period of time.
If he had just started to take all these values from his cat I guess it would be simple to do, but since he already has a lot of data entered in his spreadsheet, I was wondering if I could use this data (and not write each number in a new document), to make things a little more simple and to avoid mistakes.
I have put my values into a XY scatter graph but need to find the maximum point i.e when the gradient is zero. I am using visual basic to obtain my data and draw my graph.
View 7 Replies View Relatedim running a new bar in Leeds and im trying to create a spreadsheet which will tell me how much to charge per drink to gain a 80% GP on products, ive got as far as listing the products and prices and calculating how much every measure (25ml) will cost. In the past ive used formulas where I can input the price i charge and it will calculate the GP (=SUM(D10/E10)*100-100) for example but id like to be able to type in the GP I want and for it to tell me the price i need, im not sure if tis possible but it will be a massive time saver.
View 9 Replies View RelatedI have some activities that needs to be done ina specified time
Like for example
TAT HRShrsACT 14ACT 28ACT 324ACT 42ACT 54
And i have a sheet where in i need to calculate turn around time
ActivityStart timeEnd timeTATACT 1ACT 2ACT 3ACT 4ACT 5
Based on time entered in start time and end time the TAT column should calculate the TAT based on the above standards.
I also would liuke to exclude weekends(Saturday, sunday). Also the TAT should only be calculated during working hrs between 7:30 PM to 4:30 AM.
I'm trying to make a worksheet where I can calculate the cost of a mobile postpaid subscription. It is charged per minute and the cost differs depending on which of the 2 available networks the customer is calling to. The first 20 minutes are free, not depending on network.
Edit:
Charges to network A is 1,79,- per minute after the first 20 minutes are spent.
Charges to network B is 2,29,- per minute after the first 20 minutes are spent.
To sum up:
1. The customer makes a call.
2. If there there are available free minutes, these should be spent first.
3. The customer is charged per minute, depending on network called.