Display Mean And Confidence Intervals On Bell Curve

Nov 26, 2013

I've managed to figure out how to normalize my data and create several bell curves. However, these charts do not display the mean, std deviation, or confidence intervals. Any way to add these into my charts?

View 7 Replies


ADVERTISEMENT

Formula To Distribute A Value Along A Bell Curve.

Nov 19, 2008

I'm trying to find a formula that would spread out a value amongst multiple cells along a bell curve. Say I have $x,xxx. I want to spread that amount out in a certain proportion, regardless of how many cells I'm spreading it throughout.

Say I have a $10,000 project. I want to be able to spread it out like a bell curve in the cells I choose. For instance, if it was a five month project it would be distributed as

January - $1,000
February - $2,500
March - $3,000
April - $2,500
May - $1,000

If I added another month it would change to
January - $833.33
February - $1,666.66
March - $2,500.00
April - $2,500.00
May - $1,666.66
June - $833.33

I already thought of manually adding percentages to each cell, but the formula needs to be dynamic.

View 5 Replies View Related

Graph Bell Curve Chart

Jul 14, 2014

I'm trying to graph a bell curve chart using the following data

Hotels per state
Total

AK
4

NH
5

[Code] ......

As you can see I have states and the number of hotels per state what I need not for statistical purposes but more for "pretyness" is to sort this data in a way that what you get is a somewhat of a bell shape curve graph.

View 2 Replies View Related

Excel 2010 :: Creating Bell Curve?

Jul 29, 2014

I want to create a bell curve for my team's annual appraisal. There are 12 people in my team. The scale is 1-5, where normally rating range from 2.9 to 4.0.

View 1 Replies View Related

Solver: Confidence Intervals

May 7, 2009

Does Solver provide confidence intervals around its parameter estimates?

View 9 Replies View Related

Derive Curve From Values Then Apply Curve To Another Dataset?

Jun 5, 2014

I have a data set (Set#1) that consists of a positional rank (1-240) and a dollar value ($46-$1) for each positional rank. It's not a straight line set.

DataSet.JPG

What I need to do is take that curve and apply it to another data set (Set#2) (1-240) and assign a dollar value ($46-$1) to each positional rank.

A "corner cutting" way of doing it would be an Index/Match to simply carry over the dollar value from (for example) #45 from my Set#1 to #45 in my Set#2. This could work reasonably well with data sets of the same size, but mine aren't always the same size, so I need to apply the curve itself. I

View 1 Replies View Related

Confidence Interval Calculation For Weibull Distribution

May 9, 2003

Confidence level calculation.

Background Info: I am doing a weibull analysis on failure data. Some of the data is right censored. I have already run a maximum likelihood estimate to obtain the estimated weibull parameters with Excel's SOLVER function. I am good on this part.

Now I want to calculate these parameters with a 95% confidence interval. I can't seem to find information on calculating confidence intervals with right censored data.

View 4 Replies View Related

Formula For S Shape Curve?

Dec 13, 2013

I have a few dates and one Total value. I need to distribute this Total Value in such a way so I can get the same shape S curve (Date vs Value).

View 4 Replies View Related

Calculating The Radius Of A Curve

Feb 19, 2009

I am trying to find a formula to calculate the total size from a to b with the curve being in cluded in the total.

View 14 Replies View Related

Price Curve Formula

Apr 9, 2009

I'm trying Calculate Curved Price Rate by SF. phil.freestyle@gmail.com

View 5 Replies View Related

How Do I Calculate A Polynomial Curve Fit

Sep 7, 2009

For Excel 2007 -

I am looking for a function [or method] to calculate a polynomial curve fit. I can do it on a graph with the existing graph and chart tools, but I need to calculate it myself. Does such software exist somewhere in my Excel 2007 package, or can anyone recommend a freeware program? I am hesitant to download an unknown, un-recommended add-in.

View 14 Replies View Related

Calculate Area Under The Curve

Apr 13, 2008

i am getting some data via RS 232 port and plotting it straight to excel, which comes out to be in forms of waves you can say sine waves, now i need to calculate area under the curve, say like if i highlight some area it will automatically calculate the area, or if i select two points on the curve it will calculate the area. please help me out i am really stuck at this part.

View 9 Replies View Related

Apply A Curve To A Column

Jan 28, 2009

I'd like to apply a curve to a column of student exam grades and have the curved grades displayed in the adjacent column. Here is how I'd like to curve:

I like to make a linear function out of two coordinate pairs.

First Pair (x1,y1) = (Highest Exam Grade, 99) = (H,99)

Second Pair (x2,y2) = (Class Exam Average, Desired Exam Average) =(C,D)

Slope = (99-D)/(H-C) = m

Linear Function = Y-y = m(X-x) = Y-99=m(X-H)

Each student grade would = "Y" i.e. Y=m(X-H)+99

View 9 Replies View Related

Find Max In Xy Chart Curve Fit

Apr 13, 2006

How I can find a max in an xy chart curve fit?

View 9 Replies View Related

Create Growth Curve

Aug 28, 2007

Does anyone know of a statistical formula that would create a normal growth curve?

For example. Let's assume that I want to forcast growth from January through December. I know that in January I will have 100 units. In December, I will have 1,000 units. Is there a formula to predict the the units in Feb-Nov (using a normal growth curve)?

View 3 Replies View Related

Calculate Best Fit Equation Of Curve

May 16, 2008

I am trying to calculate the equation of a curve which best fits some data. On the x-axis is date and y-axis the readings. The curve is quadratic, so on the chart I am fitting a 2nd order polyomial and displaying the equation. To prove that the equation the trendline gives me is reasonable, I am applying the equation on the x parameter to get the y parameter estimate and looking to see the error between predicted and actual - see attached.

The equation and the output from it are clearly rubbish, even though on the graph the trendline is a reasonable fit - see attached. Has anyone any ideas why? I think it has something to do with using a date on the x-axis but no idea why. Is there a way to correct for this? I also tried using the following I to calculate the coefficients which came up with a reasonable forecast (although linest should only be used for linear data): =LINEST(C3:C15,B3:B15^{1,2,3})

View 2 Replies View Related

Create S Curve Based On Dates

Apr 4, 2014

I am working on Project Planning, I need to create the Progress curve for our Project based on Weight Factor every month.

I need to create the Plan and actual curve based on the dates defined in particular activities. Once the activity progress is calculated every month based on cut off date then it will sum product with corresponding WF to get the progress achieved every month. Presently I am calculating the values every month and pasting the values in Chart data every month. I had created the S Curve and attached here.

Now my objective is to automatically calculate the values for the entire cut off date at one time (From Project Start to End). i.e I don't want to do any manual work in the Chart. I will update only the actual Dates in the file, then the curves need to get automatically updated.

1) I don't want to calculate the progress for individual activities, I would like to calculate the overall progress directly.

2) When I change the Cut off date, then the previous values needs to become static.

View 1 Replies View Related

Drawing Tangent Line On Curve?

Mar 8, 2014

Can we draw tangent to a curve in excel graphs..? If yes if i could have some demo....** this.. I am working on finding rate ** change at an instantaneous point and average rate ** change ie: secant line

View 1 Replies View Related

Excel Split A Curve And Fit Trendline Using VBA

Feb 2, 2014

I need to solve about 450 excel sheets for my project.

The spreadsheet has X and Y data and curve is plotted. I need to split the curves into 3 parts based on slope change.

I can do it manually but I need an excel Macro which does this work.

A sample is attached : Excel forum-Lab data.xlsx‎

View 14 Replies View Related

Given Points On Curve, Solve For Equation

Feb 25, 2009

Is it possible in excel to find the equation for a curve?

I have 6 known x,y data points on a curve. I need to find the equation for the curve.

View 4 Replies View Related

Use Excel To Plot Growth Curve?

Mar 15, 2012

I would like to use excel to plot a growth curve. I would like it to plot the points that correlate to my data without connecting them by a line. I would then like to give excel a formula and have it plot that line on the graph.

View 9 Replies View Related

Put Together A Cancel Curve On An Annual Membership Model

Nov 15, 2009

What would be the best way to put together a cancel curve on an annual membership model?

View 5 Replies View Related

Histogram Plot With Normal Curve Overlay

Aug 28, 2002

I would like to create a histogram from experimental data with the normal distribution curve overlaying the histogram.

View 7 Replies View Related

Generating Normal Curve From Statistical Values?

May 14, 2013

Is there a way to generate a normal curve from just the statistical values (mean, std dev, etc)? I used the NORMDIST function but have to manually do the x values and it generates what I would descirbe as a "sample" curve. I would like to make one based on user input.

View 5 Replies View Related

Excel 2013 :: Plotting Gaussian Curve Over Bar Chart

Apr 14, 2014

I'm trying to overlay a Gaussian distribution on some data. The data is a frequency of particle size diameters, ranging from 200-1000 um (see attached). I'm using Excel 2013.

View 1 Replies View Related

Creating Curve With Multiple Values Already In Excel Spreadsheet?

Jul 11, 2013

Here's the spreadsheet I am talking about : [URL]

So as you can see each row = one day divided in 2 cycles of 12 hours : every 12 hours the cat gets a new injection of insulin (the columns "U" being the number of units of insulin the cat receives)

Now I want to turn this sheet into two different curves that would look like these : [URL]

As you can see the first graph shows data based on days (x) and insulin dose (y), while the second curves shows data based on days (x), and blood glucose values (y). This is basically the only way we could clearly see how the cat's disease is evolving over a long period of time.

If he had just started to take all these values from his cat I guess it would be simple to do, but since he already has a lot of data entered in his spreadsheet, I was wondering if I could use this data (and not write each number in a new document), to make things a little more simple and to avoid mistakes.

View 9 Replies View Related

Calculate Maximum Point On Curve From Xy Scatter Graph

Jan 18, 2008

I have put my values into a XY scatter graph but need to find the maximum point i.e when the gradient is zero. I am using visual basic to obtain my data and draw my graph.

View 7 Replies View Related

Transpose One Row With Intervals

Mar 21, 2009

I am trying to write a macro for transposing one row into multiple columns where the starting point for each column will be 15 cells starting from B4. I want to replicate the transpose for 200 rows.

View 4 Replies View Related

Change The Intervals

Jul 9, 2008

How do i change my data file from 1' intervals to 5' intervals?

The way it is now The way I need it
8300 8300
8301 8305
8302 8310
8303
8304
8305
8306
8307
8308
8309
8310
thru 11,000

View 13 Replies View Related

Getting Date At Specified Intervals?

Feb 12, 2013

My sheet consists of the following Data in the table ( to be increased to 99 rows or events )

I need to find the Next Date Occurence till the End_date

Next_Date1 = Start_date + Interval
Next_Date2 = Next_date1 + Interval

and so on till Next_Datexx is greater than End_date

I need a VBA code to fill the adjacent columns ie Next_date1 to Next_Date99 ( till the end_date), only if the Status is "DONE". If the Status is blank then the relevant colums must not fill.

I can do it with formulas, but need the VBA code.

Also the number of rows can be increased to 99 rows

Event
Start_date
End_date
Interval

[Code].....

View 2 Replies View Related







Copyrights 2005-15 www.BigResource.com, All rights reserved