Calculation Time Not Scale With Worksheet Size

Feb 14, 2013

I have a rather large spreadsheet that takes a long time to calculate. One sheet has the data (about 2800 rows by 650 columns), with samples in rows and data for each sample in the columns. A second sheet has functions to group the data according to predefined patterns. That second spreadsheet is about 800 columns wide and as many rows as I need it to be, as the samples don't need to be analyzed all at once.

Ideally I would like to do all samples at once by making the second spreadsheet 2800 rows high, but the calculation time is just way too long. And there's the problem. The calculation time seems to increase exponentially with the number of rows I calculate at a time. I ran a few tests making it different sizes, and here are the results:

rows
time(seconds)

100
3.5
150
12
200
23

[Code]...

I tried both HLOOKUP and INDEX/MATCH functions and it didn't make a lot of difference. These numbers are for INDEX/MATCH.

Graphing these numbers show that it follows an exponential curve pretty closely. What is interesting is that the progress indicator at the bottom of the screen finishes in a few seconds, about 5 seconds for 350 rows, and I can see the new data after those few seconds. But then it sits and appears to do nothing for the rest of the time. So, for 350 rows, it looks to be done with the calculations within 5 seconds, but then it freezes for another 2 minutes with CPU usage maxed out before I can do anything with the program. That actual calculation time seems to scale linearly with the number of rows I calculate, but the time after it finishes calculating before it finishes whatever else it's doing scales exponentially.

The spreadsheet does have a macro and a couple of other sheets and a macro that do some later analysis and I wondered if that had something to do with it. To check that, I created a new spreadsheet and set it up the same as the original one, with the data in one spreadsheet and the INDEX/MATCH formulas in the other. I copied the data over, but setup the formulas new without copying/pasting anything. It didn't make any real difference.

View 2 Replies


ADVERTISEMENT

Convert Time On Scale Of 100 To Scale Of 60?

Feb 1, 2013

How can we convert time on a scale of 100 to a scale of 60?

View 3 Replies View Related

% Calculation With Values Depending On Size..

Jan 12, 2010

There is a data range in the E + G columns. The content of the E column can be 5 different items with variable GROSS weights in the G column:

.........E..........G..........R...........S...........T
1.....Size.....Gross....%.........Net......Size
2.....200 g....138......56.52...20........45 g
3.....100 g.....84....................35......100 g
4......45 g......52....................60......200 g
5.....500 g....253...................124.....500 g
6.....Strip......15.......................7........Strip
7.....100 g.....90
8.....500 g....280
9......45 g......62
10........................

View 2 Replies View Related

Retrieving Variable Rows From Another Worksheet: Reducing "Calculation Time"

Aug 10, 2009

I'm using this formula to pick all rows from a huge range of cells "DATA" in another sheet, by matching the first column value (SAPDATA is the range that contains all the first column cells of DATA).

{=IF(ROW($B49)-ROW($B$48)>COUNTIF(SAPDATA,$D$4),"",INDEX(DATA,SMALL(IF(SAPDATA=$D$4,ROW(SAPDATA)),ROW($B49)-ROW($B$48)),2))}

All possible first column values have been stored as a dropdown in cell D4, and whenever I change the choice in the dropdown cell, the retrieval of those hundreds of rows takes ages in excel.

View 9 Replies View Related

Counting Number Of Days Over A Time Scale - Graph

Oct 6, 2012

I have got a project that has several hundred starts and finishes. I want to count them over time to use as an indication of progress. ( I want to show this graphically)

I have got the graph working but it is pretty long handed.

I have tried using a pviot table and picvot graph which almost does it but has a few problems (if there is no data in a month then it wont create an entry for the month, and the cumulative over time is not quite working).

Both examples are in the attached file : Progress Curve ozgrid1.xlsx

View 6 Replies View Related

Excel 2007 :: Inconsistent Time Scale - X Axis

Mar 8, 2012

Basically I have some performance figures for a fund that I want to make a chart for, the problem is that the first date (the start date of the fund) is 15/09/2011 but every reporting date after that is the end of the month.

So my data looks something like this (not real figures)

15/09/11 20
30/09/11 22
31/10/11 23
30/11/11 25
31/12/11 26
31/01/12 27.5
29/02/12 29

So what I want is a graph where the x axis starts at 15/09/11 but then the next label is 30/09/11 and 31/10/11 etc, while still keeping the scale proportionate to the dates, ie the distance between 15/09/11 and 30/09/11 will be half the distance between 30/09/11 and 31/10/11.

The 2 outcomes I seem to be stuck with is either forcing the graph to start at 31/08/11 and making the y axis cross at 15/09/11, however with this the x axis goes left past the y axis cross point and it just looks dumb, although everything right of the y axis is correct.

Or secondly I get the graph to start at 15/09/11 and set it to label every 1 month and all the labels are 15/09/11, 15/10/11, 15/11/11 etc

I have access to excel 2003 or 2007.

View 4 Replies View Related

Add Vertical Line To 2 Graphs With Scale X Axis At Same Time

Sep 16, 2012

Two graphs with different scale x-axis.

Graph No. 1 with smaller time frame, Daily.
Graph No. 2 with larger time frame, Weekly.
Objective: Add vertical line to mark the same times in both graphs.

Trouble is both graph already utilise the secondary axis. VBA is allowed.

View 6 Replies View Related

Scale Height & Widths Of All Textboxes On A Worksheet

Sep 6, 2007

I have numerous Text Boxes on my worksheet. The number of these objects vary, as many will be continually duplicated/ deleted.

The code below is a simple recording of selecting each object and scaling.

VB: AutoLinked keywords will cause extra spaces before keywords. Extra spacing is NOT transferred when copy/pasting, but IS if the keyword uses "quotes" ...

View 9 Replies View Related

Time Calculation (Spanning Dates And Using Military Time)

Jul 15, 2014

I have 4 distinct columns.

Adm Date Adm Time Trans Date Trans Time
1/16/2014 937 1/16/2014 1045
1/1/2014 121 1/1/2014 121
1/14/2014 800 1/11/2014 735
1/30/2014 100 1/30/2014 205
1/13/2014 800 1/12/2014 1202

I would like to calculate the difference (# hours spanned from the dates shown). Unfortunately when we transfer the data the COLON is dropped from MILITARY TIME so I am having problems in the calculation. This is also made more difficult as some of the calculates span over two dates.

View 5 Replies View Related

Calculation Of Time With Two Different Time Formats

Jan 30, 2007

Need a point in the right direction with this one! I want to calculate the difference between two time values, the problem is there two different formats as below:-

1) 520.00 - this is a number format

2) 500:00:00 - this is a time format HHH MM SS

What could I use to show I have a 20.00 hour difference???

View 2 Replies View Related

Changing Marker Size In Charts For All Series At The Same Time?

Apr 24, 2014

I have a chart with 5 different series. Instead of editing each one, say the marker size, is there anyway I can change the marker size for all of the different series at the same time?

View 1 Replies View Related

Listbox Automatically Reduces In Size Each Time I Open It

Jul 15, 2006

I have a problem with one of my files. Each time I open it up, the listboxes keep getting smaller and smaller. I have no idea what is causing it.

View 9 Replies View Related

Hh:mm:ss Time Calculation

Nov 5, 2008

i need to total a range of cells, however, these contain time values; hh:mm:ss. it shows me the total when all cells are highlighted. but =sum() doesn't work.

View 2 Replies View Related

Calculation On Time

Mar 1, 2009

I have been burning brain cells trying to figure this out.
I get these numbers from an online source and they come in like this:

A B C D E
1/1/0912:01AM02:40AM11:18AM07:55PM

The times do not come in as times...when I format the cell to time it doesnt change...that is my first problem.

What I would need to do to these times is: take B and C and find what time is in the middle of them and put that in a different column.

This mess will also need to be plotted on a chart with time by the minute for one day as the X axis. In my example I drew lines on the chart to show what I mean....the blue lines I dont want charted...I use those to find the time in the middle.

View 12 Replies View Related

Same Time Calculation

Feb 5, 2009

I am trying to get a total column that will give the total only when two particular devices are down at the same time. This total will be taken from a long list of downtime entries for different devices but I only want the total when two particular devices are down, for example

Devicedatedowntimedateuptimetotal time
102/01/0911:00:0002/01/0911:09:0000:09:00
202/01/0911:00:0002/01/0911:04:0000:04:00
202/01/0902/01/09
103/01/0903/01/09
303/01/0903/01/09
604/01/0904/01/09
204/01/0913:09:0004/01/0913:12:0000:03:00
104/01/0913:02:0004/01/0913:15:0000:13:00
505/02/0905/02/09
total 1/200:07:00

In the example I am just wanting to work out the total time when both device 1 and 2 were down at the same time, above the total would be 7 minutes because for 4 minutes on the 2/1/9 and 3 minutes on the 4/1/9 they were down at the same time.

View 9 Replies View Related

Time Calculation ...

Jun 4, 2009

Having been looking round this site for quite some time now and always finding what I needed I am now a registered member who needs your expertise.

I have a spreadsheet for which I need to calculate hours worked depending on a few criteria.

[data] ...

The criteria is that Sat/Eve is 8pm to 6am weekdays and midnight to midnight on a saturday. Sun is midnight to midnight on a sunday, BH is a bank holiday and basic is everthing else. What I want to know is it these columns can be populated automatically using formulas.

I would really appreciate it if someone out there is up to completing this challange, as I have to manually populate this at the moment and it can be 5000+ lines long (it takes hours). If i need to change the layout it's not a problem, whatever it takes to automate it has got to be worth the effort.

View 9 Replies View Related

Time Calculation

Apr 21, 2007

I have a time card sheet that I want to make automatically calculate the time I have worked. It is set up with four columns that can't be changed. The first column is "Time In(TI)", second column "Time Out(TO)", Third column "Time Taken For Lunch(TTFL)", and Finally "Hours Worked". I have no problem getting the formula to calculate the difference in "Time In" and "Time Out" but taking the 30 minutes out of that is causing a rift. If I put the 30 minutes in 00:30:00 format it will take it but it thinks it's 12:30:00 and it displays in 00:30:00 which I want it to display 30. Just to clarify, I am using =(TI-TO)-TTFL in the Hours Worked cell.

View 3 Replies View Related

Worksheet Size Reduction

Jan 13, 2014

I had a data sheet that used about 20,000 rows, down to AF20000 or so. I deleted about 16,000 rows and now want to reduce the size of the worksheet so that when I hit Control+Shift+End, it takes me only to AF4000, not to AF20000. Can this be done without replicating into a new worksheet?

View 4 Replies View Related

Worksheet Display Size

Oct 4, 2007

some spreadsheets i open dont have 65536 rows , they only a 100 or 200 its seems the worksheets have been cut down. how can i do this based on the last row in the e coloum.

Ie last entry in the e coloumn is 500 the worksheet to only be that big

View 11 Replies View Related

Cutting Down Worksheet Size?

Mar 24, 2013

I have seen a worksheet/workbook in the past that only contains (for example) Columns A:H and Rows 1:150. The rest of the columns and rows do not show. Unfortunately I cannot find the example I was looking at and I cannot find any information on how to achieve it.

View 3 Replies View Related

Create UserForm TextBox At Run-Time & Auto Size To Fit Text

Dec 11, 2008

I have a user form on which I need to create a textbox every time the user clicks a button. There are too many to create them all in advance and make them visible when needed. The sample attached, from this forum, is good, except, the numbers in the text box just scroll along and I need to see all the text typed into my textboxes. I would like the textboxes to be multiline, wordwrap and have them resize according to the amount of text.

View 6 Replies View Related

How Do I Reduce Calculation Time

Sep 12, 2008

I am a big fan of huge files (30MB+) all interlinked with array formulas ...and lots of them. The problem is...one calculation take literally 5 hours. (I have one file I try to calculate since cca 4 hours now...it's at 63%)

I keep getting extra memory with no visible improvement on the processing time. Is there a trick out there that I can use? Something is clearly wrong.

I feel I will soon have to give up Excel, or my formulas, or my job ...

View 14 Replies View Related

Formatting With Time Calculation

Oct 15, 2009

I have a calculation whereby I use two variables which are 1. Man hours left in the week formatted as [hh] and 2. Amount of work left to do in the week formatted as 0" Man Hrs" I need to carry out a calc which says:- Man hours left in the week - Amount of work left to do in the week.

The answer should tell me if I have a deficit or surplus of hours which can then use for planning purposes. Unfortunately the problem I have is that I can't make the formatting the same for both unless someone knows of a workaround.

Man hours left in the week = 128. Man hours required to complete all work this week = 224. Therefore I need to say 128-224 = -96. However when I do this this an answer of 16 is returned.

View 5 Replies View Related

Time Calculation Between Two Cells?

Feb 14, 2014

I have attached excel sheet. Column A consists of List of LAN numbers, Column B consists of List of Documents tagged & Column C consists of time at which particular document is tagged.

I need to calculate the time taken to tag all the documents in Lan1/Lan2/Lan3 in Column D. (I can ignore the date by doing text to columns).

View 3 Replies View Related

Variable Time Calculation

Dec 12, 2007

[code] ......

=SUMIF($A:$A,">="&TODAY()-1,D:D)-SUMIF($A:$A,">"&TODAY(),D:D) calculates the total in Col D looking back from today. The results gives you 12:00. What I need is a formula that will look back from the current time to 24 hours in the past, NOT 1 day, to calculate the total in Col D. Looking back 24 hours, from 10:00am, the results would be 6:00.

Since the first time on 12/12 has not arrive, it will not calculate it, but will look back from 10:00am on 12/12 to 10:00am on 12/11 and calculate a result of 6:00 hours.

View 9 Replies View Related

Time Conversion/calculation

Mar 11, 2008

I need a formula that will calc the following: using Excel XP

#MIN.
INLUNCHOUTHRS
8:00 AM04:00 PM 8.00
8:00 AM304:30 PM 8.00
8:00 AM304:30 PM 8.00
8:00 AM304:00 PM 7.50
8:00 AM605:00 PM 8.00

View 9 Replies View Related

Calculation Of Time Formula

Jul 14, 2009

I am trying to calculate the response time between when a phone call comes into my workplace and when the responder calls back...I have created a formula that does this using the times and dates of when the calls were recieved and went back out. This works except when the call comes in on one day and goes back later in the day the next day, making the response time larger than 24 hours. I also have it set up to eliminate 15 and a half hours from the calculation because our place of business is not open during this time. Further details....

The formula currently being used is... =IF(G50=E50, H50-F50+(H50

View 9 Replies View Related

Time Spent Calculation

Feb 3, 2010

I need to find out the total time an issue was 'open' (not resolved) during business hours. Issues come in and resolution time is based off of a priority. Priority 1 should be resolved in one hour, Priority 2 should be resolved in 4 hours, Priority 3 should be resolved in 1 business day (8 hrs), Priority 4 should be resolved in 2 business days (16 hrs), Priority 5 should be resolved in 5 business days (40 hrs), Priority 6 should be resolved in 10 business days (80 hours).

I have start dates/times field in a column (mm/dd/yyyy hh:mm) , a resolution dates/times field in another column (mm/dd/yyyy hh:mm) and a priority in another column (1-6). I need to calculate the time an issue is in open status (not resolved) based on it's priority but I need for it to take into consideration business hours (Monday thru Friday...7 am to 7 pm)...and not calculate time outside of 'business hours'.

View 9 Replies View Related

Textbox Time Calculation

Oct 26, 2006

I'm attempting to calculate the total number of hours between a start time and end time using textboxes on a Userform.

Here is my latest attempt:

Private Sub D24_Exit(ByVal Cancel As MSForms.ReturnBoolean)
Dim myvalue As String
Dim myhour As String
Dim myminutes As String

myvalue = D24.Value

Select Case Len(D24)
Case 1
myhour = "0" & Mid(myvalue, 1, 1)
myminutes = "00"
Case 2
myhour = Mid(myvalue, 1, 2)
myminutes = "00"
Case 3

The above codes are an attempt to force an entry as time (7, 07, 700, 0700=7:00 / 13, 1300=13:00 etc.). However, the result is not correct.

For example:
Start Time in Textbox(D24)=07:00
End Time in Textbox(D25)=17:30
Result in Textbox(D27)=0.4375
Desired Result in Textbox(D27)=10.5

I've never calculated times in textboxes,

View 3 Replies View Related

Subtotals And Time Calculation

Jan 26, 2007

I am trying to calculate the time spent on each task.

I have column A with Task IDs and column B with Time. Column A could have the same task ID repeated but the column B has the time for each entry. There is only start time for each task.

Where the Task is repeated, want to know how many times the task has taken place and overall time spend on one task ID, calculating from the first entry to the last entry.

View 3 Replies View Related







Copyrights 2005-15 www.BigResource.com, All rights reserved