Covert Duration Between Start And End Date To Units

Oct 1, 2013

I need to formula to covert duration between start date and end date to units below.

Start Date
End Date
Number of Month
Number of Years
Number of Days

6/1/13
8/31/13

[Code] .........

View 6 Replies


ADVERTISEMENT

Calculate Duration Based On Start & End Times

Jan 21, 2008

I have a spreadsheet with 4 columns - Start Date, Start Time, End Date and End Time. In the 5th column, I need to fill in the "Duration" which is calculated as follows :- Duration = (End Date,End Time) - (Start Date,Start Time)

View 2 Replies View Related

Formula To Calculate Based On Start Month Number And Duration Number Of Months

Mar 14, 2014

I need a formula that will calucalte the monthly total based on the following conditions:

Col A = Yearly Cost
Col B = The number of the month when the costs are starting (1=Jan etc)
Col C = The duration or the number of months for which the costs are to spread
Col D is Year 2013 with the months across columns D-O. Row 1 above those columns shows the month's corresponding number.

Right now I have =IF($B3<=D$1,$A3/$C3,0) however if my start month is 1 and my duration is 5, I need the costs to stop after May. I've attached a sample file. Calculate based on start month and duration.xlsx

View 3 Replies View Related

Covert Into A Date

Oct 27, 2008

I have a long list (+1000 entries) of numbers (that actually represent dates) in cells one under neath another.I need to get them into date form so i can arrange them from earliest to latest.

Kind of looks like the following:

Cell1 - 1122005 (which i supposed to represent 1/12/2005)
Cell2 - 10192005 (.......................................10/19/2005)
Cell3 - 9282005 (.........................................9/28/2005)

Right now Excel just sees a bunch of numbers and does not know what to do with them.

View 9 Replies View Related

Covert Number To Date 20131126 To 11/26/2013?

Jan 1, 2014

Covert number to Date 20131126 to 11/26/2013

View 7 Replies View Related

Date Duration

Oct 26, 2008

Date problem.

I need to find the duration of time based on 4 columns:

column A : Start date DD/MM/YYYY
Column B : Start time HH:MM:SS [24 hour clock]

column C : End Date DD/MM/YYYY
Column D : End time HH:MM:SS [24 hour clock]

Column E: The duration result in : in Days and Hours

I have several thousand rows and need to complete before tomorrow

View 9 Replies View Related

Formula To Return Percentage Of Duration Elapsed Between Two Dates A Third Date Represents?

Feb 20, 2014

I need a formula that will calculate the percentage of the total duration between two dates (in dd.mm.yyyy hh:mm format) that a third, intervening date represents.

As an example:

a) 10th Jan 2014 09:00
b) 20th Jan 2014 09:00
c) 30th Jan 2014 09:00

In this case the answer sould be 50% because 'b' represents exactly half of the time elapsed between 'a' and 'c'.

Note: the formula needs to work effectively across the boundary between two consecutive years.

View 1 Replies View Related

Compute The FuTure Date When Start Date,Lead Date,Weekly Offs,Leaves And Holidays

Nov 15, 2008

First and foremost I would like to congragulate you on this wondeful piece of code in the below link...

The query was to get a future date excluding Fridays and Holidays...

http://www.excelforum.com/excel-work...rkingdays.html

I have a similar query and therefore I pasted this link...

I actually wanted to get a future date using a Dynamic two day off as my the offs keep on changing as well as incorporate Holidays and Leaves if any..

Now Holidays would be official Public Holidays and
Leaves would be taken by the employee..

The code needs to pick the Leaves + Holidays and different offs maybe even more than 2 offs...

View 7 Replies View Related

How To Auto-Populate Date Range (working Days Only) From Start Date And End Date

May 25, 2014

I am now trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.

View 1 Replies View Related

Calculate Next Due Date Based On Start Date Frequency And Current Date?

Mar 9, 2014

I'm trying to workout how to take a known initial date a repeating frequency and work out the next due date from today.

Example

Initial Date :- 1st of January 2014

Frequency :- every 5 weeks

Current Date :- 9th of March 2014

Next Due date should be :-12th of March 2014 (if I worked it out correctly from my paper calendar)

I want to use a cell formula to do this for different initial dates and varying frequency periods (the frequency will always be whole weeks i.e. 1,2,3,4,5,6,7,8,8,10)

View 4 Replies View Related

Create Calculator To Show Start And End Date Based On Specific Date Provided

Jan 12, 2014

I am trying to create a calculator which will show start date and end date based on the specific date provided.

EX: column A has January 1, 2013, column B has Wednesday, Column C should have a start date which supposed to be 4 days ago (December 28).

View 6 Replies View Related

Calculate Start Date From Finish Date Minus 14 Working Hours

May 7, 2014

I needs a formula (not VBA) to calculate the required start date.

I have to do a job of 14 working hours and this job must be finished on 05-may-2014 13:00

My working week is from monday u/i friday and every day I work from 08:00-16:00

At what time do I have to start the job to get it done in time.

The formula should give this result: 01-may-2014 15:00

View 3 Replies View Related

How To Auto Populate Date Range (working Days Only) From Start And End Date

May 26, 2014

i am trying to create a excel macro to auto populate all the dates with reference to a start date and end date. The catch is that only working days are required in the range. My reference cells (start and end date) are in Sheet 1 while the destination cell range are in Sheet 2. The reason for creating a macro instead of a function is that the intervals between the start date and end date changes frequently (annual, semi-annual and quarterly) Best case scenario would be a button which I can just press after i input the dates to generate the range of dates in another sheet.

View 4 Replies View Related

Automating Out Current Loan Period From Start Date And Today Date In IMPT Function?

Jun 12, 2014

Trying to automate the period part of the impt function

To calculate current value of loan i have the below formula below with the 3 being the current period

=IPMT(4.3%/12,3,5*12,-7000)/(4.3%/12)

What i would like to do is for the period to be self calcuating from current date and the loan start date. I can return a value in days using start date - today() and aware month function returns the month number but stuggling to find a way to work out cumulative month from the start date.

View 4 Replies View Related

Vbcodes To Select Start Date Then Begins Highlight Until End Date

Oct 28, 2006

i need VB to select the start date of booking and autohighlights the "blank booking slot cells" until the end date that is input in Excel. You can visualise this as a room booking system. The left most column is the dates and the first row represents the different rooms type. E.g. if one guest books the Twin Deluxe No. 123 room on 23 Oct 2006 until 25 Oct 2006. We wish the VB can essentially help us identify the start date then begins highlighting the three slots for 23, 24 and 25 Oct on the column for the Twin Deluxe Room 123.

View 4 Replies View Related

Calculate End Date From Start Date & Number Of Weeks

Jun 26, 2007

Take a look at the attachment file. Those highlighted in yellow are entered by the user. What is the formula to calculate the End date in (A6) after the user has entered the start date (A2) & the number of weeks (A4)?

View 5 Replies View Related

Highlight-Select Start Date To End Date

Oct 28, 2006

We are doing a project on a booking system and wish to use VB codes to autohighlight the slots from the start date until the end date.

View 9 Replies View Related

Find Start Date And End Date In Range

Jul 30, 2007

This is a sub that uses the Find method to find a series of dates and copy them to another worksheet. The following error comes up: Object variable or With block variable not set. I have tried using a set command etc. but other errors end up coming up.

Private Sub CommandButton7_Click()

On Error Goto errorHandler
Dim startDate As String
Dim stopDate As String
Dim startRow As Integer
Dim stopRow As Integer
startDate = InputBox("Enter the Start Date: (mm/dd/yy)")
If startDate = "" Then End
stopDate = InputBox("Enter the Stop Date: (mm/dd/yy)")
If stopDate = "" Then End
'startDate = Format(startDate, "mm/??/yy")
'stopDate = Format(stopDate, "mm/??/yy")
startRow = Me.Columns("A").Find(startDate, _
LookIn:=xlValues, lookat:=xlWhole).Row
stopRow = Me.Columns("A").Find(stopDate, _
LookIn:=xlValues, lookat:=xlWhole).Row
Me. Range("A" & startRow & ":A" & stopRow).Copy _
Destination:=Worksheets("Report").Range("A1")
End

errorHandler:
MsgBox "There has been an error: " & Error() & Chr(13) _
& "Ending Sub.......Please try again", 48

End Sub

View 9 Replies View Related

Add Days Between Start Date And End Date?

Jun 2, 2014

What I am trying to accomplish is, to add days from the start date (daily) and to stop adding at the end date.

Example:
(Column A) Start Date: 1/9/13
(Column B) End Date: 1/8/14

View 6 Replies View Related

Enter Start Date And End Date?

Mar 12, 2014

when I enter a start date and end date, it should autopopulate the columns with the dates in the middle including start date and end date.

View 1 Replies View Related

Autofill From Start Date To End Date

May 26, 2006

I have one column( date) which I wanna set date range from VBA macro. The problem is I wanna use Autofill to fill from the start date to the specific end date, but with Autofill func I cannot do this.

I attached a sample to explain my problem. Please take a look and give me a hint to do this.

View 6 Replies View Related

Getting The Date For The Start Of The Week

Jun 4, 2008

I have this column with a value like 04/06/2008. I will want another of the column to auto generate the date for the start of the week like 02/06/2008 which is a Monday.

View 14 Replies View Related

Start End Date Calculation

Nov 12, 2008

Need a formula that will generate the ending date of task, adding therefore if needed the number of weekend(s) in between the start and end date to the End date.

Let us say: task is starting in 2008/11/11 the duration of the task is 7 days. So, we should get an End Date= 2008/11/19.

2008 11/11 11/12 11/13 11/14 11/15 11/16 11/17 11/18 11/19
Tue Wed Thu Fri Sat Sun Mon Tue Wed

View 3 Replies View Related

Start And End Date Query

Nov 25, 2013

I've attached a sample of something I'm working on and the layout it's currently in.

I have a list of customers and an amount per month, in the sample, I want to be able to use a formula that will select which month the customer first has an amount >0 and in the end date column, I want to see when the customer then stopped showing an amount >0.

I have a massive list of these customers and sorting them each month is difficult.

DaveStart and End Month Sample.xlsx

View 2 Replies View Related

Start And END Date -- Status

Jan 24, 2010

1. If I enter a date in B3, then D3 will be S, and if I enter date in C3, D3 will be left blank while E3 result is D (Done). To have a clear view, I have attached the excel sheet.

View 3 Replies View Related

How To Covert Email Macro

Oct 22, 2013

I am trying to insert a macro to send myself an email when ever someone uses my spreadsheet (I'll embed the code in an existing macro).

The reason for this is to not only gauge who/how many people are using it but also make sure no one is using it externally (I suspect people are passing it on to people outside the company which they are not supposed to). I need it to be covert so I don't tip them off and they don't start circumventing this check.

I have found the below which works well, but I wanted to see if there could be some additional checks to better conceal the sending of an email.

Can I also somehow check the Outlook status to make sure it is working "online" so the email doesn't sit in their Outbox if they are not connected to the network/LAN?

Code:

Private Sub Workbook_Open()
Application.DisplayAlerts = False
Dim oApp As Object 'Outlook.Application 'Object
Dim ns As Object 'Namespace
Dim fldr As Object 'MAPIFolder
Dim mItem As Object 'Outlook.MailItem
Dim sendTo As Object 'Outlook.Recipient
Dim bOutlookFound As Boolean

[code]....

View 1 Replies View Related

Covert A Word Document

Jan 25, 2009

I need to covert a word document to excel.

View 9 Replies View Related

Calculate End Date Using Start Date And Number Of Days Excluding Specific Days

Nov 22, 2013

I want to calculate the end date of my German courses. This is how it works:

A course consists of 60 LU*. The course can occur i. e. three times a week: Monday, Wednesday and Friday. In each day the course lasts 2 LU, which means 6 LU each week. There is no course on Tuesday, Thursday, Saturday, Sunday and on holidays. Therefore this type of course that begins on 18-Nov-2013 will end on 03-Feb-2014.

Another course which occurs Tuesday, Thursday and Saturday, and respectively has 2 LU on Tuesday, 2 LU on Thursday and 3 LU on Saturday and starts on 03-Dec-2013 will end on 06-Feb-2014.

Therefore I want to create a worksheet where I set the start date, choose the days and respectively the LU amount on those days. The end date shall be calculated according to these criteria.

The workday function on excel cannot do this and I do not have any programming skills to work with VBA.

Legend:
*LU = lesson units; 1 LU is 45 minutes

Holidays:
28-Nov-13
29-Nov-13
08-Dec-13
09-Dec-13
25-Dec-13
31-Dec-13
01-Jan-14

[Code] ...........

View 7 Replies View Related

Return Start And Finish Date?

May 25, 2014

I am trying to return start and finish date of events depending on when resources are allocated.

View 4 Replies View Related

Sumif To Include Start Date

Jul 23, 2014

I am trying to find a formula for column D on the PO Costs EOY sheet. My criteria is as follows:

1. Column b on PO Costs EOY= Column A on Fabric and accessories
2. The order date in Column A is equal or in between the dates on rows 3 and 4 in fabric or basket accessories
3. I do not want to include in the some anything before order date, ie, if the order date is 8/8, i only want to sum 8/9 and greater.

The order date will always be on the last day of the week. So the sum would start the follow week.

View 3 Replies View Related