Calculate Workdays - Completion Date

Dec 26, 2012

I have the following function:

=IF(G13="",IF(H13>1,1,IF(G13>1,workdays(H13,G13,Holidays))))

The intent is to calculate the completion date against the assigned date as follows:

G13 - Typically the assign date but sometimes can be blank because someone forgets or doesn't bother to insert

For this example, let's say: 12/17/12

H13 - Completion date

For this example, let's say: 12/20/12

I'm expecting a result of '3' for 3 days

The first half of the function is intended to calculate 1 day if G13 is blank or not defined. However, when I have dates in both cells, I'm getting a "false" answer instead of a numerical value that I'm expecting.

In our workplace, we do work weekends & sometimes 7 days a week.

View 11 Replies


ADVERTISEMENT

Calculate The Number Of Workdays?

Jan 2, 2014

I need a way to calculate the number of workdays, Saturdays and Sundays in a month.

In my model, the client can choose to work on Saturdays and/or Sundays.I need someway to show that a given month (e.g. June 2014) has some # of workdays, and some # of Saturdays and some # of Sundays.I can do this on three separate rows.
eg.

Row 1: Month
Row 2: Wordays
Row 3: Saturdays
Row 4: Sundays

Still i need some way of determining that a given month (June 2014) has 22 work days, 4 Saturdays and 5 Sundays,... et cetera

View 4 Replies View Related

Calculate Workdays Between Dates

Nov 2, 2006

I am trying to map the total networkdays across the months of the year for a list of contracts with variable start and end dates.

Example of the results I'm after:

Contract StartDate EndDate January February March etc.
Contract1 15 Jan 07 13 Jul 07 13 20 20
Contract2 5 Feb 07 2 Mar 07 0 18 2


I assume that the add-in NETWORKDAYS function is involved (and I'm ordinarily comfortable with using this function with only two dates and my named range of holiday dates), but I can't seem to figure out how to use it in this more complicated way. My own extensive struggles with it have led to ridiculously long and nested formulas that even I didn't understand after a few days away from them. I've searched the posts and seen questions similar to mine, but not close enough to give me a solution.

View 4 Replies View Related

How To Forecast Project Completion Date

Sep 28, 2008

I have project start date in cell C2((MMDDYYYY format).In cell D2 I have put the total days needed to complete the project.In cell E2:E6 I have got the scheduled Holidays.

I need to calculate the project completion date in F2.We work from Monday to Saturday,Sunday being off day.

The detail is as follows:-

View 9 Replies View Related

Show Message If Completion Date Not Met

Aug 28, 2007

I have a spreadsheet where I have input all of my technicians service calls and installations.

In Column C Row 5 and up to the max I assume because I'm not sure how many rows I would use in a year, I have an estimated completion date.

In Column D and the same Rows as above I will input the Actual Completion date.

What I want is if the current date is past the estimated completion date (Column C) and there is no date entered in the Actual Completion date (Column D) I would like a MsgBox to pop up saying "Please enter a new completion date on row _"

"_" would be which ever row the estimated completion date has expired without an actual completion date being entered.

View 9 Replies View Related

Displaying What CAMPUS A Student Was LOCATED At On The Course Completion Date?

Jul 29, 2014

I have a spreadsheet containing 2 worksheets. First worksheet has my Students Details and the second spreadsheet has their Campus Locations.

What I need to create is a Formula that tells me "What CAMPUS was the student LOCATED at on the Course Completion Date?"

[URL]

what I'm trying to do is as follows:

John Completes his Course on the 25th July 2013, his Student ID is 450.

I need to go to the CAMPUS LOCATION spreadsheet and first search for Johns student ID (450) in column B. Because John is listed in B2,B3 and B4 excel needs to check date in Column E to see if his completion date was before the Date he started at Campus.

If it is then the Campus he was at will be the value of Column D on that line.

If it is not then it needs to search the next line until it satisfies the condition.

View 5 Replies View Related

Finding Data That Has 2 Work Orders And Comparing With Completion Date

May 31, 2007

What I am looking for is a macro/formula that will look at a unit number, then the type of work done, then the completion date and decide if the same type of work was done on the same unit within a 7 day span of time.

Example

Unit is 11111, work is plumbing completion date is 10/4/07
Unit is 11111, work is plumbing completion date is 10/7/07

This means the work has been done 2 times (obviously showing that it did not get fixed the first time)

Is there any way to mark an X in the square with the formula, or any type of identifier what-so-ever

I have attached a spreadsheet and hope it helps

Again I know this is complex so it is OK if no one feels like messing with it but I wanted to check here first.

View 3 Replies View Related

Subtracting Workdays From A Set Date

May 13, 2009

I am using excel 2003 and I am trying to subtract 20 days from the date in cell A3 in order to give me a date for me to order materials. However all I get is #NAME? in the cell.

View 4 Replies View Related

Add Workdays To Date And Time

Jul 3, 2014

I have data in column C which is the date and time

Data is: 16/06/2014 09:47:14
Cells are formatted as dd/mm/yyyy" "hh:mm:ss

Column H has another date and time based on service level agreements

Data is 17/06/2014 09:47:14
Cells are formatted as dd/mm/yyyy" "hh:mm:ss

I need to add 3 workdays to the 1st value so it returns 19/06/2014 09:47:14

I've used the following formula =WORKDAY(C2,3) and it returns the correct date but time shows as 00:00:00. Is there way I can pick up the time from Cell C2?

View 2 Replies View Related

Subtract Number Of Workdays From A Date

Feb 26, 2014

I am looking for a formula which substract a number of workdays defined in a cell from a date defined i nanother cell. For example I have a date in cell B2: 10.08.2014 - this is the due date for service delivery. In cell C2 there is a number of workdays: 84 - this is the duration for the delivery process. I would like to have a formula calculating in cell D2 the date when the delivery process has to start. The tricky point is that B2 is basicly a range of merged cells B2:B6. As an example I am attaching an exmple sheet.

View 10 Replies View Related

Count Workdays Between 2 Date Cells

Sep 4, 2009

I would require a formula to count the amount of workdays between cell a1 and cell a2. Assume formula is in celll a3 and both a1 and a2 are date formated.

View 2 Replies View Related

Add X Workdays To Date Including Saturdays

Apr 30, 2008

How to add 2 "working days" to a date, including Saturdays as work days, and excluding holidays and Sundays? Similar to: = WORKDAY ("01/02/2008", 2, 39451) But instead of resulting in Mon Jan 7th, the answer should be Sat Jan 5th. (39451 is Fri Jan 4th.)

View 4 Replies View Related

Date Macro :: Only The Workdays (not Saturdays And Sundays)

Sep 14, 2009

i need a macro that when run will look in to a cell say A1 and see "august 2009" and will list in another sheet all the workdays for august 2009, And if possible, (i can do without this but it would be better) only the workdays (meaning skipping saturdays and sundays,)

View 9 Replies View Related

Formula To Look Up A Date Array And Return How Many Workdays Between The Range

Feb 8, 2014

Assume I have a simple date array

1/13/20142/12/20143/12/20144/11/20145/13/20146/11/2014

I want Excel to see where today's date falls and return how many work days it is from the date boundaries.For example, today is 2/8, which falls between 1/13/2014 and 2/12/2014

Cell I19
=LOOKUP(TODAY(),B2:Q2)- yields 1/13/2014
=NETWORKDAYS(I19,TODAY()) yields 20 workdays

But I want to also grab the 2/12/2014 date and get the number of workdays from that- all in one equation.If not one equation then 2 but not separated for each border date like I have above

View 4 Replies View Related

Calculate Next Due Date Based On Start Date Frequency And Current Date?

Mar 9, 2014

I'm trying to workout how to take a known initial date a repeating frequency and work out the next due date from today.

Example

Initial Date :- 1st of January 2014

Frequency :- every 5 weeks

Current Date :- 9th of March 2014

Next Due date should be :-12th of March 2014 (if I worked it out correctly from my paper calendar)

I want to use a cell formula to do this for different initial dates and varying frequency periods (the frequency will always be whole weeks i.e. 1,2,3,4,5,6,7,8,8,10)

View 4 Replies View Related

Macro Stops Before Completion?

Apr 13, 2014

i ran some tests and it was working good only doing folders with ~100 files. i tried running the macro on all the files (~70,000), but I ran into problems with the computer going into standby while I was away. I tried running a batch of 3000 files and it completed, but only got up to around ~400 out of ~3000 records. Maybe, it stops cause of code related inefficiencies?

Here's the code:
macro_forexcelforum.txt

View 1 Replies View Related

Macro Quitting Before Completion

Nov 24, 2008

The macro is designed to grab a closing stock price for a date specified for a list of Symbols in column A and the date in column B. The closing price is then displayed in column D.

The problems (there are two that I found) I am running into is that when the Macro encounters a symbol in Column A and is not recognized, an error message pops up and the macro stops altogether. I want the macro to continue to run down the list but I can't figure out where in the macro it is stopping and, more importantly, how to make it continue. I have attached a copy of file if needed (if opened, you can see it stops working after row 11).

View 5 Replies View Related

Macro To Delete Itself Upon Completion

Feb 20, 2009

I have 2 command buttons on a sheet, one of which I would like to upgrade to delete the other, as well as itself, upon completing the rest of its functions. That's right, normal VBA isn't fun enough anymore, I want kamikaze suicidal code that wipes itself off the face of the earth.

My colleagues are... less than comfortable with VBA. I use it to produce some of the forms which I send to them, and if I could delete the code automatically after running, I'd save myself some time and/or save them some confusion.

View 2 Replies View Related

Subscript Out Of Range After Completion

Dec 31, 2009

I'm getting a "Subscript out of Range" error on a routine that was running fine a few days ago. It's part of a larger macro, so I've pasted the full code for that macro below. The problem is in the routine labled "Replace Regional Labels". What that's supposed to do (and DOES do) is to replace labels such as 110 or 11000-CSD with 11000. The error message comes up AFTER the routine has completed it's work. The offending line is:

View 2 Replies View Related

Calculate Start Date From Finish Date Minus 14 Working Hours

May 7, 2014

I needs a formula (not VBA) to calculate the required start date.

I have to do a job of 14 working hours and this job must be finished on 05-may-2014 13:00

My working week is from monday u/i friday and every day I work from 08:00-16:00

At what time do I have to start the job to get it done in time.

The formula should give this result: 01-may-2014 15:00

View 3 Replies View Related

Calculate The Number Of Days From A Date Entered Into Cell A1 To Today's Date

May 19, 2009

I need a formula that will calculate the number of days from a date entered into cell A1 to today's date. Whether it's before or after todays date. Example:

5/10/2009 to today is -9

5/22/2009 to today is 3

View 2 Replies View Related

Calculate Number Of Days Between Two Date Within A Current Month Including End Date

Apr 2, 2009

I have two columns of dates, leave start and end dates (when people start leave i.e. annual leave). Would need to introduce column(s) to calculate how many days fell within the month including the end date and excludes weekends.

For example, if the staff on leave from 31st March to 6 April, i need to show that the number of leave taken as 1 day in March and 4 days in April.

View 9 Replies View Related

How To Calculate Average Of Values Against Selected Date Of Each Month Within Date Range

Jan 2, 2014

I have a table that looks like this (its basically a historical data of a stock exchange):

Date
Index
January 4, 2010

[Code]....

The List continues till the current Date.

I want to calculate Average Index Values of a Date of each month within a Date Range.
Example: Calculate Average Index Values for 3rd of Each month from 1st Feb 2010 to 3rd Jan 2011. Formula should calculate Average of the Index Values for 3rd Feb 2010, 3rd March 2010, 3rd April 2010, 3rd May 2010, 3rd June 2010, 3rd July 2010, 3rd Aug 2010, 3rd Sept 2010, 3rd Oct 2010, 3rd Nov 2010, 3rd Dec 2010, 3rd Jan 2011.

Both the Date and the Date Range is variable. Also, the Index Value for selected Date of one or more month may not be available as that being a holiday. In that case, the formula needs to use the last available Index Value before that Date. e.g. If Index Value for 3rd Oct 2010 is not available, system will use the Index Value of 2nd Oct 2010.

View 1 Replies View Related

Time To Completion Countdown Timer

May 8, 2014

I need to list multiple items that end in, example:at time entered there is 45:14:50 = Hr:Mn:Sec to completion, and would like the date and time of completion or just a countdown to 0 would work. I will have 60 to 70 items running at the same time with different start times and lengths. Picture queueing up items at different times to complete in different length of time and I need to be ready when each item is done. I know this is an Excel forum but I also use Apple Numbers so if either one works better I'm fine with that.

In the attached file, column R is the start time that I enter that needs to be calculated to column S. When I enter an item that takes 54hrs 23min 45seconds to complete, what date and time will it be ready.

View 9 Replies View Related

Macro That Closes Excel Upon Completion?

Jan 14, 2008

This is my first time posting to the site so I will start with a simple question. I have an email macro that will send the workbook to a specific recipient. What I want it to be able to do is close excel after the macro is ran and the email is sent. If anyone would be kind enought to supply me with a code that will work .....

View 9 Replies View Related

Calculate Date Difference & Use Current Date If Cell Empty

Sep 22, 2007

i am trying to create a forumla in a column (D in my expamle below) to count the number of days between two dates. Knowing that col D will change everytime the @now date changes - but thats ok..

COL A COL B COL D
ROW 1 Open Date Closed Date Count of days open
ROW 2 4/1/07 BLANK CELL Formula result here
ROW 3 4/1/07 9/5/07 Formula result here

if col b has a date then subrtract col a from b and display the # result, if col b is blank then subtract col a from location I store the @ now date - say Col ZZ Row 99? so no matter there is a count of number of days in every row in column D

View 3 Replies View Related

If Date Cell Less Than Todays Date Calculate Difference In Days

May 13, 2008

I have column B with a heading "Days Remaining" and column L with a heading "Deadline". starting with row 5, I need to be able to enter a date in L5 and see the days I have left, from that day untill today, on B5. I need to then be able to enter a date into L6 and see a result in B6 and on and on. Then I need to be able to insert or delete a column and have the formulas still work in the columns with the heading "Days Remaining" and "Deadline"

View 7 Replies View Related

Changing Cell Colour On Basis Of Completion?

Apr 7, 2013

I have two sheets, one sheet showing the total calories burned, in the sheet two, i have the target set,

How can i change the color of cell in the target on the basis of the achivement for example the target is say 10,000 cells and after I achieve 1500, it will change the color, after 3000 it will change another color and so on and so forth.

View 1 Replies View Related

Vacation Accrual Based On Completion Of 90 Day Probation?

Nov 29, 2013

I need to create a tracking sheet for my vacation. The vacation starts to accrue here after a 90 day probation following the hire date. Each individual is allowed 40 hrs/year. I also need to see the hours accrued, the hours used & the balance. Everyone's balance renews on their anniversary. I will fill in the blanks for the names in one column & the hire date in the next column and I would like formulas for the following columns.

View 12 Replies View Related

Calculate Timecycle From Open Date To Close Date?

Jun 12, 2014

Looking to calculate timecycle from open date to close date. Having trouble trying to figure out how to have the formula look at the close date cell and if it is blank go to the next cell in the row to find a close date and subtract the open date from the close date to get the total number of days in the timecycle. See attached example.

View 1 Replies View Related







Copyrights 2005-15 www.BigResource.com, All rights reserved