Add X Workdays To Date Including Saturdays

Apr 30, 2008

How to add 2 "working days" to a date, including Saturdays as work days, and excluding holidays and Sundays? Similar to: = WORKDAY ("01/02/2008", 2, 39451) But instead of resulting in Mon Jan 7th, the answer should be Sat Jan 5th. (39451 is Fri Jan 4th.)

View 4 Replies


ADVERTISEMENT

Date Macro :: Only The Workdays (not Saturdays And Sundays)

Sep 14, 2009

i need a macro that when run will look in to a cell say A1 and see "august 2009" and will list in another sheet all the workdays for august 2009, And if possible, (i can do without this but it would be better) only the workdays (meaning skipping saturdays and sundays,)

View 9 Replies View Related

Excel 2007 :: NETWORKDAYS Function - How To Include Saturdays As Workdays

Nov 26, 2011

I have never worked on workdays before so I do not know most of the available formula and play around. I googled across and found this one: [URL] .......

Where Bob has given an ARRAY formula.

Following is my layout in A1 to C3 grid (for testing purpose):
Start Date11/1/2011HOLIDAYEnd Date11/30/201111/3/2011NETWORKDAYS2011/22/2011
The formula resides in B3.

Is there any other development in 2007+ versions of Excel which can handle 6 working days in a week?

View 9 Replies View Related

Autopopulate Saturdays In Multiple Cells Based On Month Date In Another Cell

Aug 19, 2014

get other cells in a spreadsheet to populate with the Saturdays of a month based on the date input in another cell.

Example
A1 = October 2014
The following cells would automatically display:
A2 10/04/14
A3 10/11/14
A4 10/18/14
A5 10/25/14
A6 11/01/14

Then if cell A1 is changed to March 2015 the following cells would automatically display:
A2 03/07/15
A3 03/14/15
A4 03/21/15
A5 03/28/15
A6 04/04/15

I can't seem to find a way to get just the Saturdays. +7 doesn't work because Saturday is not always the 7th day of the month.

View 2 Replies View Related

Subtracting Workdays From A Set Date

May 13, 2009

I am using excel 2003 and I am trying to subtract 20 days from the date in cell A3 in order to give me a date for me to order materials. However all I get is #NAME? in the cell.

View 4 Replies View Related

Add Workdays To Date And Time

Jul 3, 2014

I have data in column C which is the date and time

Data is: 16/06/2014 09:47:14
Cells are formatted as dd/mm/yyyy" "hh:mm:ss

Column H has another date and time based on service level agreements

Data is 17/06/2014 09:47:14
Cells are formatted as dd/mm/yyyy" "hh:mm:ss

I need to add 3 workdays to the 1st value so it returns 19/06/2014 09:47:14

I've used the following formula =WORKDAY(C2,3) and it returns the correct date but time shows as 00:00:00. Is there way I can pick up the time from Cell C2?

View 2 Replies View Related

Subtract Number Of Workdays From A Date

Feb 26, 2014

I am looking for a formula which substract a number of workdays defined in a cell from a date defined i nanother cell. For example I have a date in cell B2: 10.08.2014 - this is the due date for service delivery. In cell C2 there is a number of workdays: 84 - this is the duration for the delivery process. I would like to have a formula calculating in cell D2 the date when the delivery process has to start. The tricky point is that B2 is basicly a range of merged cells B2:B6. As an example I am attaching an exmple sheet.

View 10 Replies View Related

Count Workdays Between 2 Date Cells

Sep 4, 2009

I would require a formula to count the amount of workdays between cell a1 and cell a2. Assume formula is in celll a3 and both a1 and a2 are date formated.

View 2 Replies View Related

Calculate Workdays - Completion Date

Dec 26, 2012

I have the following function:

=IF(G13="",IF(H13>1,1,IF(G13>1,workdays(H13,G13,Holidays))))

The intent is to calculate the completion date against the assigned date as follows:

G13 - Typically the assign date but sometimes can be blank because someone forgets or doesn't bother to insert

For this example, let's say: 12/17/12

H13 - Completion date

For this example, let's say: 12/20/12

I'm expecting a result of '3' for 3 days

The first half of the function is intended to calculate 1 day if G13 is blank or not defined. However, when I have dates in both cells, I'm getting a "false" answer instead of a numerical value that I'm expecting.

In our workplace, we do work weekends & sometimes 7 days a week.

View 11 Replies View Related

Formula To Look Up A Date Array And Return How Many Workdays Between The Range

Feb 8, 2014

Assume I have a simple date array

1/13/20142/12/20143/12/20144/11/20145/13/20146/11/2014

I want Excel to see where today's date falls and return how many work days it is from the date boundaries.For example, today is 2/8, which falls between 1/13/2014 and 2/12/2014

Cell I19
=LOOKUP(TODAY(),B2:Q2)- yields 1/13/2014
=NETWORKDAYS(I19,TODAY()) yields 20 workdays

But I want to also grab the 2/12/2014 date and get the number of workdays from that- all in one equation.If not one equation then 2 but not separated for each border date like I have above

View 4 Replies View Related

Calculate Number Of Days Between Two Date Within A Current Month Including End Date

Apr 2, 2009

I have two columns of dates, leave start and end dates (when people start leave i.e. annual leave). Would need to introduce column(s) to calculate how many days fell within the month including the end date and excludes weekends.

For example, if the staff on leave from 31st March to 6 April, i need to show that the number of leave taken as 1 day in March and 4 days in April.

View 9 Replies View Related

SumIF With Dates: SUM All Expenses After The Posted Date Including That Date

Feb 13, 2009

In the expense log, Column C is a list of Dates and Column I is a list of expenses. I want to Sum the expenses in the 'Expense Log 09' to a new sheet based on a Date entered in H24 on the new sheet. I have tried the formula as shown below and Get the result #NAME?

=SUM(IF(Expense Log 'Expenses Log 09'!C8:C100,H24,'Expenses Log 09'!I8:I100)). I would Like to SUM all expenses After the posted date including that date.

View 5 Replies View Related

VBA – Including Date In Filename

Mar 22, 2007

I’m trying to save a new workbook with the current date included at the end of the filename, in the format yyyy-mm-dd.

I took a guess at the following but it doesn’t work - the filename comes out as 'Report39163' Can anyone help please?

ActiveWorkbook.SaveAs Filename:="\UsersDataTemp" & "Report" & Format(Date, yyyy-mm-dd) & ".xls")

View 9 Replies View Related

Index With Multiple Criteria Including Date Range

Dec 2, 2013

I know need to modify the formula to include validating if the indexed reference occurs within a certain month.

{=INDEX('Duration Calculations'!B$2:B$5000,SMALL(IF(MONTH('Duration Calculations'!$J$2:$J$5000=10),IF(ISNUMBER(SEARCH("br",'Duration Calculations'!$A$2:$A$5000)),ROW('Duration Calculations'!$J$2:$J$5000)-ROW('Duration Calculations'!$J$2)+1)),ROWS(P$100:P101)))}

Essentially, what I am trying to do is index the value from B column if it meets the following criteria

1) Date in column J is equal to any date that occurs in October
2) the Column A has a text value equal to "br"

If both true then I need to index the value in column B.

The formula as states works finding any value equal to "br" but seems to be ignoring the date range.

View 1 Replies View Related

SUM (count) - Multiple Criteria Including Date Ranges

Oct 23, 2009

My setup is - excel 2003 sp3 / windows xp

On one sheet (Data) I have a list of action items, each with owner; target date; classification and in some cases revised target date. I'm trying to report on these fields and provide a status, by owner and classification, of how many are overdue; due this month; due next month; due beyond 2mths.

Using a SUM array formula on another sheet I can count the number that are overdue based on date; owner; classification; and target date, but can't find a solution if there is a revised target date. Any guidance you can give would be greatly received.

=SUM((Data!$L$3:$L$27=D$18)*(Data!$P$3:$P$27=$C23)*(Data!$N$3:$N$27

View 9 Replies View Related

Creating A Log That Logs The Last User That Saved The Workbook Including The Date And Time

Mar 16, 2004

Is there any way of creating a log that logs the last user that saved the workbook including the date and time. I would like the log to be a sheet hidden in the workbook. Not many people will be saving the workbook.

View 9 Replies View Related

Date Cells In Project Plan To Change Based On Other Cells Including Other Date Cells

Oct 31, 2008

This is a project plan with tasks and dates. Column A is the activity number. (Example 1, 2, 3" etc). Column B is the task (Ex. "Complete Report"). Column C is number of days required to complete the task. Column D is the dependency column. (Ex. Cell D2 =1 in other words Task 2 is dependent on task 1). Column E is the date.

I would like to have a seperate start date cell and a go live date cell.

The objective is to enter a start date, and have each column E date increase based on the number of days entered in Column C. If a task is dependent on another and I change the number of days in Column C I need the dependent task to change the same amount of days.

View 9 Replies View Related

Include Saturdays And Maybe Sundays

May 20, 2008

currently I'm working as project manage for a software development studio and I am using MS project for all my work. Since the development team aren't aloud to have a MS project license on their PC I have to copy their tasks from MS project and put them into Excel.

I would say that I am okay using Excel but not an expert. I want to create a formula that uses NETWORKDAYS to determines a finish date from a duration and start date.

The headers I would use for each column are Duration, Start and Finish. So I would like to be able to get a team member to put a duration down i.e 1 day and give me the start day and in the finish date it produces a finish date automatically without including Bank Holidays and Weekends. What would the formula be for that?

I have the same question as Madball and was able to work out the Worday function, however for my company, we work on Saturdays and or Sundays sometimes.

I would like to be able to specify from line to line if Saturday or Sunday needs to be included in the duration calculation resulting in a finish date, however if I can simply get one formula to work that includes Saturdays alone (most common working day of the weekend, and do work more than don't) it would be the most helpful, I think I can get it adjusted from there.

View 12 Replies View Related

Highlighting Saturdays And Sundays In A Column

Jan 14, 2010

I am running Excel for Mac V2008.

My spreadsheet has various columns with column A representing dates of a 6 month period formatted as: ddd d-mmm-yy, one day per cell.

I want to highlight the cells which are Saturdays and Sundays and are not working days for my Plant.

I think it may be done using conditional formatting, but I have been unable to discover the right formula which would allow this to happen.

View 9 Replies View Related

Populating Current Month Saturdays Dates Vba?

Feb 26, 2014

I have sheet1 want to populate current month all Saturdays dates in range C14 to C18 I am trying for vba or formula.

View 4 Replies View Related

Count Total Number Of Saturdays In 2013

Apr 13, 2012

the closest appears to be the number of Fridays in a particular month.

What I need to calculate is the number of Saturdays in each year from 2013 through to 2022 (by year), and the same thing for number of Sundays. I presume that it will be 52, however if a year starts on a Sunday and it is a leap year then there could well be 53.

I tried =SUMPRODUCT(--(WEEKDAY(YEAR(C1)=7))) (where C1 has 2013) to try and calculate the number of Saturdays in 2013, but it didn't work.

View 8 Replies View Related

VBA To Add Workdays To Datetxtbox

Mar 26, 2014

I have a userform that captures dates and records them to another excel workbook so we can analyse the data. I have one last part to finalise; When a date is added to the "daterecievedtxtbox" I would like a formula to be offset to the end of the spreadsheet, that will take this date and add 3 working days to it. Then I can add in some formulas later to flag them when the date passes the 3 working days.

At the moment I have this:

[Code] ....

Which adds 3 days to this txtbox and writes it to the sheet that I have defined. I would like to know if there is a function that I can use to add 3 WORKING days to this, excluding saturday and sunday.

View 4 Replies View Related

Workdays In A Month

Oct 28, 2009

I would like to know how to get the number of working days in a month based on the date in B4 which is formatted as "mmmm".
So if B4 was October the result would be 22 regardless of the actual date in B4.

I also have a named range "Holidays" for UK bank holidays (ready for December) that I would like included within the formula.

View 9 Replies View Related

Calculate The Number Of Workdays?

Jan 2, 2014

I need a way to calculate the number of workdays, Saturdays and Sundays in a month.

In my model, the client can choose to work on Saturdays and/or Sundays.I need someway to show that a given month (e.g. June 2014) has some # of workdays, and some # of Saturdays and some # of Sundays.I can do this on three separate rows.
eg.

Row 1: Month
Row 2: Wordays
Row 3: Saturdays
Row 4: Sundays

Still i need some way of determining that a given month (June 2014) has 22 work days, 4 Saturdays and 5 Sundays,... et cetera

View 4 Replies View Related

Filter For Workdays Returns Nothing

Jul 9, 2014

I am looking to find a way to filter a list for the next twenty business days.

View 7 Replies View Related

Net Workdays Cycle Time?

Dec 3, 2013

So I have a cycle time formula; Start Date to Completion Date, if the task is not complete the completion date field is blank. In this case the cycle time is listed as a negative 5 digit value. The networkdays formula takes into consideration weekends and holidays.How can this field be left blank rather than the negative value?

=NETWORKDAYS(I2,P2,Sheet3!$A$2:$A$10)

View 6 Replies View Related

Display How Many Workdays There Are In A Month

Oct 18, 2007

What formula would I use to display how many workdays there are in a month.

The month is displayed in cell A1

View 9 Replies View Related

Conditional Formatting With Workdays

Sep 7, 2008

I have an excel file I am working on with a due date column. I have already created 2 conditional formatting.

1. if cell value is less than today's date then format the cell red
2. if cell value equals today's date then format the cell orange

I need to create two more conditional format....one where it looks at today's date and if the due date date cell is within 1-3 business days from today's date then I want the cell format to turn yellow and I need a last conditional format to look at today's date again and if the due date cell is within 4 -5 business days from today's date then I want the cell format to turn green. Can these two additional conditional formats be done?

View 9 Replies View Related

Calculate Workdays Between Dates

Nov 2, 2006

I am trying to map the total networkdays across the months of the year for a list of contracts with variable start and end dates.

Example of the results I'm after:

Contract StartDate EndDate January February March etc.
Contract1 15 Jan 07 13 Jul 07 13 20 20
Contract2 5 Feb 07 2 Mar 07 0 18 2


I assume that the add-in NETWORKDAYS function is involved (and I'm ordinarily comfortable with using this function with only two dates and my named range of holiday dates), but I can't seem to figure out how to use it in this more complicated way. My own extensive struggles with it have led to ridiculously long and nested formulas that even I didn't understand after a few days away from them. I've searched the posts and seen questions similar to mine, but not close enough to give me a solution.

View 4 Replies View Related

Difference Between 2 Dates In Workdays Only

Mar 4, 2008

I need to calculate the difference between two work days to understand how many days late we missed a due date. The NETWORKDAYS formula gives me the COUNT of the workdays, but I need the difference.

Example 1:
Expected Due date: 3/3/08
Actual Due date: 3/3/08

NETWORKDAYS for the dates above gives me the value of 1, but for my needs I need the resulting value to be zero.

Example 2:
Expected Due date: 3/3/08
Actual Due date: 3/5/08

NETWORKDAYS for example 2 provides a value of -3 (days late), but in reality it's only -2 (days late)

View 7 Replies View Related







Copyrights 2005-15 www.BigResource.com, All rights reserved