** array formulas need to be entered using the key combination of CTRL,SHIFT,ENTER (not just ENTER).
Hold down both the CTRL key and the SHIFT key then hit ENTER.
The logic of the formula is:
The max Sunday date within the date range minus the min Monday date within the date range +1 = total days divided by 7 (days in a full week) = full weeks
How to get "only Sunday" highlighted in a series of dates included in excel columns. I tried some formulas found from the web pages, but they all deal with both "Saturday and Sunday"...
In B13 I have the start date: 12/1/2008 In C13 I have the end date: 1/5/2009 In cell D13 I want a formula that counts the number of days between the two dates that are not Sunday. The start and end dates are included in the count.
I have created this formula using Ctrl + Shift + Enter:
I am looking for Macro code preferably to get list of dates with Saturday / Sunday in a separate columns which falls Saturday and Sunday on imputing the year.
I am currently using this formula =DATE(YEAR(A1),MONTH(A1)+6,DAY(A1)) to get me 6 months ahead from a certain date. There is a new problem that has arose for me. I need a formula that will give me 6 months from a certain date if it falls on a Monday if the 6 months does not fall on a Monday then give me the next Monday date. for example 6 months from 1/2/2007 is 7/2/2007 which falls on a Monday which is fine but, If the start date was 1/3/2007 this falls on a Tuesday so I would need the next Monday date 7/9/2007.
"Decision Date". It is a numerical date (ex: 1/5/09 indicating January 5th 2009).
I need to turn that date into the week that it falls into within a particular quarter of a year. 1/5/09 would be Week 2 (it is in the second week of January, and 2nd week of the quarter) 2/3/09 would be week 6 (6th week of the quarter).
And then I need the formula to start over once each quarter restarts... for example, April 1st would be week 1 (1st week of the second quarter).
I've been having problems coming up with a formula that will take a start date and an end date and come up with the number of weeks INVOLVED within this date range (each week being a Sunday through Saturday).
My problems is that the start and end dates could be any day of the week and not necessarily the same day (meaning divisible by 7 doesn't always work). I tried using ROUND((A2-A1)/7,0)+1 where A1 was the start date...and A2 was the end date.
The problem I had was if I picked a Monday as the start date, and went 12 days out (The saturday of week2)...it came up stating 3 weeks were involved - AND if I selected a Friday start date and picked the following monday in week 2 - the result was 1 week involved when 2 different weeks were involved.
I have a large spreadsheet which lists individual dates over two years and circulation figures next to each date. Sometimes there are two entries for a particular date e.g. 1/10/08 there were 150 readers of magazine A and 200 readers of magazine B. When displaying this on a graph it give a bar for each day, whereas I would like a bar for each week.
Is there a formula to convert the individual dates into weeks and then total the circulation figures for that week?
Hereīs the deal: based on weekly reports, I need to count and sum orders created in our CRM.
Iīm exporting, once a week, a full report of opportunities created in our CRM. Week after week I copy&paste the changes to my main file or dashboard. This allows me to see, manually four values my sales manager wants:
1. Opportunities created in the last week 2. Opportunities created in the last 2 weeks 3. Opportunities created in the last month 4. YTD
I donīt need help with the last one, thatīs the easy part. The thing is, I have to do this manually. Every thursday I run the report, export it, find the new opportunities and add them to my main report. Then, I just modify an already defined IF formula that counts and a SUMIF one that sums the values, so it will take into account only the last week, the one before that one and the whole month.
So, my questions are...
1. I need to set different formulas for count and sum, thatīs clear, but how can I make this autimatically without having to change the formula each week?
2. Do I need to consider the date my main file is modified, and count backwards?
As usual I am not sure Iīm being clear, though I hope Iīm getting better at this. Iīm attaching an example where B2:D7 is similar to my main report, and G4:M12 is my DataTable.
The formulas in C4, C5, C6, D4, D5, D6 should be "automatic", so when I copy&paste the extra rows from the weekly reports into my datatable, those cells will count and sum without me having to change the period in the formulas.
how create a formula in D2 to D27 using the date A1 = (A2 to A27), and calculate how many weeks delayed comparing the value of Cum Actual (B1) if it less than, equal or greater than the value of Cum Planned (C1).
I want to calculate leave on the basis of Date of joining (DOJ). Rule is: If DOJ is not he first day of the month, then no leave is earned for that month. Suppose DOJ is 26/12/2006, for Dec.2006 no leave is earned. One leave will be earned in January 2007 & subsequent months.
But if DOJ is 01/12/2006, then one leave will be earned in Dec.2006 & subsequent months also.
A zip file containg two excel files is attached for ready reference.
I am using excel to analyze stock changes. Yahoo spits out a column with dates and another with closing prices but occasionally inserts a row showing a dividend, something like this:
In the spreadsheet, column A is date and Column E is closing price, such that the cell in column E where the dividend is listed is blank.
The problem- as I update data each week, the dividend row moves. How can I consistently figure price changes for 4 weeks and 13 weeks without getting messed up by the dividend row? Is there to auto delete the row or make the formula count down 4 cells in the price column, while skipping any cells without data?
I'm trying to see how accurate people's work predictions are to actual work completed. So I have these formulas:
=IF(C15=0,"",(SUMIF(L$24:IO$24,"Est.",L15:IO15))) - total estimated days =IF(C15=0,"",(IFERROR((SUMIF(L$13:IO$13,"Act.",L15:IO15)),""))) - total actual days
But the problem of course is that people estimate a load of work and only fill in the actual days as they go along, so the accuracy of comparing one to another is almost always misleading.
What I want to do is only count the values in the weeks Estimated if the Actual figure is also there (L24:IO24), which is always the cell directly on its right.
I am trying to simplify a type of gannt chart bar across a spreadsheet. The spreadsheet has dates across row 3 that are calculated from the first cell F3 with =F3+7 to populate the rest of the row with dates. I want to be able to input a start date in D4, then all the other titles in column A. This start date will start the coloured bar at that start date in the chart, I will then copy/drag that start date cell for however number of weeks for the duration and I want the finish date to auto populate E4 with the finish date and also auto populate the numbers of weeks in C4 for that bar.
Excel 2007ABCDEFGHIJKLMNOPQRSTUVWXYZAAABACADAEAFAGAHAIAJAKALAMANA OAPAQARASATAUAVAWAXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBWBXBYBZ CACBCCCDCECFCG1D42342McArthur River Mine Power
I am trying to update a spreadsheet for 2012 to 2013 and want to use a formula to change SUNDAY 8 January to Sunday 9 January and so on for rest of year.
Basically I have 2 columns each with a list of dates in no particular order (and containing blank cells too), one planned date column and one actual date column.
What I need to do is plot this on a graph, and since the number of dates has no set limit and I dont want to have to plot maybe 100 dates on the x axis, so i want to group them by week before plotting them, i.e. 10 dates for week ending 10th jan, 25 dates for week ending 17th jan etc
I have a pivot table that counts how many of each date occurs, i.e. 10 x 2nd jan, 7x 3rd jan etc etc but it does not split them into weeks.
im sure theres an easyish way of doing it so i can get the 2 lines on the graph for no. of planned dates each week and no. of actual dates each week, i just cant see it.
Today I am having a very annoying problem that really has me stumped I need to work out the lag between a Due Date and Delivered Date
But as people sometimes manage to deliver on the Due Date it needs to show a zero (as in they got it in on time) but using the formula below the result is a 1 and I want a zero
Can anyone help me please? I have tried putting assorted -1s in to the formula and it looks like it might work until I copy down and find that if a person delivered one day early the result shows -3 for example!