Identifying Dates For This Week And Next

Oct 10, 2009

i have a spreadsheet that contains dates spread across different rows and columns. How can I identifying dates for this week and next week by colouring the cells?

example dates that fall within this week will be red, next week will be blue.

View 7 Replies


ADVERTISEMENT

Generating List Of Week Working Days And Identifying Holidays

Oct 28, 2009

From another thread I got this formula placed on B5:
=NETWORKDAYS(EOMONTH(B4,-1)+1,EOMONTH(B4,0),Holidays)

his generates the number of working days for that month (regardless of the date on B4) that exclude Holidays listed under the range "Holidays".

I also got this code (Credits to XXXX)

View 4 Replies View Related

Identifying Weekend Dates In A List Of Dd/mm/yy Dates

Jan 7, 2010

Is it possible to set conditional formatting to highlight any days which are saturday and sundays?

I have long long list of dates in the 17/12/2009 format, I need to be able to quickly see which dates are weekends.

View 4 Replies View Related

Identifying Start And End Dates In A Series

Jul 11, 2007

i am trying to both identify the start date and the end date of a series in excel.

if you will, picture a spreadsheet with two rows with data. the top row is comprised of dates in mm/dd/yy (end of month) format. the bottom line is percentages . . . a corresponding % for each date directly above. these percentages add to 100%. in two separate formulas, I would like to identify:

1. the date in which the first %>0 occurs (start date)
2. the date in which the cumulative addition of all months %'s equate to 100% or the date in which the last %>0 occurs (end date)

keep in mind many if not most of the %'s will be 0%.

View 13 Replies View Related

Convert List Of Dates To Count No. Of Dates By Week

Jan 27, 2006

Basically I have 2 columns each with a list of dates in no particular order (and containing blank cells too), one planned date column and one actual date column.

What I need to do is plot this on a graph, and since the number of dates has no set limit and I dont want to have to plot maybe 100 dates on the x axis, so i want to group them by week before plotting them, i.e. 10 dates for week ending 10th jan, 25 dates for week ending 17th jan etc

I have a pivot table that counts how many of each date occurs, i.e. 10 x 2nd jan, 7x 3rd jan etc etc but it does not split them into weeks.

im sure theres an easyish way of doing it so i can get the 2 lines on the graph for no. of planned dates each week and no. of actual dates each week, i just cant see it.

View 13 Replies View Related

Use Dates To Get Week It Falls On

Dec 12, 2008

I have a list of dates in col "A". In col "B" i would like it to display the week it falls on. Example 12/12/08 would fall under week 12/7/08 to 12/13/08.

View 6 Replies View Related

VBA Filter By Last Week Dates

Oct 3, 2012

Is there a way with VBA to sort lets say column A by last weeks dates. For example, if to day is Wed Oct 3, can I filter it for Sep 24-28?

All the dates in col A are in 10/2/12 format.

View 3 Replies View Related

Display Day Of Week From Dates

Mar 15, 2008

I have a column of dates in one column and in the next column next to the dates, I want to show the day of the week that each date represents, such as;

Col A Col B
1 March 2008 Sunday or Sun

etc etc..

View 5 Replies View Related

Calculating Two Values Between Two Dates (per Week)

Jun 9, 2014

I need to make a table for an injury category per shift per week. (Falls per shift per week)

I have attached an example of the spreadsheet. I have a formula in the table now that was calculating just the injury type per week but just need to add the function to read per shift but can't seem to get it to read correctly.

View 2 Replies View Related

Getting Dates To Cover Week Numbers

Jan 10, 2014

I wanted to work backwards from a weeknumber (as defined in Excel). In other words, given a week number (i.e. 5) what is the first date and last date of that weeknumber. These are the formulas that I came up with and they work fine.

Formula: [Code] ......

Ffor 1st of the week and

Formula: [Code] .......

For the last of the week.

Attached File : Weeknumber.xlsx‎

View 5 Replies View Related

Dates Showing As 1 Week Ahead / Behind?

Aug 11, 2014

I'm using this formula to look up the date stored in one vile (shown as a number, e.g 35), and then pulling this back to the first sheet in order to convert it to a date. Problem is the date keeps showing up as a week after its supposed to be.

=IF(VLOOKUP(B76,'[MAD File.xlsx]Feuil1'!$A:$K,11,0)="","",MAX(DATE(BN76,1,1),DATE(BN76,1,1)-WEEKDAY(DATE(BN76,1,1),2)+('[MAD File.xlsx]Feuil1'!K74)*7+1))

View 3 Replies View Related

Count All Rows (dates) That Will Come Due In A Week

Mar 27, 2009

Worksheet is an action log. It has a column containing "due dates". I want to count all rows (dates) that are "less than" today (to see what work is overdue). I also want to count all rows (dates) that will come due in a week. Conditional formatting highlights them OK but I also want to maintain a set of counts. I can do all this in a macro but I don't want to use macros, just formula.

View 2 Replies View Related

How To Assign Week Number Against Dates

Apr 15, 2012

We have started a new venture from 5th April & I need to create a template for a year and assign week no against the dates. The week1 will start from 5th April & week 52 will end on 31st March.

Also there will be a summary of the Week No(Starting Date & End Date) against each week at the top of the template. I could put the formula for the summary part but I am unable to figure out how to assign week no against the dates as given below. It is very difficult to assign the week no manually for the whole year & also it is vulnerable to error. a formula across B7:B23 which can deliver the desired result?

Sheet2  ABC1Week NoStart DateEnd Date2Week15-Apr8-Apr3Week29-Apr15-Apr4Week316-Apr22-Apr5   6DateDesired
Result 75-AprWeek1 86-AprWeek1 97-AprWeek1 108-AprWeek1 119-AprWeek2 1210-AprWeek2 1311-AprWeek2 1412-
AprWeek2 1513-AprWeek2 1614-AprWeek2 1715-AprWeek2 1816-AprWeek3 1917-AprWeek3 2018-AprWeek3 2119-

[Code] .........

View 9 Replies View Related

How To Count Dates Based On Week

Jul 18, 2012

I have a worksheet that lasts for a year that is something look like this:

Date Name
1/1 John
2/1 Erwin
3/1 Robert
4/1 John
16/1 Erwin
17/1 Erwin
17/1 John

In my report worksheet, I need a formula to count everyone's attendance from their participation dates based on week

Name Week1 Week3
John 2 1
Erwin 1 2
Robert 1 0

View 4 Replies View Related

Recognize A Series Of Dates As A Particular Week In The Year

Nov 12, 2008

My intentions are for Excel to recognize a series of dates as a particular week in the year. For example: 12/28/2008 thru 1/3/2009 equals Week 1, 1/4/2009 thru 1/10/09 equals Week 2.

I cannot for the life of me calculate a working formula.

View 7 Replies View Related

Calculate Number Of Week And Days Between Two Dates?

Sep 28, 2011

Any example of counting the # weeks/days between two dates?

View 1 Replies View Related

VBA - Changing Dates According To A Week Before Today Date

Sep 11, 2013

So I have this sheet template to copy for various other sheets, and on A3-A1000, they contain dates from August 1st 2013 to whenever. Starting with A3 as August 1st. The problem is now, it's September 10th, and I would like A3 to be a week before September 10th. Then A4 would be September 11th. And so on and so forth. The dates also must only consist of weekdays and the dates must be hard coded. Is this possible? I have the simple code for copying over the spreadsheet, but I don't know the rest.

Code:
Sub Submit()

Sheets("Client Name").Copy after:=Sheets(Sheets.Count)
ActiveSheet.name = Sheets("Control").Range("C19").Value

View 1 Replies View Related

Count Numerical Day In A Range Of Dates - Not Day Of Week

Jul 8, 2014

I want to find the number of times the 23rd happens between a range of dates.

Let's say I invoice a customer on 5/23/12 (Column C) and I've sent an invoice every month on the 23rd. I want to count how many invoices I've sent during the past few months. I need a formula which tells me how many times the 23rd of the month happens between 5/1/12 (in column A) and 12/15/12 (in column B).

I thought it might be =COUNTIFS(A1:B1,DAY(C1)) but that formula is for counting cells in a range.

I found formulas for counting the specific day of the week (like Tuesday) and for counting the number of cells containing a number, but not this.

View 1 Replies View Related

Counting Dates That Fall In A Specific Week Of The Month

Feb 2, 2009

Please see the attached xls file so see what I am referring to.

I have shipments that are going to different destinations (rotterdam, austria, london, etc.)

I would like to count the arrival dates in column H that fall under each week's span, but ONLY IF its corresponding value in column F is 'rotterdam'.

Column C contains the ideal numbers that I would like column B's formula to return. I plan on doing this for the entire year, but if someone can some up with a formula, I might be able to modify it for the rest.

Note: This is only an example spreadsheet, I am going to be referencing an external file with much more information on it.

View 6 Replies View Related

Finding All Dates In A Column That Are In The Range Today To A Week From Now

Sep 21, 2008

Im trying to search a column (A), that has a list of dates (not in order), for the row in which the dates are equal to or greater than today and less than or equal to a week from today. I then want the information contained in the rows with these dates to be transferred to another sheet and ordered by date.

View 13 Replies View Related

Auto Fill Week Dates To Match Weekday And Month

Nov 18, 2013

How do I auto fill a series of 2014 dates in the row below the weekdays? I have a row C5 that has a series of auto fill weekdays successfully for 2014. I can't seem to auto fill the weekdates in the row below. I have to make manual adjustments for each Monday, and for the correct month ends, etc.

View 8 Replies View Related

Subtract Two Dates To Get Number Of Week Days - Networkdays Does Not Work

Dec 10, 2013

I am trying to find a formula that will return the number of week days between two dates. My specific situation is that my job sets up work orders (WO) to be completed by our staff. We have 3 dates - the date the WO was created, the date the WO is due to be completed, and the date the WO was actually completed.

I would like to subtract the Complete date from the Due date. Generally, this should always equal zero because our staff should be completing WOs on the due date! But obviously that doesn't always happen. There are times that they complete them late, and times they complete them early (yay!).

The problem with NETWORKDAYS is that even when they are completed on time, the result is 1. This formula counts instead of subtracts. I adjusted the formula to =NETWORKDAYS(A3,A4)-1 which works fine for those WOs completed on time or completed late. But for those completed early, it adds (or subtracts, really) 2 days. So for a WO completed a day early, instead of it showing -1, it shows -3. I've attached an example of WOs and the NETWORKDAYS formula I've used so you can see.

Subtract Days.xls

I'm really looking for something that will subtract week days, not count them.

View 3 Replies View Related

Calculating Number Late Last Week From Multiple Dates / Date Sets

Jul 2, 2014

I am putting together a simple table to display current week's data vs previous weeks. The current week's data is drawn from a status chart which changes frequently. The constant change is fine for 'Current' as I only want the current data displayed.

The problem I am having is calculating the number of late jobs that existed during the previous week.

The status log has a due date which is compared to the current date to determine 'on time' status for the current week.
Due dates are reissued regularly so I can't use

=COUNTIF(RANGE,WEEKNUM(NOW()-1)) to return data about last week from my status chart.

I have available a 'Movement Log' (in the workbook but a separate worksheet) which tracks the changes in the due date field, but I'm not sure how to integrate that data to calculate the # of jobs that were running late from the last week.

My thought is that I need to perform a count of the # of late based on a comparison of 'due date' to 'date of the last day of last week' with a way to insert the "old due date" from the movement log to replace what is shown in the status log if necessary.

Movement Log.JPG

Status Chart.JPG

View 1 Replies View Related

VBA - Finding And Counting Unique Dates And Days Of Week Within Date Range

Feb 11, 2013

Within a user entered range of two dates, I would like to identify the individual calendar date(s) and count the number of Mondays which fall within the specified date range.I will eventually be using the same "Monday" code to find the same data for every day of the week within the dates ranges, but I figured I'd start with Mondays and build from there.

For Example: Date range 1/1/2013 - 1/15/2013 (date ranges could potentially encompass a full business quarter) Within the range, list each of the dates as dates. (used for comparative counting purposes elsewhere in the document)Count the number of Mons, Tues, Weds, Thurs, Fris, and Sats within the date range.Based on the example date ranges above; Mons = 2, Tues through Sats = 3 each.

View 2 Replies View Related

Auto Open Macro To Find Correct Week Tab & Day/date In 52 Week Worksheets

Jan 19, 2010

I am new to VBA & not sure of the full understanding of code copied from a workbook which worked on the same principle but with Monthly (12) tabs. I thought if modified to show weeks, the macro would be able to locate the current week tab & day/date within - but upon opening, the cell stops at WK19 & column O - rather than WK43, Column N (which changes daily).

Sub Auto_Open()
week(1) = "WK1"
week(2) = "WK2"
week(3) = "WK3"
week(4) = "WK4"
week(5) = "WK5"
week(6) = "WK6"
week(7) = "WK7"
week(8) = "WK8"
week(9) = "WK9"
week(10) = "WK10"
week(11) = "WK11"
week(12) = "WK12"
week(13) = "WK13"
week(14) = "WK14"
week(15) = "WK15"
week(16) = "WK16"
week(17) = "WK17"
week(18) = "WK18"
week(19) = "WK19"
week(20) = "WK20"
week(21) = "WK21"
week(22) = "WK22"
week(23) = "WK23"
week(24) = "WK24"......................................

View 9 Replies View Related

Auto-updating Formula For Week Over Week Change?

Dec 11, 2013

I was wondering if there's a way to add a formula to calculate week over week % change automatically every week when I enter in new data. see the attached excel file for reference.

What I would like to have is the ability for the formulas in c5 and f5 to be able to auto-update to the newest week and the previous week's data instead of manually having to update it each week. So if I were to add a new row with data for week beginning 12/2, the formula in c5 and f5 would automatically update to calculate the week over week variance. I tried researching prior to asking the question on this forum, and I think it may be possible to do it using the index match function, but I'm not sure how to apply it in this case.

View 3 Replies View Related

Delete And Insert Record Week On Week

Aug 6, 2008

I have a comparison model that looks at two weeks of data. I am trying to get around the deletion and insertion of records week on week. With the code below, I can currently find and correct the deletions and insertions to the list, and then resort the list so that the comparison will work.

Sub CheckForNewProjsRemovedProjects()
Dim MyCell As Range, oCell As Range, NewCell As Range
Dim Rng1 As Range
Set Rng1 = Range("A1:A" & Range("A" & Rows.Count).End(xlUp).Row)
' Columns("B:B").Select
Range("B1:B" & Range("B" & Rows.Count).End(xlUp).Row).AdvancedFilter Action:=xlFilterCopy, CopyToRange:=Range( _
"C1"), Unique:=True
For Each oCell In Rng1
For Each MyCell In Range("C1:C" & Range("C" & Rows.Count).End(xlUp).Row)
If MyCell.Value = oCell.Value Then................

View 9 Replies View Related

Week Number Caluclating Hours For Week

Mar 6, 2010

I have a running time sheet daily. It has 2 columns for Labor and 2 columns for travel
i.e. travel From / To 1300-1400 calculate 1 hour then travel home 1600-1700 1 hour this is calculated by the date entry 01/02/10 I have another calculation that tracks by the date i.e. 01/02/10 then Next job which all works fine.

The problem becomes how do I calculate a weekly total labor and travel by the date So added another column called weekly hour’s labor and use the Weeknum to determine which week is which day/date so the first Monday in January 2010 is week 2

2 problems
Having many multiple day / date entries are the same date x 7 days Monday –Sunday
(Relies on the date entered and the weeknum) 01/03/10 each line is complete however the dates carry over as does the time

When trying to calculate each row x 3 same date time then the value will be incorrect I need to calculate
Say 9.5 hour labor from the date 01/03/10 not 28.5 hours and then calculate the total weekly hours
01/03/10, 9.5 hours labor, 3 hours travel
01/03/10, 9.5 hours labor, 3 hours travel
01/03/10, 9.5 hours labor, 3 hours travel

i do have work and travel times for each job on the same line (separate columns) but I display the total here by date to summarize the totals
i have tried sum products and sumif to avail. I am using Windows XP SP2 with MS Office 2007

how do i calculate weekly hours by date and weeknum ?

Total Work per day

Total Travel per day

Daily....................

View 9 Replies View Related

Formula To Tell When Its Week 1 Or Week 2 Of A Any Given Month

Jun 16, 2014

I'm trying to write a formula that will tell me when its week one or week two, week three and week 4 based on a given date of any month.

I'm using weekday formula but no luck.

View 6 Replies View Related

Comparing Files From Week To Week

Feb 5, 2009

I have to download a report every week and have been manually checking the report weekly for changes.

View 5 Replies View Related