I am trying to get a formula that will give me the number of days remaining in the week. I have a formaula for number of days until the end of the month and number of days until the end of the quarter, but just need the week.
So if the formula was run today it would show 4 as the result.
When setting up a Direct Debit There are 3 options, the 7th, 17th and 27th. I've put these into a drop down list. I need this list to be slightly dynamic. I must allow 10 working days from the date of the arrangment before I can apply the DD.
To explain further. If someone were to want to set up a DD and spoke to me today. If they then requested the DD be taken on the 7th, I wouldn't be able to set it up until the 7th of December as 10 working days are required. I'd like the list to reflect this. I can do it in OO with a simple if / switch but excel is a strange creature and I'm not sure how to approach the problem.
From that I think I also need to calculate the number of weeks remaining in the current financial year. I think I should be able to do this by using the Today() function and some maths.
I'm basically looking for a forumla that will count each employees total scheduled work days for the month inserted and then depening upon the day it is will show how many days the employee has left to work for the month.
I am trying to find a formula that will return the number of week days between two dates. My specific situation is that my job sets up work orders (WO) to be completed by our staff. We have 3 dates - the date the WO was created, the date the WO is due to be completed, and the date the WO was actually completed.
I would like to subtract the Complete date from the Due date. Generally, this should always equal zero because our staff should be completing WOs on the due date! But obviously that doesn't always happen. There are times that they complete them late, and times they complete them early (yay!).
The problem with NETWORKDAYS is that even when they are completed on time, the result is 1. This formula counts instead of subtracts. I adjusted the formula to =NETWORKDAYS(A3,A4)-1 which works fine for those WOs completed on time or completed late. But for those completed early, it adds (or subtracts, really) 2 days. So for a WO completed a day early, instead of it showing -1, it shows -3. I've attached an example of WOs and the NETWORKDAYS formula I've used so you can see.
Subtract Days.xls
I'm really looking for something that will subtract week days, not count them.
How to determine how many days are remaining in the quarter after I provide it a specific date. Ultimately I am trying to build something where if I enter a date it will break down how much it will contribute for the remaining current quarter and for one full year (on a quarterly basis).
For example lets say I buy gumball machine today and I know that it will contribute X dollars for 2009 and X+1 dollars in 2010. I would like to break it down quarterly and have it say - you will get X for the rest of the quarter in 2009 and X for each quarter in 2010.
I have a running time sheet daily. It has 2 columns for Labor and 2 columns for travel i.e. travel From / To 1300-1400 calculate 1 hour then travel home 1600-1700 1 hour this is calculated by the date entry 01/02/10 I have another calculation that tracks by the date i.e. 01/02/10 then Next job which all works fine.
The problem becomes how do I calculate a weekly total labor and travel by the date So added another column called weekly hour’s labor and use the Weeknum to determine which week is which day/date so the first Monday in January 2010 is week 2
2 problems Having many multiple day / date entries are the same date x 7 days Monday –Sunday (Relies on the date entered and the weeknum) 01/03/10 each line is complete however the dates carry over as does the time
When trying to calculate each row x 3 same date time then the value will be incorrect I need to calculate Say 9.5 hour labor from the date 01/03/10 not 28.5 hours and then calculate the total weekly hours 01/03/10, 9.5 hours labor, 3 hours travel 01/03/10, 9.5 hours labor, 3 hours travel 01/03/10, 9.5 hours labor, 3 hours travel
i do have work and travel times for each job on the same line (separate columns) but I display the total here by date to summarize the totals i have tried sum products and sumif to avail. I am using Windows XP SP2 with MS Office 2007
how do i calculate weekly hours by date and weeknum ?
Any 'date' or 'day' formula that will automatically insert days of the week in a column? I am attaching a sample.
I want to be able to use a drop-down menu to insert a day of the week (e.g.: Sunday) in cell B2 and have the succeeding days (Mon, Tues,Wed, Thurs, Fri, Sat) populate cells C2~H2 in sequence.....
Column A Name of the company Column B Date Column C Day Column D Week of the Year Column E High Price Column F Low Price
My requirement is I need the average high price for the first three days of the week i.e Mon, Tue, Wed in Column I and average Low Price for the remaining days is Thu, Fri, Sat , Sun in Column J.
If in some case any day is missing then average high / Low price for the next two days is to be calculated.
I had a column of text and numbers in col A; day of the week and date (taken from a web scrape, so have no control over how they are imported), such as in the following example. Additionally i have put a column of one's beside it in col B, and then summed them in col C.
If i parse the text from the numbers, and then use a filter to remove Saturdays and Sundays, the sum total of col B will still remain the same. What i need is a method to totally delete or neglect Saturdays and Sundays so that the sum would equal 10 for example. Note that the data is updated daily, so in A1 today will be Friday 16/08/2013, but A1 tomorrow will be Saturday 17/08/2013. Also note that i have used 1's in my example, but that is just for explanation purposes, the actual data is varied.
I have just spent the last two days making this spreadsheet only to realize that weekend data is totally messing up my calculations.
Although the date formatting contains the date, ie Thursday, 18 October 2007, when I try to use a contains filter it wont recognise the text of the day I want to filter.
I have a production schedule with start and finish dates for each project. To the right of this I have a matrix with "week starting" dates. What I am looking for is a formula that will indicate how many days in each week the project will take. Below are the cells filled in correctly. However, I did this manually. Any idea of a formula? I'm pretty new to this.
WEEK STARTINGSTARTFINISHUNITS PER DAY9/1/089/8/089/15/089/22/089/29/089/10/089/24/0813.4503530
I am trying to fill a row with abbreviated days of the week. example type Wed in cell A1 and cells B1 through Z1 change to the appropriate day Thu, Fri, Sat etc. I know how to do it with the fill off the menu but want to be able to change Wed to Thu and the same cells will change.
I currently am trying to refine some spreadsheets at work (hospital setting). The type of files im working with are medication sheets where on the left it states the medication and to the right of it, the cells have the days of the month(1-31) but I need them to change depending on the day they come into our facility. Above the numbers i would also like it to say the day of week with the first initial (M, T, W, T, F, S, S) in the cells are the top. It is something that we have to make for each day it it gets really annoying and is a waste of time moving the dates over for every day. find a way where I can open the file and the numbers and letters are all in the right place without having to change it for the day that the patients are coming in.
I have created a excel file which stores attendance for my employees.
The format is like
Select month in one cell select year in other cell
And from cell e8 to ai8 i have nos (1-31) represent no of days in a month:
a8 - 1 b8 - 2 c8 - 3 d8 - 4 like wise till ai8
Now I want a calender where user need to select the YEAR, and then MONTH and based on the above selection both days as well as date (not the month and year) should be displayed.
I am currently using this formula "=IF(ISERROR(--(COLUMNS($E8:$E$8) & "-"&$C$2)),"",COLUMNS($E8:$E$8))" for date and your vb code to hide the cells depending on days of months.
I need something like this
sun mon tue wed thur fri sat sun mon 1 2 3 4 5 6 7 8 9
wkNumber = DatePart("ww", Now(), vbMonday, vbFirstFourDays) But also i would like to have a dynamic array that will give me the dates of this week Currently i do that using vlookup in a table stored in my personal.xls but that is no longer possible as i have to distribute my macro and i no longer have that possibility.
I have a Timesheet where I am trying to get Saturday and Sunday to auto fill with a certain color whenever the month is changed. The spreadsheet is setup so that if the month is changed in a specified cell, then the dates of that month auto fill down a specified column. I would like Saturday's and Sunday's to be a certain color without having to manually color fill them every time the month is changed. Is there a formula or macro for this. I have tried setting up conditional formatting but I don't know how to get the color to follow Sat&Sun. I have attached the spreadsheet.
I am very new to Excel. The date is in column B as Tuesday, 29 April 2014, but I need to format the spreadsheet in such a way that every day of the week is a different colour e.g. Tuesdays are Blue, Wednesdays will automatically turn pink etc. how will I do that?
I have using the following Formula: =COUNTA(A3:A7,A10:A14,A17:A21,A24:A28,A31:A35) Basically is counts how many week days there are in a particular month. Now I have a cell (B47) that counts how many Bank Holidays are in that month. I am having trouble using the formula then minus B47. I must be missing something really simple.
What I am trying to to is calculate the number of Years, Months, Weeks, and Days from one date to another. So far I can calculate years and months accuretly but I'm having trouble with the days and can't seem to figure out how to do the weeks.
I'm using the formula: =DATEDIF(B1,B2,"y")&" Year(s), "&MOD(DATEDIF(B1,B2,"m"),12)&" Month(s), and "&(MOD(DATEDIF(B1,B2,"d"),365))&" day(s)"
B1 is the current days date B2 is the entered date
What I am getting when I enter the date 9/14/09 with the current date (8/3/06) is 3 years, 1 month and 43 days. when it shoud only be 3 years 1 month and 11 days. Any date I enter the days are not right. I can't seem to figure out what I am doing wrong. Also I'd like to get the weeks to come up also. Such as Start date 8/3/06 Entered date 10/19/09. What I want to see: 3 year(s), 2 month(s), 2 week(s), 2 day(s).
A column (A1:A60) is being progressively filled in with numbers, and occasionally some blank cells are between.
I need a formula to work out the number of the remaining cells (that are yet to be filled in) from the last entry till the last cell (A60) of the column.