Record Employees Sick Days & Holidays
Oct 6, 2007
I have a calender with days in the columns and months in the rows. However I have 3 rows for each month. I'm using text and values combinations in the cells to record data
Example First Sheet
Feb Rows, 11,12&13
Columns C,G Dates 1st to 5th
Therefore 1st of Feb has 3 cells to enter data, ie Basic Hours, Sickness, Holiday
Currently I'm defining a name range for each month, ie DFeb. Currently I'm recording each of the rows into columns in another sheet and the date in the row, by using a Hlookup on the date and a vlookup on the month
ie Second Sheet...............
View 5 Replies
ADVERTISEMENT
Jun 25, 2008
Please see attached spreadsheet on what I am trying to achieve.
In the data tab I have my base data, which is dates across the top and names down the side. I have information in the middle such as 'H8' which means that the person was on holiday for 8 hours on that particular day, and 'S8' which means they were sick for 8 hours on that day.
I want a macro that will rearrange the information in the table and put it into the report format which is in the report sheet.
If you see the spreadsheet you will probably get a better idea of what I am trying to achieve.
View 5 Replies
View Related
May 16, 2014
My aim is to find the end working date for each task, as well as the next working date for the next task. The working days for this employee are only Monday (6hours), Wednesday (6 hours) and Friday (8hours).
 
D
E
F
G
H
 
Start Date
Duration
Completed Days
Remaining Days
End Date
4
5/05/14
3
=IF(TODAY()>=H4, E4,IF(TODAY()
View 3 Replies
View Related
Jan 27, 2010
I’ve tried formulas for this but nothing is working, and was wondering if there was some vba that would do the job
Please find attached a sample sheet of where I’m up to.
I’m trying to calculate when someone goes sick to see whether they are entitled to company sick pay (CSP) Statutory sick pay (SSP) and most people will have waiting days (W D) before qualifying for CSP.
A6:A735 have set dates for two years
D6:D735 have the sick days an employee has taken
B6:B735 Matches the sick date to the date in column A
G2 has how many days entitlement for CSP
H2 has how many waiting days (W D) before CSP can start
In Column C i need CSP, SSP, or W D next to the number 1
And if someone only has 1 day sick they would not qualify for any of the above and I just need “S” in column C.
View 14 Replies
View Related
Jan 8, 2009
I am trying to put a time sheet together that will place the number 8 in a cell when the work "sick" or vacation is in another cell.
For example, if I am out sick on monday, I would like to put "sick" in the cell next to monday and have the number 8 be placed in another place. Then If I am out "sick for three days I would like all of those "sick" days to add up to 24.
View 5 Replies
View Related
Apr 3, 2008
Im trying to count people working during times of the day. They work shifts from 8am to 9pm. I need to know at each 30 minute interval of the day how many are working. IE at 12:00 or say 13:30 I need to know how many are working. I also need to be able to account for people that are sick. IE If a person works during the day I wouldnt count them as sick at night.
Im data is set up like
Column A agent name
Column B agents start time
Column C agents end time
Column D holds two variables either sick or support.
I have found a thread that counts the people working but doesnt account for the sick or support variables. I didnt link that thread as I thought it went against the rule "STATE WHAT YOU WANT TO DO, NOT WHAT YOU THINK YOU NEED TO ACHIEVE IT "
View 9 Replies
View Related
May 13, 2014
1. Find the working days between 15th Nov 09 to 28th
2. Add a column that shows the date after a number of months from today date. The number of months from todays date for each of the country is mentioned in column No. of Months after which revised.
3. Find the date our training will end using excel considering the fact that SAT and SUN are holidays. (Use the date when your training started)
View 2 Replies
View Related
Aug 8, 2014
I want a formula that counts all days of a month "listed in a column" but excluding sunday.
View 14 Replies
View Related
Oct 7, 2011
I need to calculate the number of days between 2 dates including holidays and weekends. That means I cant use NETWORKDAYS as it excludes weekend.
View 9 Replies
View Related
Jul 6, 2012
I'm trying to count the total days between to dates but minus the fed holidays. I have a list of holidays I can ref. I like how the NETWORKDAYS function works but I need to include the weekends.
View 2 Replies
View Related
Dec 29, 2013
I am working on a sheet right now where I want to put the day a certain number of days in the future but I want to skip only Holidays, or days in a list on another part of the sheet, but count the weekend days.
All the formulas and post I have read is about someone wanting to skip weekends too. I did find a workdays formula where you and pick what you want to be considered as the weekend but I just want to skip holidays.
Example:
Day is Dec-31-2013 7 days in the future is Jan-7-2014
I want it to be since Jan 1 is a Holiday the answer will be Jan-8-2014
View 4 Replies
View Related
Jun 21, 2006
I have a date in a cell and need a formula that will calulate the next 4 days excluding weekends and holidays. I have search and found where one can do more complex items but not just a simple formula. I have attached an example.
View 2 Replies
View Related
Jan 2, 2008
way to get a worksheet to display workdays that exclude public holidays? I have used the Workday() function, but this keeps displaying the date over xmas. Is there an easy way to do this?
View 9 Replies
View Related
Jan 23, 2014
I have to dig out data for all employees first entry and last exit for two months. My raw data is in sheet 1 as under:
LAST_NAME
FIRST_NAME
EMPLOYEE
[Code]...
I am using excel 2010
View 8 Replies
View Related
Oct 28, 2009
From another thread I got this formula placed on B5:
=NETWORKDAYS(EOMONTH(B4,-1)+1,EOMONTH(B4,0),Holidays)
his generates the number of working days for that month (regardless of the date on B4) that exclude Holidays listed under the range "Holidays".
I also got this code (Credits to XXXX)
View 4 Replies
View Related
Feb 13, 2013
Im having a hard time creating the formula to calculate the min number of employees to complete a number of jobs that come in each day and need to be finished in 18 days or less.
Data that I have:
Forecast of the number of jobs for 251 days ( jobs range from 10 -80 per day) Each job needs to be finished in 18 days or less we need to staff a fixed number of employees for the whole year each employee can complete 4 jobs per day no weekends
i have excel 2010 and crystal ball
View 1 Replies
View Related
Dec 24, 2011
I have a spreadsheet to record profit or loss on a daily basis. The figure for each day can therefore be positive, negative or zero.
I want to add a column to display the total for the last 7 days (NOT the last 7 calendar days), in which either a profit or a loss was recorded (so excluding any cell that is zero).
I would prefer to add (insert), the column for each day as it comes and the range would obviously vary if the new day's figure was not zero.
View 9 Replies
View Related
Dec 19, 2008
i am trying to find the answer for a value that my change from time to time. the example is dealing with time, a 24 hour period. the cell entry my look lilke.... "SE/10". that is where se = sick time used out of the 24 hour period. so in the example "SE" = 14. but this may change depending on how many hours taken
View 8 Replies
View Related
May 25, 2007
I seek advice on using the value of NOW() as a record ID in an address book program. Question #1: Do Excel developers often use a record ID? Question #2: What record ID schemes are fequently employed besides date/time? I have decided to create an Excel address book as an exercise to increase my knowledge of VBA, and also as a useful application for work.
I realize that a record ID is not essential in Excel in the way that it is essential in Access, but I feel the need to have some unique ID associated with each address, so that I may have different worksheets, with data related to a given Contact, sort and manipulate it, if necessary, but have the record ID as a way to restore the relationship of rows to a given Contact, and also, as a handy way to examine the data in the date/time sequence in which it was entered. I have experimented with the following code, to assure myself that I can access the number returned by the NOW() function, manipulate it as a string, and format in various ways if necessary.
Dim n As Double
n = Now()
sn = Str(n)
p = InStr(sn, ".")
first = Left(sn, (p - 1))
l = Len(sn)
d = l - p
S = Mid(sn, (p + 1), d)....................
View 2 Replies
View Related
Sep 17, 2007
I have been trying to come up with a formula that calculate the number of times one of my employees has taken sick leave. The instances do not mean number of times they have taken a medical leave but the number of instances. For ex: In the month of Sept, my employee takes a medical leave on 1st Sept, then another on 7th Sept and then 3 days of medical leave on 12,13, and 14th Sept. So the total medical leaves is equal to 5, but the number of instances is 3.
The formula should be able to provide a result of 3.
View 9 Replies
View Related
Sep 17, 2007
I have been trying to come up with a formula that helps calculate the number of times one of my employees has taken sick leave. The instances do not mean number of times they have taken a medical leave but the number of instances. For ex: In the month of Sept, my employee takes a medical leave on 1st Sept, then another on 7th Sept and then 3 days of medical leave on 12,13, and 14th Sept. So the total medical leaves is equal to 5, but the number of instances is 3.
The formula should be able to provide a result of 3.
View 9 Replies
View Related
Mar 16, 2014
I am creating an asset management sheet. For the formula I am trying to work out there uses 3 fields : ID, start date, and end date.
What I want to do is be able to show if the ID is duplicated within another record with an overlapping date. So an item is flagged if it is in the list within the same dates as another record. I tried a few countif formulas but with no success.. I may just be approaching the problem incorrectly though.
View 1 Replies
View Related
Dec 19, 2008
I have a series of data that acts upon a traffic light system, i.e. Green, Amber and Red. These variables are posted along row 1 for example and there are 10 columns. Per column I have a tick and cross to answer a question. How can I find out how many ticks were on green days, amber days and red days? I have attached an example.
View 4 Replies
View Related
May 26, 2009
I am looking to create a macro that will create a new sheet when data is added on a summary sheet. Example.
1. Summary sheet called "Variations" contains columns that will contain the information needed for new sheet (Columns A to D)
2. When data is entered on "Variations" sheet: Column B, then macro automatically creates new sheet renamed to e.g. VO1 (Number used on "Variations" tab) and is a copy of "Master" tab.
3. Data entered in Column A to D on "Variations" tab is automatically entered onto new sheet created (e.g VO1). Shown is blue on attached file. Additional data is updated on "VO1" sheet and this then links back to "Variations" tab
View 6 Replies
View Related
Mar 20, 2009
I'm trying to find a macro that will run allowing the user to select a 'starting record number' and a 'finishing record number' when printing.
I have a spreadsheet that feeds from a master list in excel, from over 5000 records.
I need to print the s'sheet with any given indivdual record's information at any given time.
Individual prints are fine. However if I wanted to print from record number 1500 to record number 3000 it would take me all day.
Is there a way I can set up a macro so an option form pops up? allowing selection of "From record" and "to Record" ?
View 13 Replies
View Related
Jan 6, 2007
Im trying to record a macro that will enter a formula in a cell each time I run the macro
Drop the Lowest2:
=IF(ISERROR(AVERAGE((SUM(C5:L5)-MIN(C5:L5)-SMALL(C5:L5,2))/(COUNT(C5:L5)-2))*Scale!$B$2*10),(IF(ISERROR(AVERAGE(C5:L5)*Scale!$B$2*10),"",AVERAGE(C5:L5)*Scale!$B$2*10)),AVERA GE((SUM(C5:L5)-MIN(C5:L5)-SMALL(C5:L5,2))/(COUNT(C5:L5)-2))*Scale!$B$2*10)
Drop Lowest1:
=IF(ISERROR(AVERAGE((SUM(C5:L5)-SMALL(C5:L5,1))/(COUNT(C5:L5)-1))*Scale!$B$2*10),(IF(ISERROR(AVERAGE(C5:L5)*Scale!$B$2*10),"",AVERAGE(C5:L5)*Scale!$B$2*10)),AVERA GE((SUM(C5:L5)-SMALL(C5:L5,1))/(COUNT(C5:L5)-1))*Scale!$B$2*10)
I know I can write the formula in a simpler way, but I was asked to make it like this.
The problem is that when I enter the formula in the cell while recording. I got a message: "Unable to record" so this part can't be recorded
View 14 Replies
View Related
Sep 1, 2009
This problem seemed to revolve around "digital signing" with further macro changes done from a different machine (without the proper certificate). Excel warns of the problem and then "unsigns" the project.
I've got a problem with spreadsheets that I've been working on. Now, when I tell it to record a macro, I get the macro name, shortcut assignment dialog box and then an error "Unable to record." After "Ok"ing that dialog box, the normal recording macro dialog comes up. Also, lo and behold, there will not be a macro recorded.
I've got no protected cells or sheets and it doesn't matter what security level is set. It is a "signed" macro but I can take off the signature and still have the problem. I checked for "Help - About" for deactivated modules and there was none.
View 2 Replies
View Related
Nov 17, 2005
I am using the count function for attendance tracking of Vacation, Personal Time, & Sick Time. (Example: = COUNTIF($F6:$CQ6, "V")
I need to be able to do half days. I have tried many different formulas/ways to incorporate the half day scenario even without using the count function with no success.
View 13 Replies
View Related
Jun 24, 2014
Due to work, I need to creat the captioned file for our company.
View 2 Replies
View Related
May 27, 2012
There are dates in column C and I need to count how many days are coming due within 90 days of each date based on the today() function but do not exceed the 90 days.
Countif Today()+90
View 5 Replies
View Related