Subtract Weekdays From Set Date
Dec 18, 2007
I need a formula which counts back a set number of weekdays from a given date. Eg. I am supplied with a project end date and need to schedule 25 week days prior.
I've searched a can only find formulas for the number of weekdays between 2 dates.
View 4 Replies
ADVERTISEMENT
Aug 30, 2013
If I have a date format 7/1/13 that shows as Jul 13, how can I subtract 1 year from this in the next cell?
View 3 Replies
View Related
Oct 2, 2007
I am looking for a way to count the number of Days after Christmas each year.
For example today is the 1st October hence it is easy to work out the number of days since last Christmas as being =Today()-25/12/2006
How do I have a reoccuring formula that is Today-Christmas each year without having to enter the year of last Christmas so that for example as at 26/12/2007 the answer will be 1 and so it will also be on the 26/12/2008?
View 9 Replies
View Related
May 22, 2009
Is there a way to subract date and time? For example if in cell A1 you have 05/20/09 8:00 am. and in B1 you have 5/21/09 16:00. You want to know the time in between.
View 10 Replies
View Related
Jul 9, 2007
in the attachment I have problems in Cell B4, A9, and B9:
1. Cell B4: if Cell C2 is 25-May-07, then Cell B4 must be 26-Apr-07, if Cell C2 is 25-Apr-07, then Cell B4 must be 26-Mar-07, I did, but it is not working well, mean the format is not applied on that (Cell B4)
2. Cell A9: if Cell B4 is 26-Apr-07, then Cell A9 must contain the day of Cell B4 format (d), like 26...
3. Cell B9: the same as Cell A9, but format must be (ddd)
View 5 Replies
View Related
Apr 18, 2008
A1 contains an entered date (4/18/08). B1 contains an entered number representing months (6). I want C1 to subtract 6 months from 4/18/08 and then show the rounded down date of 10/1/07.
View 9 Replies
View Related
Feb 26, 2014
I am looking for a formula which substract a number of workdays defined in a cell from a date defined i nanother cell. For example I have a date in cell B2: 10.08.2014 - this is the due date for service delivery. In cell C2 there is a number of workdays: 84 - this is the duration for the delivery process. I would like to have a formula calculating in cell D2 the date when the delivery process has to start. The tricky point is that B2 is basicly a range of merged cells B2:B6. As an example I am attaching an exmple sheet.
View 10 Replies
View Related
Nov 9, 2011
I'm trying to calculate a date in the future and subtract one day.
The date entered in N38 is 11/09/11.
The term entered in months in C8 is 24.
I want N39 to return the date 24 months in the future minus one day.
So N39 should dispay 11/08/13
How the heck do I do that?
View 5 Replies
View Related
Oct 31, 2008
I am trying to add/subtract dates and times to return one sum; but I only want to count the work week (5 days M-F) and work day (8 hrs.) 8am- 4pm. This is to compute the actual turn around time for a certain process.
i.e.:
Date ReceivedTime ReceivedDate ApprovedTime Approved10/1/20081:00 PM10/15/20089:00 AM
The total hours this process should equate to is: 9days and 6hours.
way to achieve this sum?
View 9 Replies
View Related
Nov 14, 2006
Need to find out exact date. if I insert 32.5 (32 years 5 months ) in particular cell. my output shld be 10 june 1974 or 10/06/1974. I want to find back date...
View 4 Replies
View Related
Jun 20, 2008
I am trying to subtract 8 hours from a date/time. What I need to do is to capture that lead time using only weekdays, and working hours of 8am-5pm.
For example:
Date/Time
6/23/2008 9:18AM (Monday)
Subtracting 8 hours from this scenario would give me
6/20/2008 10:18AM (friday)
View 3 Replies
View Related
Apr 25, 2014
I'm in Excel 2010, and the cell with the date I want to work from is G22e?
EDIT: I'm trying to get the difference of the (date+12 months)-TODAY() to appear in months and days. (I also meant H22 not G22)
Here's the latest thing I tried (that doesn't work):
=IF(DATEDIF(H22,TODAY(),"y")>=1,DATEDIF(H22,TODAY(),"y")&" yrs, "&DATEDIF(H22,TODAY(),"ym")&" mths, "&DATEDIF(H22,TODAY(),"md")&" days",IF(DATEDIF(H22,TODAY(),"ym")>=1,DATEDIF(H22,TODAY(),"ym")&" mths, "&DATEDIF(H22,TODAY(),"md")&" days",DATEDIF(H22,TODAY(),"md")&" days"))
EDIT #2: I guess I should probably note that the date in H22 is the result of another formula
=EDATE(G22,12)
View 7 Replies
View Related
Sep 28, 2009
=Date(year(today()),month(today()),A1) works great, However I need the formula to subtract 1 month if the value returned would be greater than today's date.
View 2 Replies
View Related
Jan 4, 2014
How I can subtract a year when I formulate based on if the current month is January.
Such as Current month = January 2014, I would require the cell to populate December 2013, any other month would return the current year value.
I have currently tried { =DATE(YEAR(A3)-1,MONTH(A3),DAY(A3)) } whereas cell A3 uses NOW() function formatted to MMMM, but it changes for every month.
View 9 Replies
View Related
May 2, 2014
I have a cells with a date and time in each cell. I want to subtract the number of days between the cells only. Is there a way to do that with the time in the cell? If not, how do I remove the time in each cell?
View 5 Replies
View Related
Apr 24, 2013
Using one spreadsheet with three date columns and two columns counting days.
If there is a value in Resolution date, then Column N is blank
If there is no value in Submit date and Resolution date, then Column N is blank
If there is no value in Resolution date, and there is a value in Submit date, subtract Submit date from todays date to show how many days it has been pending approval
Created on = J4
Submitted on = K4
Resolution Date = L4
Days to Approve = M4 I've got that formula =IF(L4="","",L4-K4)
Days Pending Approval= N4 (cell with formula)
If Resoultion Date L4 has a value, return blank
If Submit on K4 and Resoultion date L4 are blank, return blank
If Resolution date L4 is blank, and Submit on K4 has a value, subtract Todays date from Submit on K4 to show Days Pending Approval
Cell J4______Cell K4______Cell L4__________Cell M4__________Cell N4
Created on___Submit On___Resolution Date___Days to Approve___Days Pending Approval
4/5/13_______blank______Blank____________Blank___________Blank
4/5/13_______4/5/13_____4/7/13___________2_______________Blank
4/5/13_______4/5/13_____Blank____________Blank___________()Today-K4
View 3 Replies
View Related
Feb 2, 2014
I need cell (O4) to display days overdue or days remaining on an assigned task based on subtracting due date (M4) from todays date, but only perform days subtraction function if (M4) is not blank and only if task complete cell (N4) is less than 100.
Have the conditional blank cell figured out, but nesting another condition for the less than 100 complete cell. So in other words, I don't want cell (O4) to subtract days and display any error, irrelevant data if there is not any due date entered or the task is entered as complete...
View 3 Replies
View Related
Jul 20, 2007
I want a forumal to do in excel.
Assuming that a workday is from 8:30am to 5:00pm. (also need to not calcualte Saturday and Sunday but this example doesn't show it).
Wednesday, 7/18/07 at 4:00pm (minus) Friday, 7/20/07 at 9:00am (should equal) 10 hours or 1 day, 1 hour and 30 minutes.
Basically what I want to do it determine how much work time has elapsed from the time a message was left on voicemail to the time that someone picks that message up. We only want to assume that a message can be retrieved duruing business hours but a message can be left at anytime!
View 10 Replies
View Related
Oct 13, 2007
How can I work out the following in hours an minutes: -
Cell A1 = 12th May 2007 20:00
Cell B1 - 14th May 2007 14:30
or should I put the dates and times in seperate cells? I would like the answer to show 42 hours 30 minutes
View 3 Replies
View Related
Dec 13, 2011
I'm trying to write a function that takes a date in format YYYYMM and adds/subtracts a number of months.
for example: newDate(YYYYMM,numMonths)
newDate(201109,5) would give 201202
newDate(201102,-4) would give 201010
I was thinking i could use the left/right function to retrieve the month and year ........
View 7 Replies
View Related
Oct 24, 2007
I have a column of values resulting from subtracting a static date and time from the current date and time.
This means it is constantly updating, which makes it impossible to sort.
All my work depends on sorting those values, though.
View 12 Replies
View Related
Apr 28, 2012
I am trying to subtract an amount from a cell until it reaches 0, then move and subtract from the next amount, and so on.
AmountFixed BudgetedResult53.50Subtracted 5 tell it hit zero1.30Subtracted remaining amount until zero43.8Subtracted remaining amount until zero3.8 was left over without hitting zero is good. Is there formula for this?
View 6 Replies
View Related
Aug 28, 2012
I have a code that I have put in the ThisWorkbook section, and I thought it should work - but nothing happens....
Code:
Sub FirstSub()
Application.OnTime TimeValue(Sheets("SetUp").Range("G1").Text), "SecondSub"
ResetTime = Now() + 1
Application.OnTime ResetTime, "FirstSub"
End Sub
Sub SecondSub()
If Weekday(Now()) > 2 And Weekday(Now()) < 7 Then Call CreatePDF
End Sub
It's supposed to call a sub called CreatePDF.
View 9 Replies
View Related
Nov 12, 2006
I need a function that recognizes the first and last weekdays (M-F) of the month. I would prefer to do this with a function and not VBA.
View 9 Replies
View Related
Aug 15, 2007
I have a sheet with alle days an date in one month
in column "A" the date (format: TTTT TT.MM.JJ)
in column "B" I have the worked hours
Below in the sheet I would to have to sums
each one for weekdays and weekends,
because my guys get more money if they work on a saturday or sunday.
I have been playing with the formulars
=sumif(weekdays(....., but cant geht the right thing
View 9 Replies
View Related
Jan 3, 2008
I would like to have a spreadsheet where everyday of the month dislpays automatically
such as
01/01/08 in A1
01/02/08 in A2
etc.
According to a cell name Account Period (eg 200801)
But I don t want week end days to be displayed. In the same excel document, I have a sheet with all non working days and week end for 2008 and another sheet.
View 5 Replies
View Related
May 8, 2012
I need to run job between 4 July 2012 and 1 September 2012 but only Monday through Friday.
I have used weekdays() to find the name of dates between these two dates but need to narrow to Monday through Fridays.
View 1 Replies
View Related
Jul 4, 2012
I have done a V-lookup that auto populates my project report doc with different lead times/dates depending on the product selected. Problem I have it that the dates being pulled through are for all calendar dates and not just working week days.
I know you can select a selection of dates and fill as week days however all of the dates on my primary sheet either have the project start date minus lead time formula or the vlook up formula in it. Filling week days overwrites any of this.
View 3 Replies
View Related
Nov 20, 2012
TWO more days to turkey day. 3 more to BF --- yaaaaak! Anyway,
Iam trying to display only 3 workdays in each of three cells. Days displayed depend on today's date.
I am usinf the following but it displays SAT and SUN.
Q3 = today's date
=UPPER(TEXT(Q3+2,"DDDD")) displays THURSDAY
=UPPER(TEXT(Q3+3,"DDDD")) displays FRIDAY
=UPPER(TEXT(Q3+4,"DDDD")) displays SATURDAY -- would like it to display MONDAY
Q3 changes to reflect today's date
therefore this would display:
=UPPER(TEXT(Q3+2,"DDDD")) displays THURSDAY
=UPPER(TEXT(Q3+3,"DDDD")) displays FRIDAY
=UPPER(TEXT(Q3+4,"DDDD")) displays MONDAY
In other words I want to display only the week days in these 3 cells.
I tried:
=TEXT(WEEKDAY(INDIRECT("Q3")),"dddd")
but "Q3 + 2" will not work
the end result desired:
MONDAY
TUESDAY
WEDNESDAY
TUESDAY
WEDNESDAY
THURSDAY
[Code] ......
View 3 Replies
View Related
Dec 13, 2012
I have a column of dates in Col B that I need to update every day. I want a macro that will automatically fill down the date in the column, but it has to be a working day. So far I have this:
Code:
Range("B3").End(xlDown).Select
Selection.AutoFill Destination:=Range("B3:B" & lastrow), Type:=xlFillWeekdays
However this doesn't work. Obviously the range will need to be dynamic (i.e. it will change from day to day as new dates are added).