So I have a cycle time formula; Start Date to Completion Date, if the task is not complete the completion date field is blank. In this case the cycle time is listed as a negative 5 digit value. The networkdays formula takes into consideration weekends and holidays.How can this field be left blank rather than the negative value?
I have data in column C which is the date and time
Data is: 16/06/2014 09:47:14 Cells are formatted as dd/mm/yyyy" "hh:mm:ss
Column H has another date and time based on service level agreements
Data is 17/06/2014 09:47:14 Cells are formatted as dd/mm/yyyy" "hh:mm:ss
I need to add 3 workdays to the 1st value so it returns 19/06/2014 09:47:14
I've used the following formula =WORKDAY(C2,3) and it returns the correct date but time shows as 00:00:00. Is there way I can pick up the time from Cell C2?
I have a small range that i need to copy to another sheet for each working day of a time period(01/01/2014-30/04/2014) excluding weekends and holidays, adding the date in the first column of the new sheet.
I would like to find out if a job took more than 24 hour cycle time (eg. 6:00 am to 5:59:59 AM next day). data:
A1 = received date & time (format "m/d/yyyy h:mm") B1 = completed date & time (format "m/d/yyyy h:mm")
my formula is '=if(B1-A1>"24:00"+0,"Yes","No"). The problem with the formula is that it doesnt exclude weekends nor public holidays. I couldnt formulate a solution using networkdays function......
I need to determine a formula which will allow me to calculate a future date based upon a current date with varying time periods.
For example:
I have a bill which is paid on the 15th and last business day of each month. I would like to be able to see the next due date regardless of what day of the week it is.
I have a bill which is paid every other Tuesday. I would like to know the next due date without having to enter +14 for every due date in the future. In other words, it is preferable to be able to open the spreadsheet and automatically see the next due date, not use autofill to repeatedly add +14 to a previous date which would limit the # of future due dates that could be calculated.
I have a bill which is paid on the last business day of each month, not the last Friday of each month. I would need excel to return a value for the last day of the month which = Monday-Friday, regardless of what day of the week it may be as long as it isn't Saturday or Sunday(holiday exclusion would be nice but not required).
I have a userform that captures dates and records them to another excel workbook so we can analyse the data. I have one last part to finalise; When a date is added to the "daterecievedtxtbox" I would like a formula to be offset to the end of the spreadsheet, that will take this date and add 3 working days to it. Then I can add in some formulas later to flag them when the date passes the 3 working days.
At the moment I have this:
[Code] ....
Which adds 3 days to this txtbox and writes it to the sheet that I have defined. I would like to know if there is a function that I can use to add 3 WORKING days to this, excluding saturday and sunday.
I would like to know how to get the number of working days in a month based on the date in B4 which is formatted as "mmmm". So if B4 was October the result would be 22 regardless of the actual date in B4.
I also have a named range "Holidays" for UK bank holidays (ready for December) that I would like included within the formula.
I need a way to calculate the number of workdays, Saturdays and Sundays in a month.
In my model, the client can choose to work on Saturdays and/or Sundays.I need someway to show that a given month (e.g. June 2014) has some # of workdays, and some # of Saturdays and some # of Sundays.I can do this on three separate rows. eg.
I am using excel 2003 and I am trying to subtract 20 days from the date in cell A3 in order to give me a date for me to order materials. However all I get is #NAME? in the cell.
I have an excel file I am working on with a due date column. I have already created 2 conditional formatting.
1. if cell value is less than today's date then format the cell red 2. if cell value equals today's date then format the cell orange
I need to create two more conditional format....one where it looks at today's date and if the due date date cell is within 1-3 business days from today's date then I want the cell format to turn yellow and I need a last conditional format to look at today's date again and if the due date cell is within 4 -5 business days from today's date then I want the cell format to turn green. Can these two additional conditional formats be done?
I am trying to map the total networkdays across the months of the year for a list of contracts with variable start and end dates.
Example of the results I'm after:
Contract StartDate EndDate January February March etc. Contract1 15 Jan 07 13 Jul 07 13 20 20 Contract2 5 Feb 07 2 Mar 07 0 18 2
I assume that the add-in NETWORKDAYS function is involved (and I'm ordinarily comfortable with using this function with only two dates and my named range of holiday dates), but I can't seem to figure out how to use it in this more complicated way. My own extensive struggles with it have led to ridiculously long and nested formulas that even I didn't understand after a few days away from them. I've searched the posts and seen questions similar to mine, but not close enough to give me a solution.
I need to calculate the difference between two work days to understand how many days late we missed a due date. The NETWORKDAYS formula gives me the COUNT of the workdays, but I need the difference.
Example 1: Expected Due date: 3/3/08 Actual Due date: 3/3/08
NETWORKDAYS for the dates above gives me the value of 1, but for my needs I need the resulting value to be zero.
Example 2: Expected Due date: 3/3/08 Actual Due date: 3/5/08
NETWORKDAYS for example 2 provides a value of -3 (days late), but in reality it's only -2 (days late)
I am looking for a formula which substract a number of workdays defined in a cell from a date defined i nanother cell. For example I have a date in cell B2: 10.08.2014 - this is the due date for service delivery. In cell C2 there is a number of workdays: 84 - this is the duration for the delivery process. I would like to have a formula calculating in cell D2 the date when the delivery process has to start. The tricky point is that B2 is basicly a range of merged cells B2:B6. As an example I am attaching an exmple sheet.
I would require a formula to count the amount of workdays between cell a1 and cell a2. Assume formula is in celll a3 and both a1 and a2 are date formated.
The intent is to calculate the completion date against the assigned date as follows:
G13 - Typically the assign date but sometimes can be blank because someone forgets or doesn't bother to insert
For this example, let's say: 12/17/12
H13 - Completion date
For this example, let's say: 12/20/12
I'm expecting a result of '3' for 3 days
The first half of the function is intended to calculate 1 day if G13 is blank or not defined. However, when I have dates in both cells, I'm getting a "false" answer instead of a numerical value that I'm expecting.
In our workplace, we do work weekends & sometimes 7 days a week.
I need a VBA Function, I have a start dates in column A and end dates in column B what I need in column C is the abbreviated days excluding the weekends. For example if I have 11/11/13 in A1 and 11/20/13 in B1 then in C1 I need (including start and end date) Wed, Thu, Fri, Mon, Tue, Wed, Thu, Fri. Another example If I have 11/29/13 in A1and 12/3/13 in B1 then in C1 I need Fri, Mon, Tue.
what was wrong with this formula, an error message comes up saying VALUE, im trying to get the formula to say that - If 2 dates are different then subtract one from the other to get a number of working days, but if the dates are both the same then to -1 from the value as for some reason the value is coming back as 2 when it should be 0?
I need to create a business days calendar consisnting of two columns start_date and end_date. Start_date is today (always a work day), end_date column will have to be start_day +1 day, start_day +2 days, start_day +7 days, start_day +30 days, and so on till + 3600 days. Every end_date must fall on a business day, or the first following business day if it is falls on a WE. Assume I know all holidays for the next 10 years. I could use Workdays or other built in function, the trouble is they all assume Sat and Sun as WE, my WEs are FRI and SAT! I tried to write a UDF but I'm failing miserably with too many ifs and elses,
Get the number of workdays between two dates in a VBA function. I tried simply using the Advanced Toolpak function NETWORKDAYS, but I get the error message "Sub or function not defined". I did reference to atpvbaen.xls in the Tools > References menu, so I don't know why Excel is not recognizing the function.
I used the following function to test it:
Function CalcNetDays(dInitial As Date, dEnd As Date) CalcNetDays = NetworkDays(dInitial, dEnd) End Function
Any reason the function is not working? Also, I need to add the holidays to the function. The holidays are listed on a worksheet column. Do I simply add the range to the function, like below?
How to add 2 "working days" to a date, including Saturdays as work days, and excluding holidays and Sundays? Similar to: = WORKDAY ("01/02/2008", 2, 39451) But instead of resulting in Mon Jan 7th, the answer should be Sat Jan 5th. (39451 is Fri Jan 4th.)
I've recorded a Macro that goes through multiple spreadsheets and refreshes the pivot tables in the sheets. I would like the Macro to run without it actually showing it go to each sheet and showing the pivot table updating. Bascially I would like the spreadsheet to remain on the first sheet while it's working with all the spreadsheet in the workbook when the macro is running.
I have a table, 2 columns by 10 rows (A1:B10). The table values are the result of calculations (imagine they are random). These calculations are performed repetitively for some specified number of repetitions (let's say 10 iterations). (e.g. all of the table values change with each iteration until the 10 iterations are complete. With each iteration all of the values in the table change). At the completion of the 10 iterations (one full cycle) I want to know the minimum and maximum calculate value as the 10 iteration cycle was performed.
To simplify; the table changes 10 times in one cycle. I want to know the minimum and maximum values attained in the cycle.
It is easy to determine the minimum and maximum values of the table for each iteration. It seems the problem would be write some vba code that 1) found the min. and max. 2) save that value 3) find the min and max in the next iteration and compare the old and new values 4) retain the value or replace the min and max values with new values and 5) proceed to the next iteration until the cycle is complete.
I want to combine cells from two adjacent columns in this way: a1 is combined with everything in column b, then a2 is combined with everything in column b, etc. So that I have a1b1, a1b2, a1b3, a1b4, a2b1, a2b2, a2b3, etc.
Is there a formula I can use to determine the number of work days in each week for a given month. The work week would start Sunday, with Friday and Saturday as days off. Each week would be in their own row.
i.e.
January
Week 1: 2 days Week 2: 5 days Week 3: 5 days Week 4: 5 days Week 5: 3 days