Caluclating Business Days
Jun 30, 2006
I am looking to calculate business days - more specifically Monday through Friday. I am not currently worried about holidays or vacations, yet I wouldn't mind including it if I could have a list to "check" from.
I tried previous searches, but found a few functions that I don't have on my computer.
View 6 Replies
ADVERTISEMENT
Dec 4, 2008
I am not able to calculate TAT(Turn around Time) between two dates without taking Off days. Plz help me on this.. File is attatched as per example..
View 6 Replies
View Related
Mar 28, 2008
we have salespeople in all 50 states and each state uses different rules for business days. Some states include Saturday as a business day, some don't, and Alaska uses 5 business days including Saturdays. We are open 7 days a week.
What I am trying to create is a worksheet that has each day of the month going down and in the cells next to it, a column for states that include Saturdays as business days; so a date 3 business days out would appear in the next cell. In the cell after, a date 3 business days out not including Saturdays. And in the last cell for Alaska, a date 5 business days out including Saturday. Of course federal holidays are all excluded.
Something like this:
March w/ Sat w/o Sat Alaska
1 5 5 7
2 5 5 7
3 6 6 8
4 7 7 10
5 8 10 11
Now Vermont has extra holidays certain months so I would have to adjust that in the formula for the middle column during those months.
View 9 Replies
View Related
Feb 18, 2009
I have created a useform in VB which will determine business days. I need help in the coding part.
In my user form I have text box, I have a calender and I have two command buttons, 1 Calculate 2 exit. What i would like to achieve is when i type a number in the txtbox and press cmd button calculate the code will shade the the date in the calender so for example if I type in 10, then the code should shade 13/02/09 on the calender since 13/02/09 is the 10th business day.
View 9 Replies
View Related
Sep 16, 2006
I'm working on a complex A/R aging summary. So Ill have couple of question, but right now I'm trying to have excel automatically keep track of the A/R process. For instance every business day I would like the number of days the Invoice is outstanding to go up by 1. So when I get to work on monday the invoices that have been due for 20 days will now show 21 without me touching it.
View 5 Replies
View Related
Dec 8, 2008
I am looking for a formula that looks at a date and could add business days to it.
for example:
If the date in a field is Monday, 15-dec-08 and my formula is to add 5 Business days (mon-fri) to it not including that date. The desired result would be Monday, 22-dec-08 but my formula gives me 20-dec-08
View 6 Replies
View Related
Jan 1, 1970
It should be deplaying dates of weekly days in Monday, Wednesday and Friday excluding sundays. Or Tuesday, Thursday Saturday excluding Sunday. e.g
Mondays, Wednesdays and Fridays of June
June 1, 2006
June 3, 2006
June 6, 2006
Tuesdays, Thursdays and Saturdays of June
June 2, 2006
June 5, 2006
June 7, 2006
This should be happening after entering any date on the first cell of the List and should accommodate up to 3 months
View 14 Replies
View Related
Dec 24, 2012
Where i want add Business Hours/Days to get the Target Date.
Working hours: 8:00 AM to 19:00 PM
Urgency Type:
ND (Maximum 1 Day 11 hours)
3D (Maximum 3 Day 11 hours)
4D (Maximum 4 Day 11 hours)
5D (Maximum 5 Day 11 hours)
Threshhold - 16:30 PM
Weekends to be Excluded.
Holidays to be Excluded based on Country. Say I have 2 countries India and America, where America has holiday on 12/24/2012 but India does not have holiday on that Day. Hence while calculating Tgt date, India should be calculated normally, for America holiday date need to excluded(There will be a Holiday table based on the countries, not limited to 2 countries).
ex: 1) A ticket opened at 12/26/2012 8:56 AM; Target date will be 12/26/2012 19:00, in this case its 1 day 10:04 hours added to the Opened Time.
2) A ticket opened at 12/26/2012 16:56 PM; Target date will be 12/29/2012 19:00, in this case ticket opened after threshold time of 16:30, Technically ticket should start from next day i.e 12/28/2012 8:00 AM and 1 day 11 hours added to this date.
3) A ticket opened at 12/26/2012 7:56 AM(Before the begin of Working hours); Target date will be 12/26/2012 19:00, in this case its 1 day 11:00 hours added to the Opened Time.
4) A ticket opened at 12/21/2012 17:56 PM(After Threshold time); Target date will be 12/24/2012 19:00, in this case its 1 day 11:00 hours added to the Opened Time. If the above ticket belonged to America, then holiday dates(both 24 & 25) need to be skipped and Tgt date will be 12/27/2012 19:00.
Here is the Sample Data
Country
Ticket
Start Date/ Time
Tgt Date/Time
Expected Tgt Date/ Time
America
ID000123
12/21/2012 18:20
[code]....
I need results to be appear in the "Tgt Date/Time" column. I have also provided results in "Expected Tgt Date/ Time".
View 1 Replies
View Related
Dec 31, 2013
Calculating Number of Business Days Between Two Dates?
View 9 Replies
View Related
Aug 7, 2012
I would like to move columns to the right as the date changes. For example, the top of the column has the current date. Within the column are about 40 rows of data. as the date changes, I would like that column to automatically move to the right and show that column with yesterday's date, and have that data associated along with it moved. I am looking for 6 months of columns to store, with the current date in the first column and subsequently moving right with the previous dates and info.
------------------------------------------------------------------------------------------------
August 7, 2012 | August 6, 2012 | August 5, 2012 | August 4, 2012 | August 3, 2012
------------------------------------------------------------------------------------------------
Accepted Processed Accepted
Rejected Accepted
Processed Processed
...
and so on
View 2 Replies
View Related
Oct 8, 2013
I have a spreadsheet that contains dates in format mm/dd/yyyy. Lets call this Column C(Paydate). In Column A I have a date that needs to be a 2 business days before the paydate. If this date in column A winds up being a Saturday or Sunday, the function needs to return the previous Friday. If the date is any weekday then it should return that weekday
For example:
C1 = 10/18/2013(a Friday) then A1=10/16/2013
C2 = 10/14/2013(a Monday) then A2= 10/11/2013(the previous Friday since 2 days before 10/14/2013 is a Saturday)
C3 = 10/15/2013(a Tuesday) then A3= 10/11/2013(the previous Friday since 2 days before 10/15/2013 is a Sunday)
View 4 Replies
View Related
Feb 11, 2010
I'm documenting the steps of a process with each step accounting for a specific amount of business days. How do I determine the specific business day based on the number of days it takes to complete a process? For example: Start date then 45 business days from that date the next step begins...then 3 business days from that date the following step begins and so on.
View 5 Replies
View Related
Dec 17, 2012
I have columns of dates and I'm looking to automatically highlight dates that are older than 5 business days from today. Is that conditional formatting?
View 3 Replies
View Related
Aug 16, 2009
I need to create a spreadsheet that will calculate the difference between two dates and show the result in days. The complicated part is that weekends (Sat and Sun) need to be ignored and any time after 4:30 pm needs to be treated as the next business day. I have been trying to look at similar questions in forum and use the WORKDAYS function with little success.
Example:
A1- 14/08/09 4:40 p.m.
B1- 17/08/09 9:10 a.m.
I need the answer (B1-A1) to show up as 0. But if the time in A1 was changed to 4:20 p.m. than the answer should be 1 day.
View 5 Replies
View Related
Mar 6, 2010
I have a running time sheet daily. It has 2 columns for Labor and 2 columns for travel
i.e. travel From / To 1300-1400 calculate 1 hour then travel home 1600-1700 1 hour this is calculated by the date entry 01/02/10 I have another calculation that tracks by the date i.e. 01/02/10 then Next job which all works fine.
The problem becomes how do I calculate a weekly total labor and travel by the date So added another column called weekly hour’s labor and use the Weeknum to determine which week is which day/date so the first Monday in January 2010 is week 2
2 problems
Having many multiple day / date entries are the same date x 7 days Monday –Sunday
(Relies on the date entered and the weeknum) 01/03/10 each line is complete however the dates carry over as does the time
When trying to calculate each row x 3 same date time then the value will be incorrect I need to calculate
Say 9.5 hour labor from the date 01/03/10 not 28.5 hours and then calculate the total weekly hours
01/03/10, 9.5 hours labor, 3 hours travel
01/03/10, 9.5 hours labor, 3 hours travel
01/03/10, 9.5 hours labor, 3 hours travel
i do have work and travel times for each job on the same line (separate columns) but I display the total here by date to summarize the totals
i have tried sum products and sumif to avail. I am using Windows XP SP2 with MS Office 2007
how do i calculate weekly hours by date and weeknum ?
Total Work per day
Total Travel per day
Daily....................
View 9 Replies
View Related
Dec 19, 2008
I have a series of data that acts upon a traffic light system, i.e. Green, Amber and Red. These variables are posted along row 1 for example and there are 10 columns. Per column I have a tick and cross to answer a question. How can I find out how many ticks were on green days, amber days and red days? I have attached an example.
View 4 Replies
View Related
May 27, 2012
There are dates in column C and I need to count how many days are coming due within 90 days of each date based on the today() function but do not exceed the 90 days.
Countif Today()+90
View 5 Replies
View Related
Mar 14, 2014
I am making process TAT(Turn Around Time) which required following information. In Excel 2007.
1-Count number of days between two dates where working days are (Sun to Thursday). So required to exclude (Friday,Sat + Holidays)
A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 22
D1-Days between two dates 21
E1 To E10-Holidays
2-Count number of days between two dates where working days are (Sat to Thursday). So required to exclude (Friday + Holidays)
A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 27
D1-Days between two dates 26
E1 To E10-Holidays
Note : Any weekend (off days) dates listed in holidays should not effect the query.
View 9 Replies
View Related
Sep 1, 2007
I'm basically looking for a forumla that will count each employees total scheduled work days for the month inserted and then depening upon the day it is will show how many days the employee has left to work for the month.
View 9 Replies
View Related
Feb 26, 2014
How would I write a function to give me the last ten business dates moving horizontally from today's date with yesterdays date the being the last date? So if A1 is 2/26/14, how would I populate B1-B10 with wanting B10 to be 2/25/14 and moving backwards but only with business dates?
View 3 Replies
View Related
Jan 15, 2009
I have a spreadsheet (attached) containing 3 columns, week commencing (c), week ending (d) and business week (e). The question is can a user enter a date in one cell (b4) and have the next cell (b5) return the corresponding business week, I have come up with a couple of solutions involving hidden columns but was wondering if there is a way to do all of this in one cell.
View 3 Replies
View Related
Mar 31, 2009
I am using the following formula to calculate business hours.
=(NETWORKDAYS(R9,T9)-1)*("17:00"-"08:00")+IF(NETWORKDAYS(R9,T9),MEDIAN(MOD(T9,1),"17:00","08:00"),"17:00")-MEDIAN(NETWORKDAYS(R9,T9)*MOD(R9,1),"17:00","08:00")
The business hours considered here is 8AM - 5PM, Start time in R9 and End time in T9. Now the problem is its calculating the correct value when the days are same, for e.g.,
Condition 1
When I am giving "31 March 2009 15:00:00" as start time (R9) and "31 March 2009 23:00:00" in end time (T9), I am getting the correct value. i.e, "2:00:00"
Condition 2
While giving "31 March 2009 16:00:00" as start time and "01 April 2009 09:00:00" as end time I am getting a value of "1:00:00", actually the value should be "3:00:00".
View 5 Replies
View Related
Jan 30, 2014
create a macro?
I want to add the Last business date in B3 cell just by running a macro.
View 13 Replies
View Related
Feb 13, 2012
My file name constantly changes, it will always be (minus 2 business dates from today)
Now when my macros run it goes between different worksheets so I need to tell it to go to right workbook. I tried below but getting an error 438 'Object doesnt support this property or method'
Code:
Workbooks("file " & Format(WorksheetFunction.WorkDay(Date, -2), "MM DD YYYY") & ".xls").Activate
Sheets("data").Select
View 1 Replies
View Related
Aug 18, 2013
I have the following formula in a cell
=NETWORKDAYS(A2,B2)-(MOD(A2,1)>=MOD(B2,1))
its works off of cells A2 for the start date and cell B2 for the end date and works perfect
I want to use this in code to automatically count business days for all rows. I have tried the following
Dim ressfp,a4,a5
a4 = Worksheets("Master").Range("O" & b).Value 'target comp date
a5 = Worksheets("Master").Range("P" & b).Value 'actual comp date
ressfp =NETWORKDAYS(a4,a5)-(MOD(a4,1)>=MOD(a5,1))
I get an error on the word MOD saying compile error syntax error but cant work out why
i have tried replacing the networkdays formula with the following
=SUM(INT((WEEKDAY(A2-{2,3,4,5,6})+INT(B2)-INT(A2))/7))-(MOD(A2,1)>MOD(B2,1))
but this gives the error that the curly brackets are invalid characters.
View 2 Replies
View Related
Apr 23, 2008
I use this formula at work to calculate business hours from Mon-Fri:
=IF(OR(L10="",L11=""),"",(NETWORKDAYS(L10,L11,$N$2:$N$23)-1)*($Q$3-$Q$2)+IF(OR(ISNUMBER(MATCH(INT(L11),$N$2:$N$23,0)),WEEKDAY(L11,2)>5),$Q$3,MEDIAN(MOD(L11,1),$Q$3,$Q$2))-IF(OR(ISNUMBER(MATCH(INT(L10),$N$2:$N$23,0)),WEEKDAY(L10,2)>5),$Q$2,MEDIAN(MOD(L10,1),$Q$3,$Q$2)))
where Q3= business start time 8.30am
where Q2= business end time 5.30pm
thus the difference between 18-Apr-08 16:30 and 21-Apr-08 13:30 is 6 hours.
I now need to adapt this formula for another Department that also works on Saturday from 8.30am to 5.30pm.
View 9 Replies
View Related
Nov 12, 2008
I am looking for vba code that will create a message box on the first business day of every month as a reminder.
View 9 Replies
View Related
Jan 9, 2007
I need to calculate a due date for the fifth business day of the next month following the input date. I am using Excel 2000.
View 2 Replies
View Related
Dec 18, 2009
I want to write a macro to add business hours to a datetime value, excluding weekends, non-working hours and holidays.
e.g., I have a value (datetime) of "18/12/2009 11:30:00 AM", I want to add 10 hours to this, so as to get the result as "19/12/2009 12:30:00 PM".
View 8 Replies
View Related
Mar 11, 2014
I have a spreadsheet that tracks all field equipment inspections. This year, certain equipments will need to be inspected twice a year. Ideally, if it was inspected in Quarter 1, it needs to be inspected again in Quarter 3 and if it's Q2 then it'll be inspected again in Q4.
I need a formula that will tell me when the next inspection is due.
This is what I have so far:
Column I (Formula): date of last inspection
Column J (manual entry): "yes" for equipment that will be inspected semi-annually
Column K (formula): The Quarter is was inspected based on Column I's date
Column LThe quarter the next inspection is due
View 5 Replies