I'm working on a complex A/R aging summary. So Ill have couple of question, but right now I'm trying to have excel automatically keep track of the A/R process. For instance every business day I would like the number of days the Invoice is outstanding to go up by 1. So when I get to work on monday the invoices that have been due for 20 days will now show 21 without me touching it.
View 5 Replies
ADVERTISEMENT
Dec 8, 2008
I am looking for a formula that looks at a date and could add business days to it.
for example:
If the date in a field is Monday, 15-dec-08 and my formula is to add 5 Business days (mon-fri) to it not including that date. The desired result would be Monday, 22-dec-08 but my formula gives me 20-dec-08
View 6 Replies
View Related
Jan 1, 1970
It should be deplaying dates of weekly days in Monday, Wednesday and Friday excluding sundays. Or Tuesday, Thursday Saturday excluding Sunday. e.g
Mondays, Wednesdays and Fridays of June
June 1, 2006
June 3, 2006
June 6, 2006
Tuesdays, Thursdays and Saturdays of June
June 2, 2006
June 5, 2006
June 7, 2006
This should be happening after entering any date on the first cell of the List and should accommodate up to 3 months
View 14 Replies
View Related
Dec 31, 2013
Calculating Number of Business Days Between Two Dates?
View 9 Replies
View Related
Oct 8, 2013
I have a spreadsheet that contains dates in format mm/dd/yyyy. Lets call this Column C(Paydate). In Column A I have a date that needs to be a 2 business days before the paydate. If this date in column A winds up being a Saturday or Sunday, the function needs to return the previous Friday. If the date is any weekday then it should return that weekday
For example:
C1 = 10/18/2013(a Friday) then A1=10/16/2013
C2 = 10/14/2013(a Monday) then A2= 10/11/2013(the previous Friday since 2 days before 10/14/2013 is a Saturday)
C3 = 10/15/2013(a Tuesday) then A3= 10/11/2013(the previous Friday since 2 days before 10/15/2013 is a Sunday)
View 4 Replies
View Related
Feb 11, 2010
I'm documenting the steps of a process with each step accounting for a specific amount of business days. How do I determine the specific business day based on the number of days it takes to complete a process? For example: Start date then 45 business days from that date the next step begins...then 3 business days from that date the following step begins and so on.
View 5 Replies
View Related
Apr 22, 2014
I'd like to add a number of calendar days to a date shown on Col A
I have 2 columns
a margin with a row number --- and Col A
When I try to add say 50 to the Col A ie =A261+50 to get 50 cd from cell A261 ----
I get a # problem
Tried to place 50 in a cell and then add the 2 cells but got the same result -- #
Can I use the margin row number to add to -- this would work well as I'd get the Row number which would also be the date.
View 8 Replies
View Related
Dec 4, 2008
I am not able to calculate TAT(Turn around Time) between two dates without taking Off days. Plz help me on this.. File is attatched as per example..
View 6 Replies
View Related
Jun 30, 2006
I am looking to calculate business days - more specifically Monday through Friday. I am not currently worried about holidays or vacations, yet I wouldn't mind including it if I could have a list to "check" from.
I tried previous searches, but found a few functions that I don't have on my computer.
View 6 Replies
View Related
Mar 28, 2008
we have salespeople in all 50 states and each state uses different rules for business days. Some states include Saturday as a business day, some don't, and Alaska uses 5 business days including Saturdays. We are open 7 days a week.
What I am trying to create is a worksheet that has each day of the month going down and in the cells next to it, a column for states that include Saturdays as business days; so a date 3 business days out would appear in the next cell. In the cell after, a date 3 business days out not including Saturdays. And in the last cell for Alaska, a date 5 business days out including Saturday. Of course federal holidays are all excluded.
Something like this:
March w/ Sat w/o Sat Alaska
1 5 5 7
2 5 5 7
3 6 6 8
4 7 7 10
5 8 10 11
Now Vermont has extra holidays certain months so I would have to adjust that in the formula for the middle column during those months.
View 9 Replies
View Related
Feb 18, 2009
I have created a useform in VB which will determine business days. I need help in the coding part.
In my user form I have text box, I have a calender and I have two command buttons, 1 Calculate 2 exit. What i would like to achieve is when i type a number in the txtbox and press cmd button calculate the code will shade the the date in the calender so for example if I type in 10, then the code should shade 13/02/09 on the calender since 13/02/09 is the 10th business day.
View 9 Replies
View Related
Dec 24, 2012
Where i want add Business Hours/Days to get the Target Date.
Working hours: 8:00 AM to 19:00 PM
Urgency Type:
ND (Maximum 1 Day 11 hours)
3D (Maximum 3 Day 11 hours)
4D (Maximum 4 Day 11 hours)
5D (Maximum 5 Day 11 hours)
Threshhold - 16:30 PM
Weekends to be Excluded.
Holidays to be Excluded based on Country. Say I have 2 countries India and America, where America has holiday on 12/24/2012 but India does not have holiday on that Day. Hence while calculating Tgt date, India should be calculated normally, for America holiday date need to excluded(There will be a Holiday table based on the countries, not limited to 2 countries).
ex: 1) A ticket opened at 12/26/2012 8:56 AM; Target date will be 12/26/2012 19:00, in this case its 1 day 10:04 hours added to the Opened Time.
2) A ticket opened at 12/26/2012 16:56 PM; Target date will be 12/29/2012 19:00, in this case ticket opened after threshold time of 16:30, Technically ticket should start from next day i.e 12/28/2012 8:00 AM and 1 day 11 hours added to this date.
3) A ticket opened at 12/26/2012 7:56 AM(Before the begin of Working hours); Target date will be 12/26/2012 19:00, in this case its 1 day 11:00 hours added to the Opened Time.
4) A ticket opened at 12/21/2012 17:56 PM(After Threshold time); Target date will be 12/24/2012 19:00, in this case its 1 day 11:00 hours added to the Opened Time. If the above ticket belonged to America, then holiday dates(both 24 & 25) need to be skipped and Tgt date will be 12/27/2012 19:00.
Here is the Sample Data
Country
Ticket
Start Date/ Time
Tgt Date/Time
Expected Tgt Date/ Time
America
ID000123
12/21/2012 18:20
[code]....
I need results to be appear in the "Tgt Date/Time" column. I have also provided results in "Expected Tgt Date/ Time".
View 1 Replies
View Related
Aug 7, 2012
I would like to move columns to the right as the date changes. For example, the top of the column has the current date. Within the column are about 40 rows of data. as the date changes, I would like that column to automatically move to the right and show that column with yesterday's date, and have that data associated along with it moved. I am looking for 6 months of columns to store, with the current date in the first column and subsequently moving right with the previous dates and info.
------------------------------------------------------------------------------------------------
August 7, 2012 | August 6, 2012 | August 5, 2012 | August 4, 2012 | August 3, 2012
------------------------------------------------------------------------------------------------
Accepted Processed Accepted
Rejected Accepted
Processed Processed
...
and so on
View 2 Replies
View Related
Dec 17, 2012
I have columns of dates and I'm looking to automatically highlight dates that are older than 5 business days from today. Is that conditional formatting?
View 3 Replies
View Related
Aug 16, 2009
I need to create a spreadsheet that will calculate the difference between two dates and show the result in days. The complicated part is that weekends (Sat and Sun) need to be ignored and any time after 4:30 pm needs to be treated as the next business day. I have been trying to look at similar questions in forum and use the WORKDAYS function with little success.
Example:
A1- 14/08/09 4:40 p.m.
B1- 17/08/09 9:10 a.m.
I need the answer (B1-A1) to show up as 0. But if the time in A1 was changed to 4:20 p.m. than the answer should be 1 day.
View 5 Replies
View Related
Dec 18, 2009
I want to write a macro to add business hours to a datetime value, excluding weekends, non-working hours and holidays.
e.g., I have a value (datetime) of "18/12/2009 11:30:00 AM", I want to add 10 hours to this, so as to get the result as "19/12/2009 12:30:00 PM".
View 8 Replies
View Related
Mar 14, 2014
I am making process TAT(Turn Around Time) which required following information. In Excel 2007.
1-Count number of days between two dates where working days are (Sun to Thursday). So required to exclude (Friday,Sat + Holidays)
A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 22
D1-Days between two dates 21
E1 To E10-Holidays
2-Count number of days between two dates where working days are (Sat to Thursday). So required to exclude (Friday + Holidays)
A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 27
D1-Days between two dates 26
E1 To E10-Holidays
Note : Any weekend (off days) dates listed in holidays should not effect the query.
View 9 Replies
View Related
Dec 5, 2011
I want to put a date in one cell then in the next cell i want it to add 60 days automatically, so to give the new date.
View 4 Replies
View Related
Feb 25, 2009
Basically it's to make my content management easier.
I have made a button and assigned a macro to it. At the moment the button creates a new column and makes it the right size etc.
View 14 Replies
View Related
Mar 4, 2007
Does anyone have a formula for calculating the amount of money used for a 45 day period.
e.g
01/02/07 $13.00
05/02/07 $22.00
10/03/08 $6.00
etc etc
each amount for a given date added to give a total for 45 days only.
View 10 Replies
View Related
Dec 17, 2008
I have a worksheet where in column B I have a vendor name, column E I have a date value and in column AF I need to calculate a due date based on 7 working days for vendor A and 14 days (not working days) for vendor B. I've tried to write an IF statement but can't do it. Can anyone suggest the right combination of IF/AND statements that would do this? I attach the workbook should my useless attempt at explaining my problem be unclear...
View 3 Replies
View Related
Aug 4, 2008
We have a client that has to total the number of days that people received medical care (for insurance purposes). BUT...they can't count duplicate days. Some of the dates show a range of days, others only one day. They've asked for my help. (We're actually a computer services firm, but I'm pretty good with Excel...until now!)
In column C I have placed the correct totals for the date ranges, according to the payment policies. But I can't figure out how to write the formula that accommodates all the variables (mostly since all the unique dates aren't entered--only ranges).
Each line is a different medical charge, so line 1 might be 22 days of hospital stay. Line 2 is for a different charge, but covers the same dates, so it can't count. Lines 3, 4, and 5 all occur within the previously calculated range, so they don't count. The date range in line 6 is six days but 4 of them have been counted already, only 2 days fall outside an already calculated range.
It would be easy enough to do this manually for a small list, but this patient has 1367 entries in 4 months of care! And there are others that are much larger.
Fortunately, all the dates are in calendar order. Also, fortunately, they don't need line-by-line totals, just the grand total at the end of all the unique days in the range. So if I can figure out how many unique days are in the columns ....
View 9 Replies
View Related
Mar 31, 2007
When I use the formula below it works great;
= J10+(1/$D$10)
J10 = 3-1-07
D10 = 1.5 (Production Rate example .2,.5, 1.5 rate per day) The result is:
3-1-07
3-1-07
3-2-07
3-3-07
3-3-07
3-4-07
3-5-07 and so on...
however, when I try to include only workdays, it does not calculate correctly.
= WORKDAY(J10+(1/$D$10),1,Holidays!B75:B88) with the same definitions as above the result is...
3-1-07
3-2-07
3-3-07
3-4-07
View 9 Replies
View Related
Nov 22, 2013
I want to calculate the end date of my German courses. This is how it works:
A course consists of 60 LU*. The course can occur i. e. three times a week: Monday, Wednesday and Friday. In each day the course lasts 2 LU, which means 6 LU each week. There is no course on Tuesday, Thursday, Saturday, Sunday and on holidays. Therefore this type of course that begins on 18-Nov-2013 will end on 03-Feb-2014.
Another course which occurs Tuesday, Thursday and Saturday, and respectively has 2 LU on Tuesday, 2 LU on Thursday and 3 LU on Saturday and starts on 03-Dec-2013 will end on 06-Feb-2014.
Therefore I want to create a worksheet where I set the start date, choose the days and respectively the LU amount on those days. The end date shall be calculated according to these criteria.
The workday function on excel cannot do this and I do not have any programming skills to work with VBA.
Legend:
*LU = lesson units; 1 LU is 45 minutes
Holidays:
28-Nov-13
29-Nov-13
08-Dec-13
09-Dec-13
25-Dec-13
31-Dec-13
01-Jan-14
[Code] ...........
View 7 Replies
View Related
Oct 15, 2008
I am trying to automatically add the last day of the month based off of the month
for example
a1 = beginning date
a2 = end date
a1 will always be the 1st day of a given month
then based off a1, know the last day,(i.e.... october 1, then put 10-31-08 into a2, or november 1, then put 11-30-08......)
View 10 Replies
View Related
Nov 11, 2011
I have a date in A2 7th Nov 2011
Column B is number weeks until next appointment - 4.
Column C is the answer Friday 2nd December if the normal result is a Saturday or Sunday then use Friday.
View 9 Replies
View Related
Nov 13, 2006
I am trying to add duration time for song files. 4 minutes and 32 seconds + 3 minutes 45 seconds, etc. etc. to get total hours and then to total to days. The range of cells is over 5,000 and I am trying to find out how long a playlist will play.
View 9 Replies
View Related
Jan 13, 2007
I've got a problem involving several Dim'd Variables needing to be added up, they're all Dim'd as Variants though as they can be either strings or numbers at any time.
I need a formula (VBA) to add them up (to add their actual numeric values - not just a "1" if they contain a number) and ignore them all together if they contain string values.
View 9 Replies
View Related
May 12, 2013
=IF($C2="","",IF(NETWORKDAYS($A2,$C2+1)
View 9 Replies
View Related
May 24, 2009
A B
1 4/1/09 12:15
2 4/2/09 10:00
3 4/4/09 8:10
4 4/6/09 9:00
5 4/8/09 5:00
6 4/11/09 7:00
I need to add up hours worked of last 3 days including current day. The date column does not contain everyday's date. How do I formulate a cell for date entry and another cell will show the sum of last 3 days including date not shown and date entered? E.g. If I enter date 4/6/09, result should be 17:10 hrs; 4/11/09, result should be 7:00.
View 9 Replies
View Related