I have the following formula in a cell

=NETWORKDAYS(A2,B2)-(MOD(A2,1)>=MOD(B2,1))

its works off of cells A2 for the start date and cell B2 for the end date and works perfect

I want to use this in code to automatically count business days for all rows. I have tried the following

Dim ressfp,a4,a5
a4 = Worksheets("Master").Range("O" & b).Value 'target comp date
a5 = Worksheets("Master").Range("P" & b).Value 'actual comp date
ressfp =NETWORKDAYS(a4,a5)-(MOD(a4,1)>=MOD(a5,1))

I get an error on the word MOD saying compile error syntax error but cant work out why

i have tried replacing the networkdays formula with the following

=SUM(INT((WEEKDAY(A2-{2,3,4,5,6})+INT(B2)-INT(A2))/7))-(MOD(A2,1)>MOD(B2,1))

but this gives the error that the curly brackets are invalid characters.

View 2 Replies


ADVERTISEMENT

Tat Calculation Only For Business Days

Dec 4, 2008

I am not able to calculate TAT(Turn around Time) between two dates without taking Off days. Plz help me on this.. File is attatched as per example..

View 6 Replies View Related

Calculation Of Business Hours

Mar 31, 2009

I am using the following formula to calculate business hours.

=(NETWORKDAYS(R9,T9)-1)*("17:00"-"08:00")+IF(NETWORKDAYS(R9,T9),MEDIAN(MOD(T9,1),"17:00","08:00"),"17:00")-MEDIAN(NETWORKDAYS(R9,T9)*MOD(R9,1),"17:00","08:00")

The business hours considered here is 8AM - 5PM, Start time in R9 and End time in T9. Now the problem is its calculating the correct value when the days are same, for e.g.,

Condition 1

When I am giving "31 March 2009 15:00:00" as start time (R9) and "31 March 2009 23:00:00" in end time (T9), I am getting the correct value. i.e, "2:00:00"

Condition 2

While giving "31 March 2009 16:00:00" as start time and "01 April 2009 09:00:00" as end time I am getting a value of "1:00:00", actually the value should be "3:00:00".

View 5 Replies View Related

CALCULATION TAKING BUSINESS HOURS INTO CONSIDERATION

Feb 18, 2004

I need to do an hour calculation on two cells which have dates and times in both. the first cell is a call that we get from a customer and the second is the date and time in which that call is closed by us...meaning that call is complete.

I need to calculate how much time in hours did it take us to complete that call for the customer. I need this calculation to respect our business hours of Monday to Friday 8am-5pm and closed on Saturdays and Sundays.

here are some examples.

from - 2/12/2004 13:00 (thursday)
to - 2/13/2004 9:00 (friday)

answer should be 5 hours

from - 2/13/2004 14:00 (friday)
to - 2/16/2004 10:00 (monday)

answer should be 5 hours

View 9 Replies View Related

Calculation Of Business Hours Excluding Sundays And Holidays?

Jan 29, 2014

I want to calculate the time in hours between to dates excluding non-working hours and sundays and holidays.

My office timings: 10:00am to 05:30pm Saturday is working day. Only sundays and holidays to be excluded.

View 8 Replies View Related

Date/Time Calculation For WeekEnds/After Business Hours

Jul 23, 2007

What calculation would I enter in a results cell if I wanted to find the delta between 2 times in date format that repersent just the business hours of 8am-5pm, therefore excluding after hours and weekends.

eg.

Date 1 Date 2 Result Time
23/07/07 8:00 24/07/07 14:55 15:55

So far I can't get the caluclation that will compensate for the after hours and week ends.

View 9 Replies View Related

Delete Multiple Rows But Not With Max Volume Of Business

May 8, 2007

I am currently doing some work which is taking ages and i wonder if there might be a quicker way of completing the work.

Each Row contains a User ID alone with the volume of business submitted under that user ID via a specific payment route, the problem i have is that i may have 10 of the same user ID's but each with a different business volume and payment route attached, I have already sub totaled by User ID so tat can see total business volume for each user however, I want to delete all the duplicate user IDs leaving only the row with the max volume of business attached.

I have approx 40,000 user ID's so i need the solution look for sets of User IDs and leave only the one with the biggest volume of business attached to it.

View 9 Replies View Related

Business-card Data Into Unique Rows Per Contact?

Sep 20, 2009

I have a lot of information for various contacts, in the following format:

Name: John Smith
Address: 123 Spring Street
Phone: 555-5555
Email: example@example.com

Name: Jane Doe
Address: 456 Elm Street
Phone: 555-5555
Email: example2@example.org

Name: Richard Roe
Address: 10 Bridge Street
Phone: 444-4444
Email: example3@example.org

What I am trying to do is convert that information so that it looks in a spreadsheet as follows:

example.jpg

I feel fairly sure this is the kind of thing Excel is capable of doing, but despite much searching and experimenting can't figure out how to do.

View 4 Replies View Related

Adding Rows And Calculation To Macro

Nov 3, 2008

I am extending rows on a salary schedule. As you can see below, the rows include: Bargaining Unit (GP) Schedule(2A) Range(5) Step (A) Hourly (S) and the hourly wage(11.52)

GP,2A,5,A,H,11.52
GP,2A,5,B,H,11.82
GP,2A,5,C,H,12.17
GP,2A,5,D,H,12.5
GP,2A,5,E,H,12.88
GP,2A,5,F,H,13.22
GP,2A,5,G,H,13.61
GP,2A,5,J,H,14.18
GP,2A,5,K,H,14.71
GP,2A,5,L,H,15.26
GP,2A,5,M,H,15.83

The Steps currently go from A thru M but I need to add N thru Z and after step M there is a 3.75% increase for each step.

You can see that this is a csv file (comma delimited). All of the other info needs to autofill and only the new steps (N-Z) will change and the wage for each of the new steps. The last row is 2 decimal points.

View 8 Replies View Related

Rows(":").Select: Calculation Within The Rows Collection

May 12, 2009

I want to use a calculation within the Rows collection, but I get a type mismatch error. I realize it boils down to syntax, but I don't know what I don't know.

1. In place of, say, Rows("2:37").Select...I want to use Rows("2:x-2").Select where x-2 is a simple subtraction calculation. I also want to use two variables. I'd hope to be able to infer what to do from above, but just in case:

2. Rows("z:x-2").Select

View 4 Replies View Related

If Calculation To Copy Rows Based On Hard Coded Cells?

Jan 31, 2014

I want to copy all rows from my input sheet that have a date less than the date in cell B3 of the output spread sheet and are contained in the stock table (range A7:B17) Sedol in column B Is a unique identifier. I started to do this but am lost.

View 6 Replies View Related

Last Ten Business Dates

Feb 26, 2014

How would I write a function to give me the last ten business dates moving horizontally from today's date with yesterdays date the being the last date? So if A1 is 2/26/14, how would I populate B1-B10 with wanting B10 to be 2/25/14 and moving backwards but only with business dates?

View 3 Replies View Related

Return The Corresponding Business Week

Jan 15, 2009

I have a spreadsheet (attached) containing 3 columns, week commencing (c), week ending (d) and business week (e). The question is can a user enter a date in one cell (b4) and have the next cell (b5) return the corresponding business week, I have come up with a couple of solutions involving hidden columns but was wondering if there is a way to do all of this in one cell.

View 3 Replies View Related

Macro For Last Business Date?

Jan 30, 2014

create a macro?

I want to add the Last business date in B3 cell just by running a macro.

View 13 Replies View Related

Workbook Name Always Changes By (minus 2 Business Day)

Feb 13, 2012

My file name constantly changes, it will always be (minus 2 business dates from today)

Now when my macros run it goes between different worksheets so I need to tell it to go to right workbook. I tried below but getting an error 438 'Object doesnt support this property or method'

Code:

Workbooks("file " & Format(WorksheetFunction.WorkDay(Date, -2), "MM DD YYYY") & ".xls").Activate
Sheets("data").Select

View 1 Replies View Related

Calculating Business Hours

Apr 23, 2008

I use this formula at work to calculate business hours from Mon-Fri:

=IF(OR(L10="",L11=""),"",(NETWORKDAYS(L10,L11,$N$2:$N$23)-1)*($Q$3-$Q$2)+IF(OR(ISNUMBER(MATCH(INT(L11),$N$2:$N$23,0)),WEEKDAY(L11,2)>5),$Q$3,MEDIAN(MOD(L11,1),$Q$3,$Q$2))-IF(OR(ISNUMBER(MATCH(INT(L10),$N$2:$N$23,0)),WEEKDAY(L10,2)>5),$Q$2,MEDIAN(MOD(L10,1),$Q$3,$Q$2)))

where Q3= business start time 8.30am
where Q2= business end time 5.30pm

thus the difference between 18-Apr-08 16:30 and 21-Apr-08 13:30 is 6 hours.

I now need to adapt this formula for another Department that also works on Saturday from 8.30am to 5.30pm.

View 9 Replies View Related

VBA Message Box For First Business Day Of The Month

Nov 12, 2008

I am looking for vba code that will create a message box on the first business day of every month as a reminder.

View 9 Replies View Related

Caluclating Business Days

Jun 30, 2006

I am looking to calculate business days - more specifically Monday through Friday. I am not currently worried about holidays or vacations, yet I wouldn't mind including it if I could have a list to "check" from.

I tried previous searches, but found a few functions that I don't have on my computer.

View 6 Replies View Related

Calculate Due Business Day Date

Jan 9, 2007

I need to calculate a due date for the fifth business day of the next month following the input date. I am using Excel 2000.

View 2 Replies View Related

Retrieving Variable Rows From Another Worksheet: Reducing "Calculation Time"

Aug 10, 2009

I'm using this formula to pick all rows from a huge range of cells "DATA" in another sheet, by matching the first column value (SAPDATA is the range that contains all the first column cells of DATA).

{=IF(ROW($B49)-ROW($B$48)>COUNTIF(SAPDATA,$D$4),"",INDEX(DATA,SMALL(IF(SAPDATA=$D$4,ROW(SAPDATA)),ROW($B49)-ROW($B$48)),2))}

All possible first column values have been stored as a dropdown in cell D4, and whenever I change the choice in the dropdown cell, the retrieval of those hundreds of rows takes ages in excel.

View 9 Replies View Related

Adding Business Hours To Datetime Value

Dec 18, 2009

I want to write a macro to add business hours to a datetime value, excluding weekends, non-working hours and holidays.

e.g., I have a value (datetime) of "18/12/2009 11:30:00 AM", I want to add 10 hours to this, so as to get the result as "19/12/2009 12:30:00 PM".

View 8 Replies View Related

IF Statements To Show Business Quarter?

Mar 11, 2014

I have a spreadsheet that tracks all field equipment inspections. This year, certain equipments will need to be inspected twice a year. Ideally, if it was inspected in Quarter 1, it needs to be inspected again in Quarter 3 and if it's Q2 then it'll be inspected again in Q4.

I need a formula that will tell me when the next inspection is due.

This is what I have so far:
Column I (Formula): date of last inspection
Column J (manual entry): "yes" for equipment that will be inspected semi-annually
Column K (formula): The Quarter is was inspected based on Column I's date
Column LThe quarter the next inspection is due

View 5 Replies View Related

Business Options/Pricing & Markup

Oct 12, 2009

When i open a new thread, so here i am doing so at the advice of him. The message below is specific to him to reply to but for anyone else that might want to help me with this set of formulas to resolve my worksheet headache and lack of skills in excel. Please feel free to have a look at the worksheet i posted and the comments in each color coded cell.

View 8 Replies View Related

Business Week Start Date

Dec 7, 2008

I am looking for a function or formula that will return the date of the first Monday in any given month and year.

View 4 Replies View Related

Calculating Business Fiscal Year

Sep 1, 2008

writing a formula that would result in my organizations' business fiscal year.

Assuming the fiscal year is 2008, the quarters are as follows:

1st QTR = 7/2007 - 9/2007
2nd QTR = 10/2007 - 12/2007
3rd QTR = 1/2008 - 3/2008
4th QTR = 4/2008 - 6/2008

When 7/1/2007 is entered, the result should be Q1-2008
10/20/2007, Q2-2008 and so forth.

View 13 Replies View Related

Calculate Date Of First Business Day Of A Month

Sep 19, 2012

I am attempting to create a formula that will select a value from a lookup table where that value is related to a specific date BUT that date, derived from an input date (any day within a selected month) must always be the first BUSINESS day of that month.

For example:

I have a workbook with two worksheets in it.

The first worksheet is the input page.

On that page I want to have a list of dates which display the FIRST BUSINESS DAY of a month - e.g.

Cell A1 - Date entered as 19/9/12 and displayed as 19-Sep-12
Cell B1 - NEEDS THE REQUIRED FORMUAL TO CALCULATE THE FIRST BUSINESS DAY OF THIS MONTH (SEP)
(in this example, this should be 3) and displayed as 03-Sep-12
Cell C1 - Will display the value from the lookup table on worksheet 2 (see below) related to the date in B1

The second worksheet is a lookup table containing a sequential list of dates from 28-Jan-69 through to present (19-Sep-12) in Column A.

The adjacent column B contains the related value to that date (the value being a foreign exchange rate) - e.g.

Daily
Date
USD

29 June 2012
1.0191

1 August 2012
1.0507

[Code] ........

Worksheet 1, Cell C1 should display the value of 1.0266

View 5 Replies View Related

Set Up Spreadsheet To Record Business Costs?

Jan 7, 2014

I am trying to set up a spreadsheet to record business costs, I have a column [A] and [B] with start times and finish times respectively. [C] is the shift length say 10 hours but I always get an error if its a night shift as the start time is invariably later than the finish time. Is there a way around this without inputting the dates into the cells as I am trying to not duplicate data entry.

View 2 Replies View Related

Computing Business Hours Between Dates?

Jan 9, 2014

computing the number of business hours between 2 dates.

Given the following information:
- Business Hours: 8am -5pm (8:00-17:00)
- Business Days: Mon-Fri
- if entry queued falls on a weekend or beyond the business hours, it should count the first hour on the next business hour.

Example: scenario 1 = Starts Sunday, 10am and Ends Monday 9am; count of hours should be 1
scenario 2 = starts on Monday 6pm and ends on Tuesday 10am; count of hours should be 2

View 5 Replies View Related

Formula To Generate 3-5 Business Days

Mar 28, 2008

we have salespeople in all 50 states and each state uses different rules for business days. Some states include Saturday as a business day, some don't, and Alaska uses 5 business days including Saturdays. We are open 7 days a week.

What I am trying to create is a worksheet that has each day of the month going down and in the cells next to it, a column for states that include Saturdays as business days; so a date 3 business days out would appear in the next cell. In the cell after, a date 3 business days out not including Saturdays. And in the last cell for Alaska, a date 5 business days out including Saturday. Of course federal holidays are all excluded.

Something like this:

March w/ Sat w/o Sat Alaska
1 5 5 7
2 5 5 7
3 6 6 8
4 7 7 10
5 8 10 11

Now Vermont has extra holidays certain months so I would have to adjust that in the formula for the middle column during those months.

View 9 Replies View Related

Userform VBA Which Will Determine Business Days

Feb 18, 2009

I have created a useform in VB which will determine business days. I need help in the coding part.

In my user form I have text box, I have a calender and I have two command buttons, 1 Calculate 2 exit. What i would like to achieve is when i type a number in the txtbox and press cmd button calculate the code will shade the the date in the calender so for example if I type in 10, then the code should shade 13/02/09 on the calender since 13/02/09 is the 10th business day.

View 9 Replies View Related