Userform VBA Which Will Determine Business Days
Feb 18, 2009
I have created a useform in VB which will determine business days. I need help in the coding part.
In my user form I have text box, I have a calender and I have two command buttons, 1 Calculate 2 exit. What i would like to achieve is when i type a number in the txtbox and press cmd button calculate the code will shade the the date in the calender so for example if I type in 10, then the code should shade 13/02/09 on the calender since 13/02/09 is the 10th business day.
View 9 Replies
ADVERTISEMENT
Feb 11, 2010
I'm documenting the steps of a process with each step accounting for a specific amount of business days. How do I determine the specific business day based on the number of days it takes to complete a process? For example: Start date then 45 business days from that date the next step begins...then 3 business days from that date the following step begins and so on.
View 5 Replies
View Related
Dec 4, 2008
I am not able to calculate TAT(Turn around Time) between two dates without taking Off days. Plz help me on this.. File is attatched as per example..
View 6 Replies
View Related
Jun 30, 2006
I am looking to calculate business days - more specifically Monday through Friday. I am not currently worried about holidays or vacations, yet I wouldn't mind including it if I could have a list to "check" from.
I tried previous searches, but found a few functions that I don't have on my computer.
View 6 Replies
View Related
Mar 28, 2008
we have salespeople in all 50 states and each state uses different rules for business days. Some states include Saturday as a business day, some don't, and Alaska uses 5 business days including Saturdays. We are open 7 days a week.
What I am trying to create is a worksheet that has each day of the month going down and in the cells next to it, a column for states that include Saturdays as business days; so a date 3 business days out would appear in the next cell. In the cell after, a date 3 business days out not including Saturdays. And in the last cell for Alaska, a date 5 business days out including Saturday. Of course federal holidays are all excluded.
Something like this:
March w/ Sat w/o Sat Alaska
1 5 5 7
2 5 5 7
3 6 6 8
4 7 7 10
5 8 10 11
Now Vermont has extra holidays certain months so I would have to adjust that in the formula for the middle column during those months.
View 9 Replies
View Related
Sep 16, 2006
I'm working on a complex A/R aging summary. So Ill have couple of question, but right now I'm trying to have excel automatically keep track of the A/R process. For instance every business day I would like the number of days the Invoice is outstanding to go up by 1. So when I get to work on monday the invoices that have been due for 20 days will now show 21 without me touching it.
View 5 Replies
View Related
Dec 8, 2008
I am looking for a formula that looks at a date and could add business days to it.
for example:
If the date in a field is Monday, 15-dec-08 and my formula is to add 5 Business days (mon-fri) to it not including that date. The desired result would be Monday, 22-dec-08 but my formula gives me 20-dec-08
View 6 Replies
View Related
Jan 1, 1970
It should be deplaying dates of weekly days in Monday, Wednesday and Friday excluding sundays. Or Tuesday, Thursday Saturday excluding Sunday. e.g
Mondays, Wednesdays and Fridays of June
June 1, 2006
June 3, 2006
June 6, 2006
Tuesdays, Thursdays and Saturdays of June
June 2, 2006
June 5, 2006
June 7, 2006
This should be happening after entering any date on the first cell of the List and should accommodate up to 3 months
View 14 Replies
View Related
Dec 24, 2012
Where i want add Business Hours/Days to get the Target Date.
Working hours: 8:00 AM to 19:00 PM
Urgency Type:
ND (Maximum 1 Day 11 hours)
3D (Maximum 3 Day 11 hours)
4D (Maximum 4 Day 11 hours)
5D (Maximum 5 Day 11 hours)
Threshhold - 16:30 PM
Weekends to be Excluded.
Holidays to be Excluded based on Country. Say I have 2 countries India and America, where America has holiday on 12/24/2012 but India does not have holiday on that Day. Hence while calculating Tgt date, India should be calculated normally, for America holiday date need to excluded(There will be a Holiday table based on the countries, not limited to 2 countries).
ex: 1) A ticket opened at 12/26/2012 8:56 AM; Target date will be 12/26/2012 19:00, in this case its 1 day 10:04 hours added to the Opened Time.
2) A ticket opened at 12/26/2012 16:56 PM; Target date will be 12/29/2012 19:00, in this case ticket opened after threshold time of 16:30, Technically ticket should start from next day i.e 12/28/2012 8:00 AM and 1 day 11 hours added to this date.
3) A ticket opened at 12/26/2012 7:56 AM(Before the begin of Working hours); Target date will be 12/26/2012 19:00, in this case its 1 day 11:00 hours added to the Opened Time.
4) A ticket opened at 12/21/2012 17:56 PM(After Threshold time); Target date will be 12/24/2012 19:00, in this case its 1 day 11:00 hours added to the Opened Time. If the above ticket belonged to America, then holiday dates(both 24 & 25) need to be skipped and Tgt date will be 12/27/2012 19:00.
Here is the Sample Data
Country
Ticket
Start Date/ Time
Tgt Date/Time
Expected Tgt Date/ Time
America
ID000123
12/21/2012 18:20
[code]....
I need results to be appear in the "Tgt Date/Time" column. I have also provided results in "Expected Tgt Date/ Time".
View 1 Replies
View Related
Dec 31, 2013
Calculating Number of Business Days Between Two Dates?
View 9 Replies
View Related
Aug 7, 2012
I would like to move columns to the right as the date changes. For example, the top of the column has the current date. Within the column are about 40 rows of data. as the date changes, I would like that column to automatically move to the right and show that column with yesterday's date, and have that data associated along with it moved. I am looking for 6 months of columns to store, with the current date in the first column and subsequently moving right with the previous dates and info.
------------------------------------------------------------------------------------------------
August 7, 2012 | August 6, 2012 | August 5, 2012 | August 4, 2012 | August 3, 2012
------------------------------------------------------------------------------------------------
Accepted Processed Accepted
Rejected Accepted
Processed Processed
...
and so on
View 2 Replies
View Related
Oct 8, 2013
I have a spreadsheet that contains dates in format mm/dd/yyyy. Lets call this Column C(Paydate). In Column A I have a date that needs to be a 2 business days before the paydate. If this date in column A winds up being a Saturday or Sunday, the function needs to return the previous Friday. If the date is any weekday then it should return that weekday
For example:
C1 = 10/18/2013(a Friday) then A1=10/16/2013
C2 = 10/14/2013(a Monday) then A2= 10/11/2013(the previous Friday since 2 days before 10/14/2013 is a Saturday)
C3 = 10/15/2013(a Tuesday) then A3= 10/11/2013(the previous Friday since 2 days before 10/15/2013 is a Sunday)
View 4 Replies
View Related
Dec 17, 2012
I have columns of dates and I'm looking to automatically highlight dates that are older than 5 business days from today. Is that conditional formatting?
View 3 Replies
View Related
Aug 16, 2009
I need to create a spreadsheet that will calculate the difference between two dates and show the result in days. The complicated part is that weekends (Sat and Sun) need to be ignored and any time after 4:30 pm needs to be treated as the next business day. I have been trying to look at similar questions in forum and use the WORKDAYS function with little success.
Example:
A1- 14/08/09 4:40 p.m.
B1- 17/08/09 9:10 a.m.
I need the answer (B1-A1) to show up as 0. But if the time in A1 was changed to 4:20 p.m. than the answer should be 1 day.
View 5 Replies
View Related
Sep 1, 2007
I am attempting to create a template to input specific dates. If a student submits an assignment on the due date, I have set up the spreadsheet to conditionally format whether the assignment was late or not. In addition, I have a column for when feedback is to be submitted and whether it was on time or not. My problem is this...
I cannot figure out a formula or a way to determine:
If the student submits the assignment late, when will the feedback be due? For example, if submitted one day late, the instructor has an extra day to submit feedback.Two days late is an extra two days to work on it etc..
View 4 Replies
View Related
Mar 13, 2008
My workday function doesnt seem to be working correctly, it is including weekends.
My Spreadsheet is like this
A1= 01/01/2008 ( Date)
A2= 30
A3= =WORKDAY(A1+A2,0)
I am expecting the result to be 11/02/2008, but i am getting 31/01/2008.
View 3 Replies
View Related
Jul 31, 2009
I'm needing a formula that will determine the number of days that fall in a specific month based on a date range. For example, if I have a date range of 10/15/2009 to 01/13/2009, I need the formula to determine the number of days in each month within the range (October has 15 days in the date range; November has 30, December has 31, and January has 13.) I have a large spreadsheet that would be so much easier to manage with such a formula. Currently, my spreadsheet is setup as follows. I need the forumla automatically fill in the number of days under each month.
Stard Date End Date Oct-09 Nov-09 Jan-10 Feb-10
10/15/2009 01/13/2009
I'm using Excel 2007.
View 9 Replies
View Related
Sep 18, 2009
I need to determine if the input date (Yearx) in a userform is a leap year. I tried doing this: Leap = Evaluate("MOD(Yearx, 4)") IF Leap = 0 then (show 29 days on my planner).
But no matter what date I put in, it generates "0" as the value for Leap, so indicates that February has 29 days. Obviously I'm not doing this right.
View 9 Replies
View Related
Jul 26, 2013
I am working on a "Salary Payment voucher excel Userform".
How can i do it, if i don't want manually fill in the number of working days into the textbox myself, Can i have the userform to automatically fill in the number of days when i initialize the userform.
We are working at 6 Days weeks.
View 4 Replies
View Related
Dec 19, 2008
I have a series of data that acts upon a traffic light system, i.e. Green, Amber and Red. These variables are posted along row 1 for example and there are 10 columns. Per column I have a tick and cross to answer a question. How can I find out how many ticks were on green days, amber days and red days? I have attached an example.
View 4 Replies
View Related
May 27, 2012
There are dates in column C and I need to count how many days are coming due within 90 days of each date based on the today() function but do not exceed the 90 days.
Countif Today()+90
View 5 Replies
View Related
Mar 14, 2014
I am making process TAT(Turn Around Time) which required following information. In Excel 2007.
1-Count number of days between two dates where working days are (Sun to Thursday). So required to exclude (Friday,Sat + Holidays)
A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 22
D1-Days between two dates 21
E1 To E10-Holidays
2-Count number of days between two dates where working days are (Sat to Thursday). So required to exclude (Friday + Holidays)
A1-Start Date Mar/01/2014
B1-End Date Mar/31/2014
C1-No Of Days 27
D1-Days between two dates 26
E1 To E10-Holidays
Note : Any weekend (off days) dates listed in holidays should not effect the query.
View 9 Replies
View Related
Sep 1, 2007
I'm basically looking for a forumla that will count each employees total scheduled work days for the month inserted and then depening upon the day it is will show how many days the employee has left to work for the month.
View 9 Replies
View Related
Feb 26, 2014
How would I write a function to give me the last ten business dates moving horizontally from today's date with yesterdays date the being the last date? So if A1 is 2/26/14, how would I populate B1-B10 with wanting B10 to be 2/25/14 and moving backwards but only with business dates?
View 3 Replies
View Related
Jan 15, 2009
I have a spreadsheet (attached) containing 3 columns, week commencing (c), week ending (d) and business week (e). The question is can a user enter a date in one cell (b4) and have the next cell (b5) return the corresponding business week, I have come up with a couple of solutions involving hidden columns but was wondering if there is a way to do all of this in one cell.
View 3 Replies
View Related
Mar 31, 2009
I am using the following formula to calculate business hours.
=(NETWORKDAYS(R9,T9)-1)*("17:00"-"08:00")+IF(NETWORKDAYS(R9,T9),MEDIAN(MOD(T9,1),"17:00","08:00"),"17:00")-MEDIAN(NETWORKDAYS(R9,T9)*MOD(R9,1),"17:00","08:00")
The business hours considered here is 8AM - 5PM, Start time in R9 and End time in T9. Now the problem is its calculating the correct value when the days are same, for e.g.,
Condition 1
When I am giving "31 March 2009 15:00:00" as start time (R9) and "31 March 2009 23:00:00" in end time (T9), I am getting the correct value. i.e, "2:00:00"
Condition 2
While giving "31 March 2009 16:00:00" as start time and "01 April 2009 09:00:00" as end time I am getting a value of "1:00:00", actually the value should be "3:00:00".
View 5 Replies
View Related
Jan 30, 2014
create a macro?
I want to add the Last business date in B3 cell just by running a macro.
View 13 Replies
View Related
Feb 13, 2012
My file name constantly changes, it will always be (minus 2 business dates from today)
Now when my macros run it goes between different worksheets so I need to tell it to go to right workbook. I tried below but getting an error 438 'Object doesnt support this property or method'
Code:
Workbooks("file " & Format(WorksheetFunction.WorkDay(Date, -2), "MM DD YYYY") & ".xls").Activate
Sheets("data").Select
View 1 Replies
View Related
Aug 18, 2013
I have the following formula in a cell
=NETWORKDAYS(A2,B2)-(MOD(A2,1)>=MOD(B2,1))
its works off of cells A2 for the start date and cell B2 for the end date and works perfect
I want to use this in code to automatically count business days for all rows. I have tried the following
Dim ressfp,a4,a5
a4 = Worksheets("Master").Range("O" & b).Value 'target comp date
a5 = Worksheets("Master").Range("P" & b).Value 'actual comp date
ressfp =NETWORKDAYS(a4,a5)-(MOD(a4,1)>=MOD(a5,1))
I get an error on the word MOD saying compile error syntax error but cant work out why
i have tried replacing the networkdays formula with the following
=SUM(INT((WEEKDAY(A2-{2,3,4,5,6})+INT(B2)-INT(A2))/7))-(MOD(A2,1)>MOD(B2,1))
but this gives the error that the curly brackets are invalid characters.
View 2 Replies
View Related
Apr 23, 2008
I use this formula at work to calculate business hours from Mon-Fri:
=IF(OR(L10="",L11=""),"",(NETWORKDAYS(L10,L11,$N$2:$N$23)-1)*($Q$3-$Q$2)+IF(OR(ISNUMBER(MATCH(INT(L11),$N$2:$N$23,0)),WEEKDAY(L11,2)>5),$Q$3,MEDIAN(MOD(L11,1),$Q$3,$Q$2))-IF(OR(ISNUMBER(MATCH(INT(L10),$N$2:$N$23,0)),WEEKDAY(L10,2)>5),$Q$2,MEDIAN(MOD(L10,1),$Q$3,$Q$2)))
where Q3= business start time 8.30am
where Q2= business end time 5.30pm
thus the difference between 18-Apr-08 16:30 and 21-Apr-08 13:30 is 6 hours.
I now need to adapt this formula for another Department that also works on Saturday from 8.30am to 5.30pm.
View 9 Replies
View Related