Create Time Sheet - How Many Hours Worked In A Week
Sep 25, 2013
I'm trying to create a time sheet to calculate how many hours worked in a week, Once it reaches 40 hours, The excess over 40 hours goes into a "overtime" cell. The "40" hours remain in the regular hours cell.
My overtime pays is anything exceed over 8 hours per day or over 40 hours per week. Right now I can only calculate overtime by either over 8 hr/day or over 40 hr/ week. I need a way to combine both.
Is there a way to conver a persons time spent (given in weeks) to adjust/convert to show per month. Attached is the sheet. Do note that week 2/25 - 3/1 is a combination of Jan and Feb so hours should be logically divided into jan and feb...
Name 2/18 - 2/22 2/25 - 3/1 3/4 - 3/8 3/11 - 3/15 Feb mar Tom 40 10 0 20 ?? ?? name 2/18-2/22 2/25 - 3/1 3/4 - 3/8 3/11-3/15 Feb Mar
I am trying to create a sheet which captures the Worked hrs for users in various cells. The SUMPRODUCT does not seem to be working for me .
Attached is the sample sheet which i would like to get the SUM using SUMPRODUCT.
Col D under Data Sheet has the names and these are repetitive. The Hrs / min in column E & F (Regular Hrs) & Additional Hrs / min under H & I.
I would like to have the Regular hrs + minutes to SUM up against each individual and displayed in consolidated under Col D (Regular hrs) & Col E (Additional Hrs).
I am using Excel 2010 and when i have used the same formulae in 2003 it worked. Not sure why it is not working in 2010.
I have a user form with textBox1 = start time (entered as "[h]:mm") and text Box2 = finish time (entered as "[h]:mm"). I would like textBox3 to display the difference between the start time and finish time as a general number!
For example Start time: 21:00 Finish time: 06:30 Hours worked: 9.50
i have a timesheet that we are trying to use. the problem is the column that says shift diff. if an employee works after 6:30pm for 1and 1/2hr, he is entitled to shift hours. shift hours is between 6m and 8am.
As long as he works after 6.30pm but works for at least one and a half hour, he will get the shift.
if work, 9am to 7:30pm, and have break between 2-3pm, should have 1.5hrs shift and 9.5hrs total if work, 7:45pm-9:45pm, and have break between 8:30-9pm, total hrs work is 1.5 and shift hrs s/b 1.5hrs if work 3pm to 12am and have break between 7-8pm, total hrs work is 8 and shift hrs s/b 5hrs
Any way to calculate the total hours staff work based on the mininum time of the first transaction to the maximum time of the transactions. I used a DMIN and DMAX function to get those times per employee. The issue is then the time goes over from one day to the next, such as from 11 PM to 4 AM the next day. As you can see in the data below,the fourth record shows the minimum time as 12 AM and the max as 11 PM with total time worked as 23 hours. In this example, the total hours worked should be five hours.
If a Rescue Officer is called out at 23:00 and is back at 04:00, this should equate to 5 hours worked.
It seems that if my times are all on one side or the other of a 24 hour cycle, my calculation work fine but it it breaks across the 24 hour (as above, it doesn't work.
A2=04:00 A1=23:00
Using (A2-A1)*24 give me -19.00 hours
My SS macro has a line:
s = (wks.Cells(c, 3) - wks.Cells(c, 2)) * 24 'calculates the duration of time worked
Is there any way of getting excel to calculate an elapsed time in hours when the start and end times roll over from one day to the next?
I charge one rate for day work and one for night shifts. My spreadsheet is set to figure the total number of hours worked and I know how to multiply by dollars to get answer #1, but is it possible to use a formula to multiply times a different rate for a night shift?
I have a timesheet where user updates start and end time for various tasks.
I have placed a time capture button in the excel sheet (which is simply a macro saying =now() function)
The user clicks it before starting and after finishing the task. The start and end times are captured in adjacent cells.
If the user starts the work, and goes on a lunch break say for 20 min, comes back finishes the task and captures end time, the time difference will not consider break time which is non productive.
How can I incorporate something like 'pause' option so that before he goes for lunch he can temporarily pause the time.
Is it possible that a cell contains both numeric and alphanumeric data and to do calculations on that? For example: if a cell conatain the value "10a" or "8.5b" etc. Would it be possible to have a column that gives me the hours worked (the numeric value in the cell) and a line that gives me the amount of people that are working on shift "a" (the alphanumeric value in the cell).
Is this at all possible? Or does that require VBA/Macros and stuff (in which case this is posted in the wrong part of the forum )
Lunch is not paid. Holiday and vacation hours get calculated at the regular pay rate. Overtime is anything in excess of 8 hours per day and/or in excess of 40 hours per week and/or over 5 working days per week. Saturdays for most the employees will be overtime because it will be their 6th workday of the week; but it will be regular time for one employee as it will only be his 5th workday of the week.
For accounting and payroll purposes, we need the totals to display in both hour and decimal format.
So far, I have Lunch, Regular and Overtime hours figured out, but I still need to work with Saturday, Vacation and Holiday hours. Also, currently, the time in and out has to be typed in with the colon and AM or PM. Is there another way to input the info without having to type in those items? I'm trying to make it as user friendly as possible.
I'm attempting to make a simple time sheet for a handful of employees. I'd like to enter the clock in time and clock out time for each day. The end cell should be the running total for the week. The tricky part for me is having the formula subtract an hour for each day that is over 5 hours.
I have been working on a timesheet but the problem I have come across is calculating actual hours worked only in the core hours and any work outside the core hours is calculated in the outside hours column. A standard work day is 7.6 hours working between 8.30am and 5.00pm. However if someone was to commence work either before 6am or after 8pm this is outside of core hours. I have attached an example of my timesheet for you to see what I am talking about.
I have a running time sheet daily. It has 2 columns for Labor and 2 columns for travel i.e. travel From / To 1300-1400 calculate 1 hour then travel home 1600-1700 1 hour this is calculated by the date entry 01/02/10 I have another calculation that tracks by the date i.e. 01/02/10 then Next job which all works fine.
The problem becomes how do I calculate a weekly total labor and travel by the date So added another column called weekly hour’s labor and use the Weeknum to determine which week is which day/date so the first Monday in January 2010 is week 2
2 problems Having many multiple day / date entries are the same date x 7 days Monday –Sunday (Relies on the date entered and the weeknum) 01/03/10 each line is complete however the dates carry over as does the time
When trying to calculate each row x 3 same date time then the value will be incorrect I need to calculate Say 9.5 hour labor from the date 01/03/10 not 28.5 hours and then calculate the total weekly hours 01/03/10, 9.5 hours labor, 3 hours travel 01/03/10, 9.5 hours labor, 3 hours travel 01/03/10, 9.5 hours labor, 3 hours travel
i do have work and travel times for each job on the same line (separate columns) but I display the total here by date to summarize the totals i have tried sum products and sumif to avail. I am using Windows XP SP2 with MS Office 2007
how do i calculate weekly hours by date and weeknum ?
Timekeeper to tally total hours worked by employee. When doing a pivot for sum total hours worked for FY13 it does not calculate correctly. I understand they formatted that column/custom h:mm but when I change the 8:00 hours to a number I come up with 0.33 .
I am attaching a sample file : sample time.xlsx
I just want them to get a running total of hours worked/pay.
I'm trying to make a way to track if I've worked more or less than the 39 hours/week I'm paid for. At the end of each week, I have a total of how many hours and minutes that I've worked .
On column C I have what I should work.
On column D I have what I did actually work
On column E I'd like to convert automatically Columd D to minutes for calculation purposes
Column F to know if I worked more or less than what I should've subtracting C and E
Column G to have an ongoing tally to know if I need to work more or less
Column H and I could probably be the same thing. Ideally what I'd like is to have a formula pull the information from column G and put it into workdays, hours, and minutes with 1 workday being 7 hours and 48 minutes.
Since I tend to work too much, I'd like to know if I've worked 3 days too much during 1 month, I can take 3 days off the next month to get everything zeroed back to where I don't owe the company anything and vice versa.
I am trying to create a spreadsheet that auto calculates my emp. time.
However I do not want to use military time. I can get it to work by =a2-a1 but only if it is 8.5 and 17.5. Any ideas how I can do clock in 8:30 clock out 4:30 = 8 hours?
I'm trying to calculate the total hours worked for two given periods over a shift , which can span two consecutive days ie. start 15:45 and finish at 00:15 the next day. Hours worked between 6am and 6pm are paid at standard rate, whilst hours worked between 6pm and 6am attract penalty rates. Hours are cacluated in 24hr time
I have attached a copy of the timesheet that we use so you can see exactly what I'm trying to achieve, and included most of the shifts that we have.
I can do the timesheet formula for adding the hours worked as follows:
Start Finish Total 08:45 17:15 8.5
However, it doesn't work when I fill in a whole week work of hours in this format:
Start Finish Total 08:45 17:15 08:30
It works on a daily basis, but when total hours exceeds 24, the formula get's all mixed up - how to I format the total column to account for every 5 minutes worked, which you can't do when converting to decimal??
This spreadsheet calculates hours worked great for first and second shift but when you enter times for third shift it goes all whacky with the outcome.
I am creating a spreadsheet that will track hours of overtime worked and within the spreadsheet there are several separate departments listed.
I have made it dynamic so that the summary spreadsheet will update as employees are added. I’m using a macro and some complicated helper cells to be able to sort the employees based on their total OT hours worked.
I have this spreadsheet and in it the time is changed from military time to regular and then I use a formula to calculate hours worked. On some of these the total is off by one minute. Does anyone know how to fix this?
I don't know how to paste the spreadsheet so you can see formulas,
I need to develop a work sheet for agency booked people to count the number of hours worked by them on daily basis. Agency can clock in at three different times and clock out at 6 different times. i tried but could not even develop logic to calculate the total earned hours. i attached the sheet for reference.
Refer to the attached sheet which is Daily Schedule for employee. I need a formula to add hours worked on single day in cell C2 for Monday, E2 for Tuesday, G2 for Wednesday, and so on.
Every day we have Clockin_Clockout info for each employee as shown for employee a & b.
FYI : I am using below formula to add employee hours for the week as (formula in cell R4).