Gantt Chart Help With Conditional Formatting Automation

Dec 14, 2009

Hey Guys- I'm not sure if this is even possible but I need some help. I have attached a file below similar to a gantt chart. I need help with the conditional formatting, as I have manually changed the colors to match what I need automated.

Basically I have 6 tasks and I need to change dates for individual projects but I also need the corresponding color to also change.

View 9 Replies


ADVERTISEMENT

Conditional Formatting Using Date Range (Gantt Chart)

Jun 16, 2014

I am looking for the best way to use conditional formatting in a Gantt chart. I want the cells to turn blue if they fall between two dates.

View 4 Replies View Related

Automation - Applying Conditional Formatting To Group Of Cells In Loop?

Jul 18, 2014

So I would like to automate the following, as doing it by hand takes a lot of time. I have searched the whole internet and finished empty handed.

Start from cell E10
Select cell
Move 3 cells down
Select cell
Move 3 cells down
Select cell
Move 3 cells down
Select cell
Move 3 cells down
Select cell
Move 3 cells down
Select cell
Move 3 cells down
Select cell
Apply double entry conditional formatting
Move 3 cells down
Repeat above until cell E5000

View 4 Replies View Related

Chart XY TIME - Activities Like GANTT

Jan 2, 2009

Let's suppose that I have a serie of activities. All activities are done in an interval of time and there is not overlapping.

View 14 Replies View Related

Holiday Calculation In Gantt Chart

Jul 8, 2014

Gantt chart to calculate holidays, it now only calculation weekends only, file can be downloaded from here.

View 2 Replies View Related

Gantt Chart - Extra Condition

Dec 15, 2008

The below is a sample Gantt chart that I'm using, it's working fine, what I want to do is when the STATUS is completed (Column H) goes from a cross to a tick (I'm using the format of Wingdings 2 - cross is O and tick is P) is to change the Gantt chart colour from it's current colour of green to say orange. In conditional formatting (in cell I3) I have, formula is =AND(I$2>=$F3,I$2

View 9 Replies View Related

Time Table/ Gantt Chart

Oct 25, 2009

Hi guys, I would like to be able to automatically gantt chart the following data table, my problem is that i am unaware of how to create the gantt chart when there are several entries for the one location - the table is a booking sheet and the gantt chart is just a graphical display of the activity occuring in each bay - if any could help me achieve the following gantt chart from the the following table it would be much appreciated: ...

View 9 Replies View Related

Automate Gantt Chart Creation

Nov 7, 2006

I am trying to find a way to automate this crude gant chart. What I am trying to do is the following:

1: By entering a start date and due date, and by adding a percentage to 4 different goals, create a sort of gant chart for each job.

2: Have this chart update as the start and due dates change.

3: Be able to past other gant charts below this one, based on the leader assigned to each job. ie. if Dave is a leader, create a worksheet that will have all of dave's Gant charts in one workbook, on one worksheet, pasted each one below the next. The goal being we can give each leader 1 sheet that has all their jobs.

View 6 Replies View Related

Create Gantt Or Timeline Chart

Jul 1, 2008

I tried so long I finally gave up and drew this by hand in MS Word:

But I wonder if you guys could help me chart this automatical in Excel.

I want to chart the time period a ship (Vela, Serpentine, Rainbow etc) are contracted. I want a specific color for the firm contract, and another for the remaining optional contract. If a ship is under construction I also want a bar showing when it's done.

Each ship has a rate. I want this written on the bar. In "Vela's" case there are to rates for the same contract: The first 740 days the rate is 24,5 the rest of the period it is 29. I also would like to be able plot an additional contract for the same ship for example after "Syrena" is done in yr 2009.

View 9 Replies View Related

Date Formula - Gantt Chart View

Jan 22, 2014

Someone else built a this timeline using a date calculation that I am unable to modify. Fix date formula in row 7 to show FY14-FY18 and in row 7 show the quarters 1-4 along the years.

View 3 Replies View Related

Gantt Chart Independent Cell Widths

May 28, 2014

I am developing a Excel gantt chat i have chosen to display the bars by the lenght of the cell because the data is also most real time so as the time reduces so will the bars however the problem comes when there is tasks being done under one above it as i cant have the cells with different widths

What would be the best way to get around it as i want to keep the almost and the appearance of the real time nature of the cell width equal to the value.

View 2 Replies View Related

Automatically Setting X Axis Value For Gantt Chart?

Sep 26, 2013

I have created a pseudo Gantt chart in Excel (a horizontal stacked bar chart). The chart is driven off data I have in a Power Pivot model (Auto Refreshed) and the Gantt chart displays data which spans a fixed 12 hour time frame.

The problem I am having is that in order for me to get the chart to display correctly I must manually (daily) get the excel decimal values for my Minimum DateTime and Maximum DateTime and then enter those numbers into the "AXIS Options" Bounds Minimum and Maximum value fields. I would like to automate that process so that the Axis Bounds are either driven from the data cells OR are always set to a specific 12 hour window 6pm->6am daily.

View 1 Replies View Related

Automatic Gantt Chart Format Formula

Sep 16, 2008

I am looking to create a spreadheet that will automatically shade blocks in a gannt chart according to a list of dates.

I.e B13 & B14 will have the start and end date of the particular task or activity (this will be on another sheet)

Row A3 - S3 will contain dates, iusing a lookup formulas excel will look up the activity name (or number) and look for the relevant date, if the date listed in row 3 is within or equal to that date it will return yes, if not a no.

this seemed straightforad, but I cant think of a consistent formula that will do this, without having to keep changing it ...

View 19 Replies View Related

Employee Scheduling Program Gantt Chart

Feb 14, 2007

I'm trying to create an Employee Scheduler. I want my employees (1 technician per row for a total of 10 rows) in the 1st column then the monthly calendar to the right (1 cell/day). That is what you'll see when you open the worksheet. Then, down below I set up my Data Area where I input my project, start date, end date, technician (where each tech is assigned a unique number), and other data across a row of cells. This could be infinite (or at least up to the very last row).

I modified a free Project Scheduler I got from XL-EasyGantt to become my Employee Scheduler but am having some difficulties getting it to do what I want. The project Scheduler basically works by entering (on the same row) the project (or task), the start date and finish date and then the cells get automatically filled in across those dates. This allows for overlapping of tasks but I want to create an Employee Scheduler so it doesn't allow overlapping or schedule a technician to start a new project before he/she has completed the one their on.

The main function which is in each cell of the monthly calendar is as follows: =IF(OR(AND($G28>=K$4,$G28<L$4),AND($M28>=K$4,K$4>=$G28)),IF(AND($E11="x",$M28>=K$4,$M28<L$4),"x",IF($E11=".",".","..")),"")

My problem: I want to be able to look at the Main Schedule and see when each Technician is scheduled for a job (or multiple jobs) for any given month. I want the function to look in my Data Area and assign the start date and end date of a project and the corresponding technician number and fill in the date cells across from their name in the Schedule above.

View 6 Replies View Related

Conditional Formatting Bar Chart?

Apr 4, 2014

I have a number of bar charts for which I'd like to colour the bars blue if the associated value is greater than zero and red if less than zero.

Is it possible to get Excel to assign the colours accordingly, in the same way as it does with conditional formatting in worksheets?

View 3 Replies View Related

Chart Conditional Formatting?

Dec 4, 2012

I have a Pivot Chart with 5 data series requiring 3 different formats.

Data: In my Pivot Table I have the following Fields - Type, Year, Month, Sales.

The Years are always the most Recent 2 Years (Currently 2011,2012).

The Months are, well, the Months Jan Through Dec.

The Sales are 'Number of Sales in The Period'

The Type is one of 3: Sales, Cumulative Sales and Change.

Sales has a field for every month in 2011 and 2012, the same for cumulative and finally, Change has the difference between 2011 and 2012 sales for each month.

Now when I plot these on the chart I have

Sales 2011, Sales 2012 Plotted as a line chart on the primary axis,

Change Plotted as a bar chart on the primary axis, with invert if negative formatting,

Cumulative Sales 2011, Cumulative Sales 2012, Plotted as a line chart on the Secondary axis. With the same colours per year as Sales, but as a Dashed Line.

I want this formatting to remain static as the data updates, and if possible when the series changes name (which i'm not sure is possible) because, come January the data series will be 2013/2012 not 2012/2011.

With the other formatting is seems to sometimes stay static and sometimes just decides to reformat everything and switch axes and i'm not really sure why.

View 1 Replies View Related

Conditional Formatting In Chart

Dec 20, 2011

Is it possible to aply conditional formating in Chart. for eg. my data in is below format

MonthNo of PO'sNo of GRN'sJan23444443Feb34343453Mar45425566April19002123Average PO's3055Average SO's3896

Now I want a Coloumn chart in which line changed to Red color which are below average. Currently i have to do manually change in it. Is it possible to change column chart color as per condition.

View 5 Replies View Related

Excel 2007 :: Gantt Or Stacked Bar Chart Timeline

Mar 19, 2012

I'm attempting to chart data obtained from our phone system to see when users are logged in/on rest.

I'm using Excel 2007.

The data we extract has:
person | status | start | finish | duration

Status is either "login" or "rest"
Start/finish is time (h:mm)
Duration is a formula (h:mm, finish - start)

I want to have a stacked bar chart that shows when a person was logged in/on rest; one bar for each person.

x-axis: person
y-axis: time (8am - 6pm)
legend: status

The problem I'm encountering is that each person logs in and out multiple times throughout the day (therefore, has multiple lines to their name in the data), and I can't get this information to appear on a single bar for each person.

I've sorted the data into a pivot table which gives me the information I want, but how to get the chart.

Row labels
a. Person
b. status
c. start

Values
Min of duration

Ideally, I would like to avoid using a Gantt chart within cells (as it would involve vlookup/if statements), but am beginning to think that's my only option...

View 3 Replies View Related

Gantt Chart: Color Cells Dependent On Criteria

Dec 5, 2006

I have a list of task owners that are assigned tasks. The tasks are mapped out in Gantt chart form with time shown by an "X".

what I want to do is to colour the cells "X" with the associated cell colour of the task owner and should the owner change, the cell colour changes.

View 5 Replies View Related

Conditional Formatting In Bubble Chart

Nov 26, 2013

I have the table: chart1.png

If the bubble size is 0-5, I need the bubble color to be green
If the bubble size is 6-15, I need the bubble color to be yellow
If the bubble size is 16-25, I need the bubble color to be red.

So, right now my chart looks like this: chart.png

As you can see the top bubble is the right color, but based on the bottom bubble value, it should be green.

How do I make this change colors dynamically based on the bubble size value?

View 1 Replies View Related

Gantt-type Chart With Quarterly Marks On The Date Axis?

May 22, 2014

I'm using a stacked bar chart (in Excel 2010, running on Windows 7) to create a simple Gantt-type chart - with just four or five bars. I've got my chart looking most of the way I want it to, but one thing still eludes me: I'd like to set up the major axis ticks to be quarters of the year (from 1/1/2011 to 4/1/2013). Since quarters are not regular intervals (they are not exactly every 90 days), I can't do this using Excel's standard functionality for choosing axis tick marks.

View 3 Replies View Related

Gantt Chart - Changing Cell Color Based On % Completed

Aug 12, 2014

I'm trying to create a simplified Gantt chart of sorts, and cannot figure out one piece of it. I'm not sure how to write out exactly what I need, but here goes.

I would like to have a formula that looks at the percent completed (which the user inputs) and multiplies it by the total duration for the task to give a total number of days completed. Then, under the corresponding dates, the color of the cell would change. I've attached a simplified version of what I'm talking about.

On the attached spreadsheet, the total duration (D2) is 5 days and the percent completed (C2) is 40%. This calculates to 2 days. With that said, I would like the cells under the first 2 days under the listed dates (E2 and F2) to change color. When the percentage complete reaches 60%, then G2 would change color, when it reaches 80%, then H2 would change, and when it reaches 100%, then I2 would change.

My guess is that the formula will need to result in a particular value, and then I'll use Conditional Formatting to do the actual changing of the cell color. Assuming this is correct, I still don't know what formula to use to accomplish this.

View 7 Replies View Related

Conditional Formatting Percentage Axis For Thermometer Chart?

Jun 11, 2014

I currently have a thermometer chart in Excel 2013 that I set up with percentages along the Y-Axis. The thermometers are showing spending based on a budgeted number. Currently, the project is over-budget so I have adjusted the thermometer scale to go far beyond 100%.

I would like to have the percentages past 100% show in red along the lefthand side.

View 2 Replies View Related

Bar Chart Conditional Formatting - Values Changing Frequently

Jan 8, 2014

I have a horizontal bar chart in which some of the bars represent positive values and others represent negative values.

How to format the bars so the "positive" bars are shaded in one colour and "negative" bars in another colour? I'd prefer not to change the bar colour manually as the values change frequently.

View 2 Replies View Related

Conditional Formatting Vertical Bar Chart Tied To A Date

Dec 2, 2012

I have 60 days of data, Nov 1st through Dec 31st.

The date is my x-axis labels.

I produce a daily report. I'd always like for the current dates vertical bar to be "red".

Is there any easy way to have this accomplished?

View 6 Replies View Related

Conditional Formatting Of Chart Based On Category Axis Value

May 24, 2005

I am trying to format the colour of a column chart based on the value of the x axis (not the y axis value). Firstly I need to know if it is possible. Secondly I would appreciate any hints / VBA code that could be useful.

View 4 Replies View Related

Conditional Formatting Of Bubble Chart Points Based On Bubblesizes

Jul 26, 2012

I am trying to format the colors of the bubbles on my bubble chart to Green (>5), Yellow (4-5), or Red (<4) based on the value used to create the bubblesize.

The problem that I am having is that .BubbleSizes is property of type String, not range like .xValues, or .Values. So instead of pulling in the value, I am pulling in the reference and getting a "Type Mismatch" Error. The reference of my data for .BubbleSizes is $D$5:$D51. Each row is it's own series and the list is dynamic, so I need to be able to support future rows without a lot of maintenance.

Here is the code that I have so far.

VB:
Sub DataSeriesFormat()
'
' DataSeriesFormat Macro
' Format Data Series based on defined parameters for Green, Yellow, and Red. Created by Derek Steinmetz 7/24/12
'
Dim x As Integer
Dim val As Variant
Dim Green As Range

[Code] ......

View 1 Replies View Related

Count Conditional Format Color Cells- Used Gantt Code

Sep 3, 2004

I've created a Gantt chart using the tip #58. Now how can I count all the cells that are colored?

View 9 Replies View Related

Conditional Formatting - Two Different Fields Affect One Cells Formatting For Date?

Sep 16, 2013

A little background on what i am doing. I have a spreadsheet that tracks when i have blown the dust out of our computers. I have set up conditional formatting so that the text turns red after 300 days and the cell turns yellow after 600 days. However, some computers are in high dust environments. I would like the spreadsheet to tell me to blow the dust out of these sooner. see the attached sheet.

dust 1.xlsx

View 2 Replies View Related

Conditional Formatting Based On Another Cell Conditional Format

Mar 20, 2013

Is it possible to change the format of cell AI3 based on the format of cell C3 and D3? I have C3 and D3 set to turn red based on what is in cell C2 and D2. I would like the following done:

If AI3=C3 & C3 is red, format AI3 blue
If AI3=D3 & D3 is red, format AI3 blue
Otherwise, leave AI3 unformatted.

Possible???

View 3 Replies View Related







Copyrights 2005-15 www.BigResource.com, All rights reserved