Date Change Using Workload Increase With IF Statements
Jun 2, 2014
I have a tracker where each row has a predicted complete date, this date is already based on some IF statements. I have a second column where I would like a second date to be based on the overall team workload.
the workload factor should add on extra time to the first date.
This would by adding on.
0-40 = 3 weeks (standard time)
41-60 = 4 weeks
61-80 = 5 weeks
81- 100 = 6.5 weeks
101-120 = 7.5 weeks
I have two tabs.....I take the total workload from the Tracker Status and the progress tab is where the first date and the new date will appear.
I tried a formula using a % increase in time (I did this using e.g. 0.33 for 33% for increase between 3 and 4 weeks) (based on the increase in weeks), but it came out with date in 2052!!! This is my formula that doesn't work properly.
=IF('Tracker Status'!B5>=100,'In Progress'!AE2*(1+'Tracker Status'!C22),IF('Tracker Status'!B5>=80,'In Progress'!AE2*(1+'Tracker Status'!C21),IF('Tracker Status'!B5>=60,'In Progress'!AE2*(1+'Tracker Status'!C20),IF('Tracker Status'!B5>=40,'In Progress'!AE2*(1+'Tracker Status'!C19,IF('Tracker Status'!B5
View 9 Replies
ADVERTISEMENT
May 26, 2008
Sheet one will contain the following:
DATE A B C D E
2/22/2008TRUEFALSEFALSEFALSERon
2/23/2008FALSETRUETRUETRUEPhill
2/24/2008FALSETRUEFALSEFALSETracy
2/25/2008FALSEFALSEFALSEFALSESharon
2/26/2008TRUETRUEFALSETRUEBill
On sheet two I need to list any date that has three or more true statements with the coresponding name.
EXAMPLE:
2/23/2008Phill
2/26/2008 Bill
View 4 Replies
View Related
Aug 11, 2013
In column A, I have dates; In column b i have security levels. I have made a table called "Security" it contains to columns, a list of security levels and no of years when each security level is required to be reviewed. the table is setup -
d1 e1
Restricted 5
etc
Example of data
ie.
a1 b1 c1
Restricted 1/06/2012 1/06/2017
What I am looking for is a formula to look up a1 "restricted". then lookup the security table and find "restricted" its value is 5 (years) then add the 5 years to date in b1, but place it in c1.
View 1 Replies
View Related
Nov 15, 2009
I have a 49 numbers in cell A1:AW1 they are not in acceding order. I want to separate all groups start from lowest number to highest giving them deferent color. As shown in example table below in cell (A2 start with nš 6 and increase up to nš 47 till cell F2 =yellow color) then Cell (G3 decrease nš 3 and increase up to nš 49 till cell L49=Green Color) and continue same process for rest ....
View 9 Replies
View Related
Dec 28, 2006
I have many data in a worksheet named "Table" with "Item" in column A and "Reference" in column B. For each change of item, I need to assign a reference number with a prefix. Below is a sample of the data.
Column A Column B
Item Reference
Orange R9
Orange R9
Orange R9
Apple R10
Apple R10
Apple R10
Mango R11
Mango R11
The starting reference number is not fixed. It could start from 8 or 10.
Thought it would be possible to automate this process using vba.
View 7 Replies
View Related
Nov 23, 2009
I have to balance workload equally for everyone (Name: abc, xyz, mno) and New Orders must be shared or distributed equally for every person. New Orders must be shared in such a way that every person's percentage share must be made equal by distributing or sharing New Orders. Find an attachment named issue.xls
View 2 Replies
View Related
Sep 28, 2009
how to change the cell colour due to a sum increase or decrease? For example: if the amount is greater than 200, change cell colour to green. If under 200 change cell colour to yellow.
View 2 Replies
View Related
Nov 1, 2006
I have two dates in A1 and B1. Eg 24/Oct/06 in A1 and 27/Oct/06 in B1.
Can the range of these two dates be updated to Cell A10, followed by the next row.
Eg,
Cell A10 24/Oct/06
Cell A11 25/Oct/06
Cell A12 26/Oct/06
Cell A13 27/Oct/06
Because the two dates in A1 and B1 are updated by user, the range is not fixed. Eg It could be 20/Oct/06 in A1 and 29/Oct/06 in B1.
View 9 Replies
View Related
Nov 12, 2009
I work in IT Service company and we need to calculate our workload based on a number of devices in our scope.
Say, somebody wants to add 300 Windows Servers to our service desk. We know that each Win Server would need 1 Person on duty to manage. So ideally we would just multiply 1*300 and get the amount of people we need.
Problem is that because the service is quite similar for each of these servers, we dont really need a dedicated person for each device so I want to make every additional device consume 20% less workload than the previous one.
In our case it would be:
1 Server = 1 Person
2 Servers = 1.8 People
3 Servers ~ 2.5 People
View 12 Replies
View Related
Oct 4, 2006
I have a rather complex worksheet, but it needs lots of manual intervention, it calculates the number of staff needed at any given hour for a call center based on the calls offered for an hour, the calls for a day are copied into the calandar and the last 7 "Mondays" "Tuesdays" etc: calls are averaged to give me a call trend, what I need is a way of automaticly adding this data.
I have created dropdown boxes with all the dates, if I choose a date, I want to be able to fill the last 7 "Mondays data"
View 9 Replies
View Related
Jul 8, 2014
I have a spreadsheet and I'm trying to add date to the left hand side. I want them to increase by one but there needs to be each date, in a column, 4 consecutive times.
Example
Jun 1 12p
Jun 1 4p
Jun 1 8p
Jun 1 12a
Jun 2 12p
Jun 2 4p
Jun 2 8p
Jun 2 12a
Jun 3 12p
Jun 3 4p
Jun 3 8p
Jun 3 12a
This is for a Dialysis flowsheet and I really need this to work.
View 6 Replies
View Related
Nov 2, 2006
I have a test due in the morning, and I really need this question answered ASAP, if anyone could. I need to create an IF formula for this situation: the standard Mhz is 500. Give 55.00 for that standard. But for every increase of of Mhz, give 25.00 per 100 increase.
View 2 Replies
View Related
Jun 9, 2014
I have set the check boxes for each line. I would like to have the today date to appear after clicking the check box on the next right cell. Do I have to use IF for this one?
ALSO I want the number to count up after click the check box. For example:
Name:
Bob (assigned)- 5
(completed)- 4
Every number of completed line increases every time each box is clicked. How can I do that?
View 2 Replies
View Related
Apr 4, 2009
I would like to create a financial modeling spreadsheet. Basically my problem is this; I want to have a month by month row for 5 years. For the value of each one I would like it to increase by 950 per month automatically.
View 4 Replies
View Related
Aug 22, 2008
I have 22-08-08 in Cell A2 I would like it to change to 22-09-08 on 23-08-08 ideally using edate (but not neccessarily).
Perhaps I can add a formula with conditional formatting eg formula is = "On Today()+1 Add 1 month to cell A2"
View 9 Replies
View Related
Apr 5, 2013
Any way to have the date auto increase 7 days when we drag/copy down the cells. For example, I have the following:
03/31/13
04/07/13
04/14/13
So, when I copy down (let say hundred cells down), the day should show 7 days apart. Is there a formula?
View 3 Replies
View Related
Dec 8, 2008
I am trying to calculate the number of forecasted hours worked per week for each contractor based on their allocation to the project and also based on a 37.5 hour standard week.
I am using a formula which was previously provided to me for another problem but theoretically should share the same logic. The formula works only when a contractor is forecasted to work for a full week. If there is a contract which finishes mid week the formula returns a weird value. Also another problem is that if a contract is starting on the 12th of January, it still forecasts a full week for the week commencing the 7th of January. I have attached a spreadsheet for everyone's reference.
View 4 Replies
View Related
May 18, 2013
I have got a table with data from 2005 to date, (for example) For the purpose of what I am doing I need a column which shows date ranges between September 2005 - August 2006 to show as 2005/2006, then September 2006 - August 2007 to show as 2006/2007. I have done some research and seen that, Potentially, a nested 'IF' can be used but it can only be used 7 times which would cause a problem going forward....
Is this the only way or is there a better way (without using VB)?
I am using Excel 2010
View 7 Replies
View Related
Feb 12, 2009
The data:
There are a number of columns, but we'll use the first 2 first. Column A has the dates from 1/1/2009 to 12/31/2009. Column B will has numbers, mainly 0-100. One cell will have a 'report date' which is just a date.
The formula needed:
I have a few cells labeled wk1, wk2, wk3. Week 1 will start with the 'report' date. wk1 I would like the Average of Column B IF the dates in Column A are within the 'wk'. wk1 = report date TO report date + 6. wk2 = report date + 7 TO report date + 13 and so on.
My goal is to have the formulas all set so that when we move to another report date and the raw data is added, I can just change the 'report date' and everything (the wk numbers) will automatically update with the new raw data.
The furthest I got was this, but it didn't work.
=AVERAGE(IF('A3:A33>=VALUE(D3)
View 9 Replies
View Related
Nov 22, 2008
I have three IF statements as below. the problem is if the first statement is true I want it to skip the next two statements or the result will be changed again.
View 2 Replies
View Related
Apr 24, 2012
I have a table of data (total 142 rows). Column contains dates, in the format dd-mmm-yyyy.
I tried to filter using DATE FILTERS->EQUALS and in the custom filter window, I chose EQUALS then picked a date from the date picker icon. The date I picked was 5/4/2009 (this is May 4, 2009, formatted automaticall by excel as m/d/yyyy).
When I clicked OK, nothing showed up despite the fact that there are 6 occurences of May 4, 2009 (formatted as dd-mmm-yyyy in the data table)
So my questions are:
1. Is this due to the formatting?
2. Is there a way to change the date format supplied by the date picker?
View 7 Replies
View Related
Jun 3, 2012
I now have XL 2007 but no longer work at the same place so do not have access to the external data source. I would like to view the SQL statements that I wrote back then but keep getting error that I am not connected to external data source and so cannot see my sql statements. I have MS Query 2007.
View 1 Replies
View Related
Mar 22, 2013
I'm trying to analyse all of my bank statenments to see where all my money went!! I've got online banking so I thought it would be a relatively easy process of copying and pasting each month into excel.
Well, that in itself was easy, the problem is with the formatting of the financial numbers. Excel doesn't seem to recognise them as numbers, so at the moment I can't do any manipulation with the numbers. I have tried everything such as:
Format Cells > Number > Number and Currency
Copy and Paste Special > Values only
Copying into Notepad and back into Excel
Even if it appears to have changed the numbers to 'number' or 'currency' formatting by right justifying the numbers, if I try to add up the numbers using the SUM function, it doesn't want to know.
For some reason nothing seems to work - what am I missing?
For an example, I have attached a snippet of the spreadsheet with my starbucks transactions.
View 3 Replies
View Related
Oct 14, 2009
How can I combine the two below statements like these to make one "Or Statement"? Sorry...I haven't done excel and/or's in forever?
=IF(('Proj Info'!L10="main")*AND('Proj Info'!L9="CT"),"BMSVC",'Proj Info'!L9)
OR
=IF(('Proj Info'!L10="serv")*AND('Proj Info'!L9="CT"),"BMSVC",'Proj Info'!L9)
View 2 Replies
View Related
Oct 31, 2008
This is a project plan with tasks and dates. Column A is the activity number. (Example 1, 2, 3" etc). Column B is the task (Ex. "Complete Report"). Column C is number of days required to complete the task. Column D is the dependency column. (Ex. Cell D2 =1 in other words Task 2 is dependent on task 1). Column E is the date.
I would like to have a seperate start date cell and a go live date cell.
The objective is to enter a start date, and have each column E date increase based on the number of days entered in Column C. If a task is dependent on another and I change the number of days in Column C I need the dependent task to change the same amount of days.
View 9 Replies
View Related
May 1, 2014
The formula below is to change the fill colour of a date cell prior to the date expiring. The 120 value is number of days
=(E7-today())<=120
The problem i have is it only seems to work if i format the cell and use mmm-yy.
I want to use the same formula for dd-mm-yy..
View 3 Replies
View Related
May 19, 2009
In a particular month, I have some transactions with a consumed date. If the time falls at 12.00 AM in the end of the month, then the transaction goes into the next month. Below is an example:
3/25/2009 12.00.00 AM
4/1/2009 12.00.00 AM
I want all the transactions that fall on 4/1/2009 due to 12.00.00 AM to convert to 3/31/2009.
View 4 Replies
View Related
Nov 12, 2009
why I cant change the date format for some of these rows?
Im trying to modify a excel file sent to me by a client but some of the fields seem to be messed up.
Could somebody explain what i must do to get all the rows in a format
yyyy-mm-dd
i have already tried to format the cells, but only some rows update!!
View 10 Replies
View Related
Mar 3, 2014
I would like to be able to input the Day and date in coloumn A and have the rest change accordingly
I wish to have it displayed as follows Monday 03/03/2014 followed by coloumn 2....Tuesday 04/03/2014.
There are 4 cells for each day set that have been "Merged and Centred". (B2,C2,D2,E2) display "Monday 03/03/2014" , F2 is a split , (G2,H2,I2,J2) display "Tuesday 04/03/2014" and so on.
I can make the dates change according to the first input but since i must also display the day as well.
View 4 Replies
View Related
May 27, 2009
when I do Format Cell, the date formats offered use US formats like 20/02/1999. Why does it do this, and can I fix it? I suspect that this the root of the following problem.
I have a button on a userform to enter today's date into a textbox. It enters it as 05/27/2009. The wrong format. I save the data to the worksheet, then use the data form to go to the next record, then back. The date then appears in the correct format as 27/05/2009.
Another related problem: if I enter a date manually into the textbox on the dataform, such as 2/3/2008, it interprets it as Feb. 3, and when I save it to the worksheet, and then use the form to view it, it comes out as 3/2/2008.
View 6 Replies
View Related