Get The Number Of Workdays Between Two Dates In A VBA Function
Oct 18, 2008
Get the number of workdays between two dates in a VBA function. I tried simply using the Advanced Toolpak function NETWORKDAYS, but I get the error message "Sub or function not defined". I did reference to atpvbaen.xls in the Tools > References menu, so I don't know why Excel is not recognizing the function.
I used the following function to test it:
Function CalcNetDays(dInitial As Date, dEnd As Date)
CalcNetDays = NetworkDays(dInitial, dEnd)
End Function
Any reason the function is not working?
Also, I need to add the holidays to the function. The holidays are listed on a worksheet column. Do I simply add the range to the function, like below?
CalcNetDays = NetworkDays(dInitial, dEnd, Range("Holidays"))
View 9 Replies
ADVERTISEMENT
Nov 2, 2006
I am trying to map the total networkdays across the months of the year for a list of contracts with variable start and end dates.
Example of the results I'm after:
Contract StartDate EndDate January February March etc.
Contract1 15 Jan 07 13 Jul 07 13 20 20
Contract2 5 Feb 07 2 Mar 07 0 18 2
I assume that the add-in NETWORKDAYS function is involved (and I'm ordinarily comfortable with using this function with only two dates and my named range of holiday dates), but I can't seem to figure out how to use it in this more complicated way. My own extensive struggles with it have led to ridiculously long and nested formulas that even I didn't understand after a few days away from them. I've searched the posts and seen questions similar to mine, but not close enough to give me a solution.
View 4 Replies
View Related
Mar 4, 2008
I need to calculate the difference between two work days to understand how many days late we missed a due date. The NETWORKDAYS formula gives me the COUNT of the workdays, but I need the difference.
Example 1:
Expected Due date: 3/3/08
Actual Due date: 3/3/08
NETWORKDAYS for the dates above gives me the value of 1, but for my needs I need the resulting value to be zero.
Example 2:
Expected Due date: 3/3/08
Actual Due date: 3/5/08
NETWORKDAYS for example 2 provides a value of -3 (days late), but in reality it's only -2 (days late)
View 7 Replies
View Related
Dec 6, 2013
I need a VBA Function, I have a start dates in column A and end dates in column B what I need in column C is the abbreviated days excluding the weekends. For example if I have 11/11/13 in A1 and 11/20/13 in B1 then in C1 I need (including start and end date) Wed, Thu, Fri, Mon, Tue, Wed, Thu, Fri. Another example If I have 11/29/13 in A1and 12/3/13 in B1 then in C1 I need Fri, Mon, Tue.
View 4 Replies
View Related
Aug 8, 2007
what was wrong with this formula, an error message comes up saying VALUE, im trying to get the formula to say that - If 2 dates are different then subtract one from the other to get a number of working days, but if the dates are both the same then to -1 from the value as for some reason the value is coming back as 2 when it should be 0?
=IF(OR(M17>0,N17>0),NETWORKDAYS(M17,N17,holidays)+1+Q17,IF(OR(M17=N17),NETWORKDAYS(M17,N17,holidays)-1,0))
View 9 Replies
View Related
Jan 2, 2014
I need a way to calculate the number of workdays, Saturdays and Sundays in a month.
In my model, the client can choose to work on Saturdays and/or Sundays.I need someway to show that a given month (e.g. June 2014) has some # of workdays, and some # of Saturdays and some # of Sundays.I can do this on three separate rows.
eg.
Row 1: Month
Row 2: Wordays
Row 3: Saturdays
Row 4: Sundays
Still i need some way of determining that a given month (June 2014) has 22 work days, 4 Saturdays and 5 Sundays,... et cetera
View 4 Replies
View Related
Nov 26, 2011
I have never worked on workdays before so I do not know most of the available formula and play around. I googled across and found this one: [URL] .......
Where Bob has given an ARRAY formula.
Following is my layout in A1 to C3 grid (for testing purpose):
Start Date11/1/2011HOLIDAYEnd Date11/30/201111/3/2011NETWORKDAYS2011/22/2011
The formula resides in B3.
Is there any other development in 2007+ versions of Excel which can handle 6 working days in a week?
View 9 Replies
View Related
Feb 26, 2014
I am looking for a formula which substract a number of workdays defined in a cell from a date defined i nanother cell. For example I have a date in cell B2: 10.08.2014 - this is the due date for service delivery. In cell C2 there is a number of workdays: 84 - this is the duration for the delivery process. I would like to have a formula calculating in cell D2 the date when the delivery process has to start. The tricky point is that B2 is basicly a range of merged cells B2:B6. As an example I am attaching an exmple sheet.
View 10 Replies
View Related
Jan 13, 2014
In cell A1 I have a date 1/1/14
I need to get the number of business days for the month that is entered in the cell. I tried NETWORKDAY formula but needs a start and end date.
View 3 Replies
View Related
Dec 6, 2013
Is there a formula I can use to determine the number of work days in each week for a given month. The work week would start Sunday, with Friday and Saturday as days off. Each week would be in their own row.
i.e.
January
Week 1: 2 days
Week 2: 5 days
Week 3: 5 days
Week 4: 5 days
Week 5: 3 days
[Code] ..........
View 4 Replies
View Related
Nov 26, 2009
I was calculating the number of days between two dates using the Days360 function. However, now it is not accurate enough for me... Is there a function that is more accurate? based on 365 days and includes leap years... that I could use as I need this calculation to be exact? For example, number of days between April 1st, 2010 and August 31, 2012 is 884, but the days360 function returns 870.
View 4 Replies
View Related
Jun 22, 2012
Is there a simple function for calculating the number of months between 2 dates.
Eg 1/5/2012 - 8/9/2020
View 1 Replies
View Related
May 1, 2006
I would like to create a monthly inventory, based on workdays (Monday - Friday)Myrna Larson has a formula that I would like to use with the workday function, but I don't know how to combine them.
=IF(A1="",A1,IF(MONTH(A1+1)=MONTH(A1),A1+1,""))+ = workday
to fit on the page, I need the dates to be from the 1st to the 15th, and 16th to the 31st. I am not sure how to write this either.
View 11 Replies
View Related
Feb 23, 2014
Here is my set up:
A2 to BF2 is a range of dates
A3 to BF3 are sales. Days without sales are 0.00
I want to pick a range of dates and find the number of days without sales between those dates. So, a formula that will look to a start date in A1 and an end date in B2, and then count the number of days that did not have sales between. Index/Match/Countif/Dateif I can't seem to make anything work.
View 3 Replies
View Related
Mar 22, 2014
How to create a spreadsheet with what I think will be a very simple formula?
If date in B2 - date in A2 is 1 or less days, put a 1 in cell C2.
If date in B2 - date in A2 is 7 or less days but more than 1, put a 2 in cell C2.
If date in B2 - date in A2 is 30 or less days but more than 7, put a 3 in cell C2.
If date in B2 - date in A2 is 90 or less days but more than 30, put a 4 in cell C2.
If date in B2 - date in A2 is 91 days or more, put a 5 in cell C2.
OR
Another, maybe simpler, way of saying it is:
If date in B2 - date in A2 is 1 or less days, put a 1 in cell C2.
If date in B2 - date in A2 is 2-7 days, put a 2 in cell C2.
If date in B2 - date in A2 is 8-30 days, put a 3 in cell C2.
If date in B2 - date in A2 is 31-90 days, put a 4 in cell C2.
If date in B2 - date in A2 is 91 days or more, put a 5 in cell C2.
View 9 Replies
View Related
Mar 26, 2014
I have a userform that captures dates and records them to another excel workbook so we can analyse the data. I have one last part to finalise; When a date is added to the "daterecievedtxtbox" I would like a formula to be offset to the end of the spreadsheet, that will take this date and add 3 working days to it. Then I can add in some formulas later to flag them when the date passes the 3 working days.
At the moment I have this:
[Code] ....
Which adds 3 days to this txtbox and writes it to the sheet that I have defined. I would like to know if there is a function that I can use to add 3 WORKING days to this, excluding saturday and sunday.
View 4 Replies
View Related
Oct 28, 2009
I would like to know how to get the number of working days in a month based on the date in B4 which is formatted as "mmmm".
So if B4 was October the result would be 22 regardless of the actual date in B4.
I also have a named range "Holidays" for UK bank holidays (ready for December) that I would like included within the formula.
View 9 Replies
View Related
May 13, 2009
I am using excel 2003 and I am trying to subtract 20 days from the date in cell A3 in order to give me a date for me to order materials. However all I get is #NAME? in the cell.
View 4 Replies
View Related
Jul 9, 2014
I am looking to find a way to filter a list for the next twenty business days.
View 7 Replies
View Related
Dec 3, 2013
So I have a cycle time formula; Start Date to Completion Date, if the task is not complete the completion date field is blank. In this case the cycle time is listed as a negative 5 digit value. The networkdays formula takes into consideration weekends and holidays.How can this field be left blank rather than the negative value?
=NETWORKDAYS(I2,P2,Sheet3!$A$2:$A$10)
View 6 Replies
View Related
Jul 3, 2014
I have data in column C which is the date and time
Data is: 16/06/2014 09:47:14
Cells are formatted as dd/mm/yyyy" "hh:mm:ss
Column H has another date and time based on service level agreements
Data is 17/06/2014 09:47:14
Cells are formatted as dd/mm/yyyy" "hh:mm:ss
I need to add 3 workdays to the 1st value so it returns 19/06/2014 09:47:14
I've used the following formula =WORKDAY(C2,3) and it returns the correct date but time shows as 00:00:00. Is there way I can pick up the time from Cell C2?
View 2 Replies
View Related
Oct 18, 2007
What formula would I use to display how many workdays there are in a month.
The month is displayed in cell A1
View 9 Replies
View Related
Sep 7, 2008
I have an excel file I am working on with a due date column. I have already created 2 conditional formatting.
1. if cell value is less than today's date then format the cell red
2. if cell value equals today's date then format the cell orange
I need to create two more conditional format....one where it looks at today's date and if the due date date cell is within 1-3 business days from today's date then I want the cell format to turn yellow and I need a last conditional format to look at today's date again and if the due date cell is within 4 -5 business days from today's date then I want the cell format to turn green. Can these two additional conditional formats be done?
View 9 Replies
View Related
Apr 1, 2014
I want to write a function which will calculate whether a certificat needs renewing TODAY or not. The validity of certificate is 12 months.
HTML Code:
A B C D
type of cert date test done valid or not?
fire 01/01/10
test 01/03/14
health and safety 01/03/14
asbesto 1/03/05
gas 05/05/05
electricity 01/06/13
validity 12 months
View 3 Replies
View Related
Jun 13, 2006
The worksheet will have a list of staff and the date they sat for a particular test. I need to be able to highlight in some way when for example 6 weeks has passed so that the staff member can be re-tested.
We want to be able to open this worksheet and see immediately any staff who are overdue for a retest. If they have undertaken such retesting we obviously don't want to see them red flagged or whatever any more.
View 9 Replies
View Related
Sep 4, 2009
I would require a formula to count the amount of workdays between cell a1 and cell a2. Assume formula is in celll a3 and both a1 and a2 are date formated.
View 2 Replies
View Related
Dec 26, 2012
I have the following function:
=IF(G13="",IF(H13>1,1,IF(G13>1,workdays(H13,G13,Holidays))))
The intent is to calculate the completion date against the assigned date as follows:
G13 - Typically the assign date but sometimes can be blank because someone forgets or doesn't bother to insert
For this example, let's say: 12/17/12
H13 - Completion date
For this example, let's say: 12/20/12
I'm expecting a result of '3' for 3 days
The first half of the function is intended to calculate 1 day if G13 is blank or not defined. However, when I have dates in both cells, I'm getting a "false" answer instead of a numerical value that I'm expecting.
In our workplace, we do work weekends & sometimes 7 days a week.
View 11 Replies
View Related
May 7, 2008
I need to create a business days calendar consisnting of two columns start_date and end_date. Start_date is today (always a work day), end_date column will have to be start_day +1 day, start_day +2 days, start_day +7 days, start_day +30 days, and so on till + 3600 days. Every end_date must fall on a business day, or the first following business day if it is falls on a WE. Assume I know all holidays for the next 10 years. I could use Workdays or other built in function, the trouble is they all assume Sat and Sun as WE, my WEs are FRI and SAT! I tried to write a UDF but I'm failing miserably with too many ifs and elses,
View 9 Replies
View Related
Jul 11, 2009
i am trying to determine how to use the workday function to generate only workdays for 1996 and forward. Each year is listed in a separate column.
View 9 Replies
View Related
Apr 30, 2008
How to add 2 "working days" to a date, including Saturdays as work days, and excluding holidays and Sundays? Similar to: = WORKDAY ("01/02/2008", 2, 39451) But instead of resulting in Mon Jan 7th, the answer should be Sat Jan 5th. (39451 is Fri Jan 4th.)
View 4 Replies
View Related