Calculating Between Two Times
Nov 24, 2009
I had an excellent response last time I posted here, this time I’m stuck again with a new formula. I’m trying to calculated amounts between different times, but keep tying my self in knots with complicated IF formulas.
Is there an easier way to work out hours worked between 2 times, but too complicated things further I need three separate amounts so I’m guessing I’ll need three separate formulas
Hours between 00:00 – 06:00
Hours between 06:00 – 19:00
& hours between 19:00 – 00:00
An example could be, 05:00 – 20:00 should be 1,13,1
View 11 Replies
ADVERTISEMENT
Apr 10, 2014
I would like to add up multiple time in and time out for my pay sheet.
As you can see, the total hours worked for Weed A is correct, but the Total Hours Worked for Monday is incorrect. The forumla I am currently using is:
=((B12-A12)*24)+((B13-A13)*24)+((B14-A14)*24)
But I would just like the total hours worked for each day to be the actual hours (2.5 hours).
View 2 Replies
View Related
Aug 3, 2008
we work 8hrs 30mns for 4 days 7hrs 30mns for 1 day this is monday to friday
using Excel i need a formula that will add the following:-
a1 8.30
a2 8.30
a3 8.30
a4 8.30
a5 7.30
total 41.30
View 3 Replies
View Related
Mar 29, 2007
I am trying to calculate the difference between a scheduled start time and an actual start time. If the actual start time is greater than the scheduled start time a negative time (hh:mm:ss) should be returned. instead the cell is populated with #############....
I have tried to reformat using the custom formats, but the only options in excel 97 are for either standard numerics or £ (these return a minus figure).
I've had a look at the time functions but could not see a suitable one.
I'm sure there is a simple format solution to this.
View 3 Replies
View Related
Oct 14, 2013
I am trying to create a booking calculation sheet for facilities. I want it to create something like a quote for customers. So when booking facilities, the hourly rate changes after 6pm. What I want to do is to put in a start time and a finish time and it calculate how many hours are before 6pm and charge them at $12 per hour, as well as how many hours after 6pm and charge them $18 per hour. I have tried a few things but they don't seem to work. I'm struggling with the logic of it really. This is mainly because the start time may or may not be before 6pm, as too the finish time.
View 6 Replies
View Related
Apr 30, 2014
calculating project completion % based on Project start date and end dates .
View 5 Replies
View Related
Mar 12, 2009
i want to calculate the TAT between two times. the TAT target is <= 2 hours. i used the following formula
a1 has 3/13/2009 (received date)
b1 has 7:08 AM (received time)
c1 has 3/13/2009 (completed date)
d1 has 9:08 AM (completed time)
e1 has TAT formula :- '=IF((D1-B1)*1440<=120,"Met TAT","Not Met TAT")
however this formula does not work in the following conditions.
In these conditions, it is considered that TAT is met.
1. When the difference in time is <=2 hours .... for TAT calculation, on working days and working hours are taken into consideration.
To illustrate.
Day begins : 8:00 AM
Day ends : 4:00 PM
If job is received at 3:30 PM and completed the next working day by 9:30 AM, then it is considered TAT is met.
calculation = 4:00 PM - 3:30 PM = half hour + next day's 9:30 AM - 8:00 AM = 1.5 hours, therefore, total working hours used to complete the job is within the agreed TAT.
If job is received and completed on non working days and during non working hours, it is considered TAT met.
If job is received almost at the end of the day, say, 3.30 PM and job is completed at 8:00 PM same day, then it is considered TAT met, rationale, only half an hour of working hours used to complete the job.
View 11 Replies
View Related
Nov 11, 2013
I need to calculate the amount of time it takes to pick up a document whilst taking into account:
- If the document was submitted before 9am or after 5pm, I need the pick up time to count from only 9am
- If the document was submitted on a different date to the pick up date, I need to factor in the days inbetween into the calculation (eg, if the document was submitted on 1st Jan at 9am, but wasn't picked up until 10am on 3rd Jan, the time to pick up would be 17 hours in total)
- If the document was picked up outside of the SLA hours, I only need to count up to the SLA starting/ending (eg, if something was submitted at 4.50pm and picked up at 8am the next day, the pick up time would be 10mins)
I've tried multiple ways of doing this and as soon as I think I have it cracked, I get an error. Below is a sample of the table I am working with:
Submit date
Submit time
Pick up date
Pick up time
Time to pick up
3/11/13
09:50:42
5/11/13
12:03:14
??????
6/11/13
11:13:54
6/11/13
14:14:31
?????
View 4 Replies
View Related
Sep 25, 2006
i need to get a formula that will calucate hours and min. its for how many hours the employee has not worked. some of them would be strait hours some would be just min there is no way to tell.
example
lates 2 hours
anp(absent no pay) 12 hours
sicks 55.5 hours
no calls
early outs 21 min
(this is just an example if it were real this person would be fired)
i know this adds up to 69.85 hours but i can't fuiger out a way to get it to calucate in excel. i know i could have it all changed to min and then devied by 60 to get the hours but how do i get it to read what is mins and whats hours?
View 7 Replies
View Related
Aug 10, 2009
I need to calculate the difference between a start time and end time in hours and minutes.
Start
01/07/2008 11:40
End
01/08/2008 19:28
Start and End columns are formatted as 'Custom' m/d/yyyy h:mm.
I'm not sure what formula to write to calculate the hours and minutes between the two times. Everything I've tried doesn't count over 24 hours. Also what do I format the result cell as?
View 3 Replies
View Related
Aug 21, 2013
It will be easier to explain in an example:
A B
Time (hh:mm:ss) Digital
1 10:03:00 0
2 10:03:01 0
3 10:03:02 1
4 10:03:03 1
5 10:03:04 1
6 10:03:05 0
[code]....
From the data above I am searching for the duration of when the digital column says '1', i.e my function = A5-A3 which would output 2 secs or 00:00:03 & likewise A9-A8.
The problem I have is that the digital signal is staggered and does not always have the same frequency. I have over 6848 lines of time to check so to do this manually would take me all day.
View 8 Replies
View Related
Sep 20, 2013
I'm currently working on a rota for which I would like the worksheet to automatically tell me how many staff members I have beginning their shift before 9am and those finishing after 7pm. I currently have this working via a very crude set of IF statements for each staff member for each day of the week, returning 1 if true and 0 if false. Then I have a sum statement at the bottom of each day. Is there a much tidier and simpler way for me to calculate this?
I've attached the worksheet. A quick note is in Q52.
View 3 Replies
View Related
Sep 16, 2009
B2: =SUMPRODUCT(--(INT('Order Entry'!$B$2:$B$37)=Summary!$A2) )
C2: =SUMPRODUCT( (INT('Order Entry'!$B$2:$B$37)=Summary!$A2) * 'Order Entry'!$A$2:$A$37) / Summary!B2
D2: =MIN(IF(INT('Order Entry'!$B$2:$B$37)=Summary!$A2, 'Order Entry'!$A$2:$A$37))
E2: =MAX(IF(INT('Order Entry'!$B$2:$B$37)=Summary!$A2, 'Order Entry'!$A$2:$A$37))
The overall picture is an order tracking sheet that has start times in column B, end times in column C, number of jobs in an order number in column D and the processing time in column A. On the Summary sheet I have dates listed for each workday.
Next to these dates I am wanting a formula that will traverse through column B of the Custom and Order Entry sheets and provide the number of orders and average processing time that match this. There can be multiple jobs per order number so it needs to order the Sumproduct by column D for each.
View 4 Replies
View Related
Feb 22, 2010
I have a number of processes that I would like to calculate the finish times of.
For example, Process A may take 18 hours to complete, Process B may take 28 hours to complete and Process C may take 125 hours to complete etc
However these processes only run during certain times, i.e. 9am to 5pm.
Ideally I would like to setup a spreadsheet that when given the start time and process time calculates the (date and) time the process will finish.
I can get it to work on a 24 hour day but I've been tearing my hair out trying to take out the none-working part of the day (the 5pm to 9am).
View 9 Replies
View Related
Feb 12, 2014
I am trying to come up with a formula that calculates total time someone has worked in a day. The scenario is an individual will work at a home and start working with an individual. Their start/end times look like this in a pivot:
Min Start Max Start Min End Max End
Location A+Counselor A 8:56 AM4:01 PM 1:11 PM 7:00 PM
Location A+Counselor B 12:00 AM 8:00 PM 6:00 AM 11:59 PM
Location B:Counselor C 7:00 AM 12:00 PM 2:00 PM 4:00 PM
Location C+Counselor D 8:00 AM 8:00 AM 4:00 PM 4:00 PM
Some people work split shifts while others work a straight shift. The formula I created was this:
=IF(OR(B9=C9,E9=D9,D9=C9),E9-B9,IF(D9>C9,((E9-D9)+(C9-B9)),IF(C9>D9,((D9-B9)+E9-C9),"New Formula Needed")))*24
(I use a pivot table to show max min for start and end times)
This works great except for the individuals that have multiple punches during the same time frame. The one scenario I am having trouble solving for is when someone punches in more than once during their shift displaying. This occurs when a counselor starts a shift working with one person but then adds another person mid shift. An example of this could be:
Location A+Counselor E Min Start Max Start Min End Max End
Consumer 1 1:00 PM 1:00 PM 8:30 PM 8:30 PM Total Time: 7.5
Consumer 2 12:00 PM 12:00 PM 2:35 PM 2:35 Pm Total Time: 2.6
Pivot says that they worked a total of 10.1 because it is grabbing the max and mins and calculating. The actual total time worked is 8.5 hours in reality.
The raw data comes in like so:
Location Counselor Consumer Start Time End Time
A A A 1:00 PM 8:30 PM
A A B 12:00 PM 2:35 PM
A A C 12:00 PM 5:00 PM
Is this solvable with a formula?
View 1 Replies
View Related
Apr 18, 2013
Calculating Lead time (in hours) between two dates/times, excluding holidays and weekend
Start Time
End Time
Lead Time
12/26/2012 15:50
1/2/2013 12:38:00
??????????
View 4 Replies
View Related
Feb 23, 2010
In my workbook I have about 20 sheets (less in the attached sample), and on most sheets I’d like to query data for each day and find an average value based on the time and then copy that result into another sheet. I’m not sure if I’ll need 2 macro’s for this or if one can be used.
Here’s a quick description:
Assuming that I am currently in the sheet I want to run the macro, then I will either input “1:45” or “0:45” into a popup box, or I could always simply input the 1:45 or 0:45 in the code itself. I’m flexible
1:45:
If I input 1:45, then I’d like the macro to find the first 1:45 in Column B and the value in the same row in Column F will be used in the calculation. Once 1:45 is located, then the macro moves up to find 22:45 in Column B and the value in the same row in Column F will be used in the calculation.....
View 11 Replies
View Related
Apr 8, 2014
I'm looking for a formula that will calculate the difference in times between specific times while working with a 24 hr clock. Please see details below:
E3 provides the start time of 4:00
H3 provides an end time of 15:30
If an employee works betwen the hours of 0:00 (midnight) to 5:59, this is considered DIFF hours and is therefore the number I am seaking. So for the data noted above, the total DIFF hours worked is 2 hours.
View 7 Replies
View Related
Mar 7, 2009
I need a formula in excel to convert start times and end times and minus out lunch time taken and then give total hours worked. For instance,
Column D Column E Column F Column G
Start End Lunch Total Hours Worked
10:01AM 7:08PM 1:01 (formula to convert hours worked)
View 9 Replies
View Related
Sep 15, 2006
I thought I found a formula that would work, but it's not working. Each month I have to count the number of service tickets that have arrived between certain time ranges. They want to gauge during what times we seem to get the biggest batch of service requests.
6 am to 10 am
10 am to 5 pm
5 pm to 6 pm
6 pm to 6 am
The format of the cells are:
1:21:19 AM
1:28:08 AM
1:35:48 AM
1:49:19 AM
2:17:02 AM
7:14:38 AM
7:29:12 AM
8:08:28 AM
8:51:48 AM
8:54:19 AM
The formula I tried for 10 am to 5 pm: =COUNTIF(B2:B677,">="&TIME(10,0,0))-COUNTIF(B2:B677,">"&TIME(17,0,0))
It gives a result of 676, and I know from manually counting that there is only 327 cells that have a time between 10 am and 5 pm.
View 3 Replies
View Related
Jul 12, 2007
I included a spreadsheet that lays out what I am looking to do, basically I copied some times and speed from net. It shows up in non 24 hour format. I need to find the times and an associated speed for each row (day) directly before and after my inputted desired time. I've searched for days, tried different formulas with index,match, lookups,timevalue, time, etc and even tried using other peoples vba code without success.
View 9 Replies
View Related
Sep 28, 2007
i need to calculate between time. If a person is working between 8 till 12 and then 1 till 5 i need to count the instances between these times.. so if somebody is working between these hours a 1 should appear and if they have finished their shift or are on lunch then this should change to 0
e.g.
8.00 | 8.30 etc.. 12.30 | 13:00
1 | 1 | 0 | 1
View 9 Replies
View Related
Nov 4, 2009
im running a new bar in Leeds and im trying to create a spreadsheet which will tell me how much to charge per drink to gain a 80% GP on products, ive got as far as listing the products and prices and calculating how much every measure (25ml) will cost. In the past ive used formulas where I can input the price i charge and it will calculate the GP (=SUM(D10/E10)*100-100) for example but id like to be able to type in the GP I want and for it to tell me the price i need, im not sure if tis possible but it will be a massive time saver.
View 9 Replies
View Related
Mar 17, 2009
I have some activities that needs to be done ina specified time
Like for example
TAT HRShrsACT 14ACT 28ACT 324ACT 42ACT 54
And i have a sheet where in i need to calculate turn around time
ActivityStart timeEnd timeTATACT 1ACT 2ACT 3ACT 4ACT 5
Based on time entered in start time and end time the TAT column should calculate the TAT based on the above standards.
I also would liuke to exclude weekends(Saturday, sunday). Also the TAT should only be calculated during working hrs between 7:30 PM to 4:30 AM.
View 9 Replies
View Related
Jul 10, 2009
Have a spreadsheet i need to add together a large array of durations which are recorded in hours minutes and seconds. They are all formated like 0:00:00 and will likely run over a 24 hour period. Adding two of these together is fine but when i try and add multiple using =(A1:A5) the result returned is always 0:00:00. I have tried formatting them as both general, and time in format H:MM:SS. Have also tried doing a pivot table changing the field options to SUM of call duration. Screenshot attach with column is question i'm trying to sum.
View 5 Replies
View Related
Mar 30, 2009
I have a bunch of recordings on my DVR. So I put the titles and description onto a spreadsheet each in their own column. Then I created a "length of time" column. So why, in this attached spreadsheet, does the "grape" total autosum all the rows in that column correctly but the "cherry" total does not total it's column correctly?
I looked at the format of all cells in both columns and they are both set at h:mm.
View 5 Replies
View Related
Oct 25, 2007
I'm trying to make a worksheet where I can calculate the cost of a mobile postpaid subscription. It is charged per minute and the cost differs depending on which of the 2 available networks the customer is calling to. The first 20 minutes are free, not depending on network.
Edit:
Charges to network A is 1,79,- per minute after the first 20 minutes are spent.
Charges to network B is 2,29,- per minute after the first 20 minutes are spent.
To sum up:
1. The customer makes a call.
2. If there there are available free minutes, these should be spent first.
3. The customer is charged per minute, depending on network called.
View 14 Replies
View Related
Mar 1, 2008
I am on an auto show board and want to come up with a way of calculating the ballots that come in, using excel. Ballot points are accrued as follows: 5 points for 1st place, 3 points for 2nd place, 1 point for 3rd place. With about 25 different categories (classes) and I am estimating participants at around 100.where I can in the automotive field knowing there is nothing besides personal gain.
View 12 Replies
View Related
Nov 9, 2008
I am having a problem with some of the cells in a spreadsheet not calculating.
For example, in column A, all the cells have formulas that pull data from another sheet. When I enter the formula, only the formula shows (not the result). I can't figure out what is wrong as the formulas in column B work fine (the results are showing, but not using the same data that column A is).
I am thinking it may have something to do with the data being used to calculate the formulas but not sure. How can I resolve this?
View 7 Replies
View Related
Dec 5, 2008
For my Intro to Engineering class, I collected data of two filter media in the laboratory. The data included the % of the media which passed through a sieve and the sieve openings. For use in a certain equation, I need the opening size at the 10th, 30th, 50th, 70th and 90th percentiles. I've tried searching on the Microsoft website but I don't think the PERCENTILE function will work correctly with the given data. I also tried using the slope between points to find the opening sizes at the percentiles mentioned, but doing so yielded different results from my professor's. Attached is the data I collected organized in tables and graphs of the data. I have also attached a pdf file of an example which my professor has given us.
View 5 Replies
View Related