Downtime Tracking Between Multiple Days Only Counting Working Hours?
Jan 29, 2014
I have a downtime tracking spreadsheet that we want to be able to track the downtime on the line. However, we only want to count the working hours, not overnight, etc. I have added the weekend day work hours and Saturday work hours but haven't been able to figure out how to connect them into a formula with the down time.
View 1 Replies
ADVERTISEMENT
Mar 2, 2010
The below formulae allows me to see the difference between two dates and only returns the difference in working hours ie :
Difference between
02/02/2010 08:00 & 03/02/2010 08:00 is 16 Hours 0 Minutes
=(INT(A3)-INT(C6))+MAX(MOD(A3,1)-MAX(MOD(C6,1)))
The following displays it in the Hrs and Mins format
=TEXT(B15,"[h]")&" Hour"&IF(OR(TEXT(B15,"[h]")+0=0,TEXT(B15,"[h]")+0>1),"s "," ")&MINUTE(B15)&" Minute"&IF(MINUTE(B15)1,"s ",""))
View 9 Replies
View Related
Dec 29, 2013
I'm having difficulty to calculate hours between 2 or 3 days exclude non working hours.
Attached is the example of start date with time & end date with time.
The situation is like "when the case log in till the case assist in working hours." so i will get the hours from case log to case assist.
Testing.xlsx‎
View 8 Replies
View Related
May 28, 2008
I have a questions about counting days and hours.
Imagine that i have an item entering my warehouse on 22/05/2008 at 21h35 and leaving on the 25/05/2008 at 5h42.
A1= 22/05/2008 and B1= 21h35
A2= 25/05/2008 and B2= 5h42
The goal is to count the full 24 hours day and the remaining hours.
For the example given i can say that on day 22 the item only says 2 hours and 25 minutes, on day 23 it stays 24 hours and on day 24 another 24 hours, on day 25 the item leaves at 5h42, so it only stays those 5h42.
So we have 2 full 24 hour days and 2h25 plus the 5h42, the the item were stored 2 days and 8 hours and 7 minutes.
The problem is when the item arrives at (example) 22/05/2008 2h00 and leaves at 25/05/2008 23h00 on another day. Lets say that on the first day the item is 22 hours stored, plus the 2 full 24 hour day and another 23 hours.
So it is 2 days plus the 45 hours, that is 2 days plus 1 day and the remaining 21 hours.
how to add to this 2 full days the 1 day and 21 hours
View 14 Replies
View Related
Aug 15, 2010
how can i calcaulate working hours between two days.
Working Hours 07:30 - 14:30
e.g. mm/dd/yyyy
start time 01/04/2010 17:34:58
stop time 01/05/2010 08:23:35
View 9 Replies
View Related
Jan 1, 2009
I'm using Excel 2003, and successfully working out start date (T2 in the formula below) plus duration in days (U2) minus any non-working days listed in a seperate worksheet. =WORKDAY(T2,U2,Holidays!C6:C17)
Each 'task' is on a seperate row, and the lead officer is named in Column E. How can I get the work day function to include the non-working days for each officer as well as the global non-working days in the seperate worksheet? I thought about using a vlookup, but that only matches the first non-working day for each officer rather than all of the non-working days.
View 2 Replies
View Related
Mar 31, 2014
I work in a HR department and I'm trying to create a spreadsheet to track the amount of extra-duty hours each worker has. For every extra hour they work today, they can use this hour next time.
Screen Shot 2014-03-31 at 9.25.22 pm.png
This is my current spreadsheetCredit hours means hours added to their 'account'.Debit means hours taken out.Hours will expire in X days if not utilised.Right now, each worker has their own spreadsheet in the same workbook.I have about 25 workers.Is this the best way to manage this?How can I create a 'bank account' system to track their hours?
hourstracking.xlsx
View 1 Replies
View Related
Mar 19, 2007
i work dispatch at a company and we're trying to track how long it takes for a technician to arrive on-site. my worksheet currently includes the date of call-in (E1) , time of call-in (F1), Service Date (G1), Service Time (H1), among many other field. the easy solution is to use the formula (G1+H1)-(E1+F1), and use the answer as the total amount of time, but the problem is if a customer call in at 3:00 PM and we service them at 9:00 AM the following day, it looks like it took 18 hours to arrive on-site, when in reality, since we close at 5:00 PM and open at 9:00 AM, we only took 2 hours to arrive on-site. is there any formula i can write to account for non-business hours and weekends, or is this a bit above what i should expect from excel?
View 12 Replies
View Related
May 5, 2014
Phasing Design.xlsx
We have a requirement to spread/phase amounts over multiple columns (representing months) using a weighting (represents working days per month).
We will calculate the weighting result in excel first (represented by a % per month), so the macro will be more of an allocation of row amount against the equivalent column %.
So far i have the following code:
VB:
Sub phasing()
Dim SourceA As Range
Dim Weight_ResA As Range
Dim TargA As Range
Dim i As Long
[Code] .....
View 2 Replies
View Related
Aug 30, 2007
1) The output of an excel duration is : 22.00:8.00:25.00 ( day:hour:minutes ) - excel cannot average and work with this number format
2) resolution - =(LEFT(L2,4))+MID(L2, FIND(":",L2)+1,4)/24+MID(L2, FIND(":",L2,7)+1,4)/1440 as an array and Custom Format the cell as [h]:mm - works perfectly.
Q: to be conistent, the initial reporting is dd:hh:mm and then I convert to hh:mm so that excel can process the data. How can I convert from hh:mm to dd:hh:mm so that the excel report can be consistent in presenting the data to senior management?
example attached.
View 9 Replies
View Related
Sep 1, 2007
I'm basically looking for a forumla that will count each employees total scheduled work days for the month inserted and then depening upon the day it is will show how many days the employee has left to work for the month.
View 9 Replies
View Related
Jul 31, 2014
I've got the below so far, but where it says V2>=(Q2+5) , I would like it to add 5 working days instead, is this possible?
Code:
=IF(AND(T2="Awaiting",V2>=(Q2+5)),"Overdue","Raised within 5 Days")
It would also be great if there is a way to say that if T2="Not Required, then put "Not Required" in W2 (where the IF statement is)
View 4 Replies
View Related
Dec 12, 2008
I have a spreadsheet where I record individual staff start time, end times and the length of their break. From this I caculate the hours they worked for the day.
E holds Start, F holds End and G holds Break length. Thus using the following forumula gives me the number of hours and minutes:
View 4 Replies
View Related
Feb 5, 2013
I am trying to figure out the calculation of cycle time from my worksheet. I have 1419 hrs equals 59 days 03 hrs.
If A2=1419
I tried this formula
=INT(A2/24)&" days " &MOD(A2,24)&" hrs"
Which gave me an answer of 59 days 3 hrs.
I was wondering how they got "03 hrs"?
View 9 Replies
View Related
Sep 23, 2008
Does any know how I can convert 29.18:20:18 to total minutes?
View 7 Replies
View Related
Oct 23, 2008
I can’t figure out why this formula is not working. I am trying to alter it a little, but I still think it should work. Here is what I am trying to do. I am looking to calculate the time difference between two work projects, but exclude time when the office is closed. So someone starts a project at 2pm and finish 10am the next day it will show a result of 4 hours because the office closes at 5.
Here is the formula. It is the time formula from cpearson.com ...
View 6 Replies
View Related
May 29, 2014
In attached file I need doing sum where total working hours are not showing correct.
TotalingTime.xlsx‎
View 14 Replies
View Related
Jul 2, 2009
I'm hoping someone here might be able to help me please?
I am trying to write a function that will convert a number into days-hours-minutes. I have managed to get as far as hours-minutes using the following function.
=INT(A1/60)&"h "&ROUND(MOD(A1/60,1)*60,0)&"m"
e.g. If A1 = "7090" the result of this function will be "118h 10m".
I now need to express the result as xxxd xxxh xxxm and this is where I am stuck!
View 5 Replies
View Related
Dec 24, 2012
Where i want add Business Hours/Days to get the Target Date.
Working hours: 8:00 AM to 19:00 PM
Urgency Type:
ND (Maximum 1 Day 11 hours)
3D (Maximum 3 Day 11 hours)
4D (Maximum 4 Day 11 hours)
5D (Maximum 5 Day 11 hours)
Threshhold - 16:30 PM
Weekends to be Excluded.
Holidays to be Excluded based on Country. Say I have 2 countries India and America, where America has holiday on 12/24/2012 but India does not have holiday on that Day. Hence while calculating Tgt date, India should be calculated normally, for America holiday date need to excluded(There will be a Holiday table based on the countries, not limited to 2 countries).
ex: 1) A ticket opened at 12/26/2012 8:56 AM; Target date will be 12/26/2012 19:00, in this case its 1 day 10:04 hours added to the Opened Time.
2) A ticket opened at 12/26/2012 16:56 PM; Target date will be 12/29/2012 19:00, in this case ticket opened after threshold time of 16:30, Technically ticket should start from next day i.e 12/28/2012 8:00 AM and 1 day 11 hours added to this date.
3) A ticket opened at 12/26/2012 7:56 AM(Before the begin of Working hours); Target date will be 12/26/2012 19:00, in this case its 1 day 11:00 hours added to the Opened Time.
4) A ticket opened at 12/21/2012 17:56 PM(After Threshold time); Target date will be 12/24/2012 19:00, in this case its 1 day 11:00 hours added to the Opened Time. If the above ticket belonged to America, then holiday dates(both 24 & 25) need to be skipped and Tgt date will be 12/27/2012 19:00.
Here is the Sample Data
Country
Ticket
Start Date/ Time
Tgt Date/Time
Expected Tgt Date/ Time
America
ID000123
12/21/2012 18:20
[code]....
I need results to be appear in the "Tgt Date/Time" column. I have also provided results in "Expected Tgt Date/ Time".
View 1 Replies
View Related
Aug 12, 2013
I have a formula that returns me a result in hours. I have a result of 1712 hours but when i try and formatt the cell to show days is says 11. (Which obviosuly isnt right)
Is there anyway to show the correct number of days?
View 2 Replies
View Related
May 11, 2014
Is there a way to calculate how many days and hours there are in a date range IE 5/11/2014 to 10/31/2014 = days and hours
View 2 Replies
View Related
Nov 13, 2006
I am trying to add duration time for song files. 4 minutes and 32 seconds + 3 minutes 45 seconds, etc. etc. to get total hours and then to total to days. The range of cells is over 5,000 and I am trying to find out how long a playlist will play.
View 9 Replies
View Related
Apr 7, 2008
I am creating a 'HelpDesk Issue Logger' and I am trying to calculate the Network Days and Network Hours between two dates with times. I want to know how many business days and hours are between the two days to give me a TURE 'Response Time.'
I have been to several sites and forums looking for the answer, but I have not been able to find a solutions that works for me. Please find attached a 'stripped' down version of my project.
Variables:
- 'Date Received' (H11)
- 'Date Actioned.' (I11)
-'Response Time' (K11)
Constants:
Work Days = Monday to Friday
Work Hrs = 8:30 AM to 5:30 PM (no lunch break)
Public Holidays = (AC13:AC30)
Formats:
Date Received: dd/mm/yyyy hh:mm AM/PM
Date Actioned: dd/mm/yyyy hh:mm AM/PM
Response Time: d - hh:mm
If there is someone out there wiling to put me out of my missery with this one, you will have a friend for life.
View 9 Replies
View Related
Oct 15, 2009
When people enter their hours I get them to do it in 24hr format, fine. BUT my problem is coming when I'm working out wages etc. I can get the user to enter 09:00 (start time) and 17:30 (end time) but then the cell works out the hours (cell 2-cell1) gives 8.30 in time format when I need it to show 8.5 (total hours worked)
This means when it goes to work out wages, it takes 8.5*hourly rate not 8.3!!
View 2 Replies
View Related
Mar 13, 2008
I am working in call center, and I get tickets and i have to meet my Services Level Agreement (SLA) with in pre defined working hours.
My working hours are 8:00 AM to 17:00 PM, Monday to Friday. (this includes 1 hour of Lunch time which is not considered as business hour)
As per the SLA, i have to complete the ticket in 40 business hours, i.e 5 business days.
Suppose a ticket is created on 3/5/2008 10:00 AM. I want to know how much time is left for me to work on that particular ticket.
View 12 Replies
View Related
Aug 5, 2014
I am measuring total time accumulated over a week using hh:mm format. Once I pass over the 24 marker then the format changes. How can I keep this to hours only?
View 3 Replies
View Related
Nov 25, 2009
i had a sheet with the employee name,Working Place, Designation,Starting Time & Ending Time of each employee working in a Department. I want to track the no of hours each employee worked in the Format 1 Hr: 45 Mins .
i tried to get the result by substracting the ending time from starting time and then formatted the cells using the TIME FORMAT from the FORMAT Menu>Format Cells > TIME. But i m not getting the required result. I want a vba code or formula for extracting the no of Hrs & Mins the employee worked using the above formula.
View 14 Replies
View Related
Dec 18, 2009
I want to write a macro to add business hours to a datetime value, excluding weekends, non-working hours and holidays.
e.g., I have a value (datetime) of "18/12/2009 11:30:00 AM", I want to add 10 hours to this, so as to get the result as "19/12/2009 12:30:00 PM".
View 7 Replies
View Related
Jan 31, 2008
I have a spreadsheet that calculates the total working hours of our warehouse staff, overtime, etc... using some good advice that has been published here before.
Cell C1 : starting hour
Cell D1 : ending hour
The hours are filled in, using 1904 system, without date as 08:00, 12:00, 21:00, etc... total hours is calculated as follows:
=(D1-C1+(D1
View 9 Replies
View Related
Mar 3, 2008
I have a spreadsheet with various date fields and next to those time fields. I need to calculate the amount of working hours between the 2 lots of values
for example
Cell A has "22/02/2008"
Cell B has "16:44:00"
Cell J has "25/02/2008"
Cell K has "08:59:00"
The answer i'm looking for is 01:29:00. The working hours are Monday to Friday 07:30 - 16:00. This is what I have so far and it gives me the total hours between the 2 dates but not the working hours. =IF(J10-A10=0,K10-B10,((J10-A10)+(K10-B10))) (Formatted with [h]:mm:ss). I have tried using workingday() but can't get the desired result
View 5 Replies