How To Use Vlookup To Calculate The Number Of Shift Per Week For Each Agent
Dec 19, 2013I would like to use vlookup to calculate the number of shift per week for each agent
View 10 RepliesI would like to use vlookup to calculate the number of shift per week for each agent
View 10 Repliescalculating the number of calls logged in a shift, based on a 3 shift system in a day. shift 1 from 08h00 to 16h00, shift 2 16h00 to 24h00, and shift 3 00h00 to 08h00. each shift receives a number of calls based on the time the call was submitted.
View 2 Replies View Relatedhow would I calculate the number of hours in a shift after midnight. What I want to say is that the number of hours after midnight on a friday shift to be taken off from friday total hours and added to a saturday shift.
How can I shift the range of cells I want to calculate an average from? For example I want to get the average of cells A1 to A10, so =AVERAGE(A1:A10) And next I want to get the average of cells A11 to A20, so =AVERAGE(A11:A20). But I don't want to manually change the data or delete rows all the time.Is it possible to do something like: =average(A1+10:A10+10)??
View 4 Replies View RelatedI have the basics set up, but need to work out how to make it calculate my pay per shift dependant on the type of shift i have worked.
I have attached a screen shot of the current page,
In it i have currently used validation drop boxes for the location and worked columns with tables just to one side of the sheet.
The shift pay is the column i am having trouble with.
I would like it to change dependant on what is selected in the 'worked' column.
For most things it should just display basic plus holiday, however if supervisor is selcted in the work column, it should display basic plus holiday plus supervisor.
a person works for certain hours and get paid according to the hours worked either by day or by night or a mix of both. Day payment is $8 when worked between 08:00 and 19:59 , night payment is $12 when worked between 20:00 and 07:59. The excel cell are formatted as datetime with yyyy-mm-dd hh:mm , the function works fine in getting the time information and checking whether the whole work is all day or all night , yet the if-then-else statements for calculation seems to be wrong!!
examples:
start = 2008-01-01 09:15 , end = 2008-01-01 11:40 , all day as it is between 08:00 and 20:00 and cost = 8/hr = 19.333
start = 2008-01-03 21:05 , end = 2008-01-04 02:05 , all night as it is between 20:00 and 08:00 and cost = 12/hr = 60.000
start = 2008-02-02 19:00 , end = 2008-02-02 20:05 , cost = 9.000 as 1 hour day = 8.000 plus 5minutes night = 1.000
Function prod(st As Date, en As Date) As Double
Dim shour As Integer
Dim smin As Integer
Dim ehour As Integer
Dim emin As Integer
Dim stod As String
Dim etod As String
pday = 8
pnight = 12
shour = Hour(st)
smin = Minute(st) + shour * 60
If (shour >= 8 & shour < 20) Then
stod = "day"
Else
stod = "night"
End If
ehour = Hour(en)
emin = Minute(en) + ehour * 60
If (ehour >= 8 & ehour < 20) Then.................
Daily i import sheets into excel and the sheet name is uniformed to the following
20061017_BNKREC - 20061018_BNKREC - 20061019_BNKREC ..........
just for clarity purposes
[2006] = year, [10] = month, [17] = previous day, [_BNKREC] = report type
I'll be creating a graph to which shows account balance by week, by account.
The data will be coming in daily. i know i will need to create either a dynamic range or copy my data into a new sheet. My head is spinning because i need excel to somehow (either in a formula or VB) determine what WorkingWeek the sheet is in. I dont want to have to keep adjusting formulae or ranges when import a new sheet..
bare with me here as its hard to explain ................
I have two processes that has to run depending of the week number of the year. So even weeks has to run "sub 2" and odd weeks has to run "sub 1".
Weeks with number 1,3,5,7,9,11,13,15 etc has to call "sub 1" and weeks 2,4,6,8,10,12,14,16 etc has to call "sub 2".
The filenames consist of "name_name_YYYYMMDD.xls" (example: SteveSmith_Runningshoes_20140719.xls)
So vba needs to calculate the week number by reading the YYYYMMDD of the filename and then call the correct sub.
Any example of counting the # weeks/days between two dates?
View 1 Replies View RelatedI have a drop down box that chooses the week number of the year (This is based off of a series of data from another sheet).
I need some kind of formula that calculates the following Friday based on a week number. Say for this year (2012) The following Friday for "week 1" is 1/13/12.
(This is for payroll information and I'm trying to calculate the pay date based of of data from that week)
Of the 52 weeks in a year, I want to know the week number that a date falls in, e.g. date - 05/08/2013 falls in Week No. 32. What's the formula to get this answer?
View 2 Replies View RelatedMy spreadsheet is set up so that Column A has dates and Column B has a value. How can I calculate the total number of values for each day of the week? I've tried a few formulas but they either didn't work or didn't actually take the value into consideration and just counted all the 'Mondays'. I'm not sure if that's clear enough, but if we're just looking at Mondays to simplify it:
Monday, 1 January 2000: 2
Monday, 8 January 2000: 5
Monday, 15 January 2000: 0
Mondays: 7
I would like to calculate the week number of the month based on a date.
Now my days would only include working weeks (Monday - Friday).
Supposed the date is 12/31/2012:
M
31-Dec
T
1-Jan
W
2-Jan
TH
3-Jan
F
4-Jan
Since it only occupies 1 day of the workweek, then it will be considered as Week 1 of January. If the date is 1/28/2012:
M
28-Jan
T
29-Jan
W
30-Jan
TH
31-Jan
F
1-Feb
It will be considered as Week 5 of January since it occupies 4 days of the working week. If the date is 4/29/2013:
M
29-Apr
T
30-Apr
W
1-May
TH
2-May
F
3-May
It will be considered as Week 1 of May since it occupies only 2 days of the working week.
Basically if the date's month occupies 3 or more of the working days of the workweek then it will be considered as part of that month's working week. Is this possible with formulas? I tried to explain it the best I can.
I have a running time sheet daily. It has 2 columns for Labor and 2 columns for travel
i.e. travel From / To 1300-1400 calculate 1 hour then travel home 1600-1700 1 hour this is calculated by the date entry 01/02/10 I have another calculation that tracks by the date i.e. 01/02/10 then Next job which all works fine.
The problem becomes how do I calculate a weekly total labor and travel by the date So added another column called weekly hour’s labor and use the Weeknum to determine which week is which day/date so the first Monday in January 2010 is week 2
2 problems
Having many multiple day / date entries are the same date x 7 days Monday –Sunday
(Relies on the date entered and the weeknum) 01/03/10 each line is complete however the dates carry over as does the time
When trying to calculate each row x 3 same date time then the value will be incorrect I need to calculate
Say 9.5 hour labor from the date 01/03/10 not 28.5 hours and then calculate the total weekly hours
01/03/10, 9.5 hours labor, 3 hours travel
01/03/10, 9.5 hours labor, 3 hours travel
01/03/10, 9.5 hours labor, 3 hours travel
i do have work and travel times for each job on the same line (separate columns) but I display the total here by date to summarize the totals
i have tried sum products and sumif to avail. I am using Windows XP SP2 with MS Office 2007
how do i calculate weekly hours by date and weeknum ?
Total Work per day
Total Travel per day
Daily....................
I have a column where I am convering the Date into a Fiscal week number.
For example 10/6/2009 is Work week 41
Now I want to show October Week 41
I need to add the month and the text "Week" before the week number. what is the formula I use.
I have a series of data in different columns, one of them is the date (daily, for like 5 years, exept weekends and national holidays), but I want to make another table with weekly data (which should be the sum of the daily data in a week, for each column). I thought there might exist any combination of formulas for that, to put once and drag it, and maybe it's pretty obvious, but even though I thought about it a lot, I couldn't find the solution.
View 6 Replies View Relatedway to calculate the hours every one has done each week to make sure everyone has done the correct hours. I was about to start using a calculator and then realised it would take forever.
I've included a zip file of the excel file
I have two rows one with the nr of weeks and another with revenues like that:....
i need to calculate the cumulative sum without inserting another row in the week that i define like an input so it could be changed.. for example the *** sum in the week 5 shloud be 900.
I am creating a load file for software from Excel. Based on our planning calendar and delivery time, I need to calculate the Delivery day.
Excel File as follows:
Planned Delivery Time Planned Order Day Planned Delivery Day
8 days Thursday (Need a formula that says 8 days from Thursday would be Friday)
13 days Tuesday (Need a formula that says 13 days from Tuesday would be Monday)
I have attempted with simple formulas adding time, complex formulas, and cannot find a simple solution that works for days of the week.
to calculate no.s of workdays between two given dates,
1.We work 06 days a week (so only Sunday is OFF)
2.What if I have some holiday between the given dates + Sunday OFF
Need a solution for calcuate a week in user enterd date?
Example
A1 A2
07/01/2009 1
07/01/2009 5
On a excel sheet I've got columns, each column represents a weeknumber. I want to calculate the so-called 4 wk average for each row and for each week and this is the formula I use:
(value*Tvalue)+(value*Tvalue)+(value*Tvalue)+(value*Tvalue)/(Tvalue)
(this is not the actual formula but simplified, that's not really important).
It's the checks that make things a bit more complex. If a value of a weeknr is zero, skip it, but if the next value is also zero, just skip the formula alltogether and make it a zero (or text like "false"). So another thing that has to be accounted for is that if a value is zero, the next weeks value is taken instead.Example (see included file):
I want to calculate the formula (mov 4wk avg) for the third value for week 12, which will make the formula
(0.2*6)+(0.3*6) now there's a zero on week 14 so I skip it, then formula will be:
(0.2*6)+(0.3*6)+(0.6*6)+(0.9*6)/(6).
Right now I'm doing this in VBA with a lot of variables and a lot of if statements.Is there an easier more effective
I know the example sheet is a 2007/2010 version but I need to accomplish this for 2003.
Please refer to attached sheet.
I am using the attached to schedule the employees. All I want is a formula to add up all schedule hours per week per schedule in cell R2,R3 and R4.
Book2.xlsx‎
calculate overtime hours from daily time entries.
Normal hours are 7.6 per day
Time 1/2 is hours over 7.6 but no more than 2 hours
Double Time is all hours over that.
I have the spreadsheet with the days of the week in one row and at the end I have 1 cell for Normal Hours, Time 1/2 and Double Time. I need a formula that will work out overtime off each day and add for all days of the week and enter data into one cell. So all normal hours are in Normal hours and Time 1/2 and Double time are automatically calculated once hours are put in per day manually.
WedThurFriSatSunMonTuesTotal Normal HoursTime 1/2Double Time 10101068
I need to calculate the absolute week and have found a formula to do so. Is there a way to embed/execute this in VBA?
TRUNC(((StartDate-DATE(YEAR(StartDate),1,0))+6)/7) where StartDate is the date which you are trying to find the corresponding week number (for example Now().
In one column I'll have a list incrementing in 1w,2w,3w,1month and I want to be able to count the number of days that have elapsed till the latest cell. Right now I'm just winging it by saying there's always 31 days in one month using a COUNTA function, but I need it to be accurate.
View 9 Replies View RelatedI have a requirements to capture the data and calculate the qty based on the defined work week. How to to this in vba macro or a formulas. I'll giving a sample data as reference. In my sample data i have already the formulas
but i wanted to automate the work week calculation specially if the number of days in a month has been change.
Btw, the values of every column is came from other worksheet. i copy paste this data as my sample.
For ex : Today is July and it has 31 days, the 31 days will be distributed to the defined workweek and calculate the contents of the corresponding column.
here is the distribution of columns per week as reference.
(31 days)
wk1 - Day1 to Day8 (8 colums)
wk2 - Day9 to Day16 (8 colums)
wk3 - Day17 to Day24 (8)
wk4 - Day25 to day 31 (7) columns
(30 days)
wk1 - Day1 to Day8 (8 colums)
wk2 - Day9 to Day16 (8 colums)
wk3 - Day17 to Day23 (7)
wk4 - Day23 to day 30 (7) columns
1. Calculate the time that has elapsed between 2 times in both hours:min (hhmm) and total mins (mm)
2. Compute the day of the week (mon-fri) a particular date fell on. I really only need to know if the date fell on a weekday or weekend.
table { }td { padding: 0px; color: windowtext; font-size: 10pt; font-weight: 400; font-style: normal; text-decoration: none; font-family: Arial; vertical-align: bottom; border: medium none; white-space: nowrap; }.xl63 { font-size: 12pt; } 1= M-F
2=S-S
3. How to write an If statement that assign a value to time based off this chart:
table { }td { padding: 0px; color: windowtext; font-size: 10pt; font-weight: 400; font-style: normal; text-decoration: none; font-family: Arial; vertical-align: bottom; border: medium none; white-space: nowrap; }.xl63 { font-size: 12pt; } 1= AM (7-1459)
2=PM (15-2259)
3= MN (23-659)
I am trying to figure out a way to count the minutes used from 8am-5pm Monday-Friday. I have this years worth of data. I would like to do it by month and by week and by day. I use office 08 for the mac and its my understanding that it doesn't have VBA. I would also like to be able to figure out if on a certain date a employee made over x amount of phone calls in a day. But have several employees. I have columns that are labeled date, employee, minutes used.
View 2 Replies View RelatedI have a spreadsheet for tracking jobs. Most everything is based off of week # rather than date. I am trying to get the stats page of the workbook to tally the total number of late jobs per week.The current week is taken care of because there is a function that automatically displays on time yes or no and I just set it to count the yeses or nos.The problem I am having is for past weeks.
I tried- =COUNTIF(Table2[On-time],"No"+(CountIF(Table2[Week # Hidden],"<Weeknum(Now())" but that doesn't work. I also tried isolating the < like this. =COUNTIF(Table2[On-time],"No"+(CountIF(Table2[Week # Hidden],"<"Weeknum(Now()) and that did not work either.
------ UPDATE
In response to using CountIFS I have also tried-
=COUNTIFS(Table2[On-time],"NO",Table2[Due Week '# Hidden],"<Weeknum(Now())") this just returns a zero value even when I have a late job listed three weeks ago.